With the shotcrete dry, on April 3 the deck crew arrives to lay out the forms.

The following day the concrete arrives and is carefully poured into the forms.

The concrete deck is smoothed and prepped for the application of the Kool Deck. (After their lead cleans out the plumbing which - oops! - they cemented over)

Finally, the tile is applied to the waterline and the face of the waterfall.

This is where we start to get nervous, as we've scheduled a party a little over a week away.

Will the pool be finished in time??