Drywall - The Interior Takes Shape! |
|
|
|
|
|
September 1st officially marks the beginning for the drywallers.....
Ron has been running around tucking insulation in every crack and crevice. He has foamed along the foundation and framing. We should have no drafts or cold spots in this house.
Okay! It took 17 weeks to frame the house, 4 weeks to wrap, and we are still waiting for the carpenters to finish the back porch......but the drywallers have decended and are setting a record breaking pace hanging the wall board!
In spite of several days of nasty wind...which blew the insulation out of the walls and down the street. And several days of rain.....the drywallers have made fast work of the downstairs walls.
If they keep up the speed - we just might make up a week or two that we lost during the framing.
First hanging the wall board....then taping and mudding - feels like progress. |
|
|
|
|
 |
|
|
|
|
|
 |
|
|
|
|
|
 |
|
|
|
|
|
|
 |
|
|
|
|
August 8th - drywall is delivered......it will be a bit until it gets installed. |
|
|
|
|
|
 |
|
|
|
|
|
|
The nephew Nick gets on the phone to Bob the Builder to make sure we are doing things right! |
|
|
|
|
|
 |
|
|
|
|
Margaret entering the living room from the entry hall. The dining room and great room are to her right. |
|
|
|
|
|
 |
|
|
|
|
|
|
Front entry looking down the hall to the great room and kitchen. The day is September 6th. |
|
|
|
|
|
 |
|
|
|
|
 |
|
|
|
|
|
Action shot of Nick - meanwhile Margaret and Ron compare clean-up injuries. They are standing in the butler's pantry. It is September 6th. |
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
Garden tub in master bedroom gets the green board treatment.....oh, I can't wait! |
|
|
|
|
|
 |
|
|
|
|
Kitchen - before we cleaned on Saturday. The arch in the back is the stove and the arch to the left is to the butler's pantry. |
|
|
|
|
|
 |
|
|
|
|
|
Laundry room and the cut-out for the built-in ironing board. The excercise room is through the doorway. |
|
|
|
|
|
|
Nick celebrates dry wall hanging in the master bedroom |
|
|
 |
|
|
|
|
|
|
 |
|
|
|
|
Great room looks good....after we mucked out all of the trash....the green board for the showers is ready to install. |
|
|
|
|
|
|
Finishing up the drywall and the lathe is being delivered.......next step wrapping the exterior of the house. |
|
|
|
|
|
 |
|
|
 |
|
|
 |
|
|
|
|
|
|