Weekly Report    (back)          (Home)   

Note : All information and details are updated on the website every week. 
Week 

Description of work done

8,9,10

         The evaluation of the various design e.g. the coupling and cohesion of system, user interface design, cost estimation calculation is now in progress. Meanwhile testing is carried out. The cyclomatic complexity is computed and the screen flow structure of the system is also included. The whole system will be ready by 23/03/2000 for demonstration.

 
7           The testing of the modules is still in progress and the design is also updated on the changes made. We set the target to start integration by week 8 so that whole system can be fully tested before demonstration.  
 
6           The deployment view of the system is done. At the same time, the first prototype is reviewed. The standardizations of the system is carried out and the next stage is to perform testing on each modules before the integration is performed. Refinement to the class diagrams and sequence diagrams are done.
 
5           Component and process view using the Rose is developed. Concurrently, the coding personnel have started to develop the first prototype especially the interface.  
 
4           The object diagram and class diagrams are created. The entity relationship and data structure diagram are developed for our actual database design to finalize the database. Feedbacks are obtained from the clients.  
 
3           Developing the sequence diagrams are finished. At the same time, a database template for the system is created to enable every individual to start trying  to use Visual Basic to manipulate it.
 
2          The familiarization of the tools especially the modeling tool like Rational Rose is carried out. Next, using the tools we need to generate the use case diagrams to describe the system. Basically the refining of the diagram is done constantly to meet the user's requirements. 
 

1

         We established our group and organized the roles of each individual and the team organisation. The main objective is to identify the project to handle as well as the software tools to use for development. Furthermore, we decided to use the object-oriented approach for our analysis and design. We had also plan a schedule to ensure completion of the project on time.  
 

 

 
Hosted by www.Geocities.ws

1