|
THE
RENUN HYDROELECTRIC POWER PLANT;
WILL
IT BE ANOTHER INDORAYON ?
THE
PERMISSION ON RENUN RIVER WATER USE;
A
QUESTION MARK STILL
Since
Soeharto stepped down from the presidency in 1998 and
the RI 1 position then taken over by B.J.
Habibie, many things changed so immediate. The
situation at PLN party, in fact, had changed, too.
Signed by the chiefs/directors of the project of Renun
HEPP were lobbying the authority officer to have
recommended permission concerning the project
construction and river water use.
From
the chronology order, the use and changes water
function for the project purpose did not follow the
appropriate regulation procedures in accordance with
Law.
PLN
just submitted any required recommendation on the
project construction after new order collapsed. But it
was not caused of PLN’s initiative, the submission
was appealed when the regional office of Public Works
Department in North Sumatra sent a letter dated July
15, 1999 to the Watering Public Works Division North
Sumatra office concerning the permission letter for
the project and another one in Central Tapanuli (Sipan
Sihaporas HEPP).
One
month later, it was August 11th, 1999, the
Chief of the project of Electrical Circuitry Power
Plant in North Sumatra, Dendi Ilyas Affandi sent a
letter to PLN Office in Jakarta. The point of the
letter was solicit request for help in obtaining the
recommendation on development river construction and
river water use of Renun and its tributaries.
It
was still in connection with the efforts to obtain the
permission, in the same month (August 1999), the
Minister of Mining and Energy, Kuntoro Mangkusubroto,
issued a letter addressed
to the Minister of Public Works (no date available on
the letter). He asked the Ministerial of Public Works
for an assistance. But if we observed the letter
briefly, the letter seemed to have been issued
invalidity.
Actually,
in accordance with Law No. 35, 1991, it is clearly
stated that “to take and use river water can only be
made if the permission has already been issued by the
competent department or related ministerial.
Meanwhile, the Renun HEPP had begun the project
construction without any of permission or legal
recommendation. The Government Law No. 35, 1991 was
broken by the project. Inside this Law is also
asserted that “it is prohibited all kind of
activities that
affect river condition changes like removing,
widening, narrowing, or closing the stream flow unless
permission is available.
The
project also broke the Government Law No. 35, 1991,
article 28, Government Law No. 22, 1982, article 16: 1
and article 23: 2. The sanctions of ignoring the
regulation are regulated by Government Law No. 35
article 33 based on Law No. 11, 1974, article 15.
Up
till today, according to PERJUANGAN Daily’s
trustworthy resources, Renun HEPP still has not had
the required permission with them or Renun HEPP, at
least, should have published their legality concerning
the project.
Acknowledgement;
The
article was copied from Saor Sihotang’s report of
PERJUANGAN Daily reporter
August
13, 2001
|