Key
Deployment experience in Spain
RadioNexo Services, a WLAN implementation
and support specialist, designed and installed the new system. The
large, complex deployment involved deploying and integrating the
network at one PorTel port site, including Cádiz warehouses,
and at PorTel Algeciras data centers.
Several
hurdles–including the constant movement of shipping containers
throughout the yard–were overcome to keep the project on time
and within budget. “That was probably our single biggest network
design challenge,” says David Durrif, RadioNexo senior network
consultant. “There are metal objects all over the yard–tractor
trailers, cranes, the shipping vessels and large shipping containers–and
radio signals bounce right off them.” Routinely, 10’x8’
containers are stacked four high by 20 deep, creating deep corridors
where network coverage is required but difficult to achieve.
The
legacy RF system was tested to find any coverage gaps. Surveying
tools such as the Aironet Client Manager, Cisco 802.11b Network
Analyzer and Web-based configuration tool, and the Aironet 4800
access point were used to measure network coverage, the strength
of the signal and the speed at which the data was processed based
on the consultants’ locations in the yard.
As
implementation challenges grew, an Aironet 4800 Bridge was used
by installing another directional antenna and creating a point-to-point
link to another access point This alleviated cost-prohibitive laying
of fiber in trenches. To achieve coverage in the deep corridors
between stacked containers, antennas were installed with enough
range to provide coverage at the bottom of the corridors and access
points were placed in strategic locations throughout the yard.
Integration
between the WLAN and existing backbone equipment and applications
had to be seamless. When an employee moved into an area covered
by a new access point, the original access point would continue
to relay data to the system. By the time the switch to the new access
point was made, the application had timed out and the server had
disconnected. To optimize the network’s performance, the timeout
settings were reconfigured, the spanning tree was enabled and support
was added for multiple MAC addresses for the hardware ports on the
switch, solving the problem of lost connections.
Thorough
testing made successful deployment complete in less than three months,
and already, there are returns on investment, increased efficiencies,
better service to customers and lower operational expenses.
For
more information from RadioNexo Services:
http://www.radionexo.com
|