Log Reports
2/10/09
- Received new pneumatics
- Finalized lower deck design
- Received shipping crates from the shop
2/9/09
- Got supplies for bumpers
- Worked on upper deck
2/7/09
- Saturday workday
- Began bringing robot up to code
- Swapped out and reformatted electronics board again
2/4/09
- Electronics board swapped out—cut to small for the electronics system
- Holes drilled to streamline the board
2/2/09
- Due to new understanding of the rules, the design was modified
- Possible name: Space-Quake
1/31/09
- Saturday work day at school
- Continued work on upper deck
- Began autonomous programming
1/27/09
- Began construction of final upper deck design
- Programmed pneumatics into Labview
1/23/09
- Reviewed priorities
- Decided what components to add
1/22/09
- Finished construction of final base
1/17/09
- Saturday work day at school
- Began final design of base
1/14/09
- Disassembled the base
- Continue to model the actual design on inventor
- Prepared the batteries
- Worked with control station
1/13/09
- Finished temporary base, successfully controlled
- Completed air tank/gauge assembly
- Added auxiliary controls for program use
1/10/09
- Saturday workday at school
- Archived all design possibilities
- Continued construction of temporary base
1/8/09
- Successfully teleoperated control system
- Finished preliminary designs
1/7/09
- Started construction of temporary base
1/6/09
- Introduce ideas to entire team everyone brainstormed
- Jed looked over rules book
1/3/09
- Attended FIRST Kick-Off at St. Louis Science Center
- Retrieved kit of parts
- Took inventory of kit
- Began strategizing
12/23/08
- Printed copies of Labview FRC Programming manual and C/C++ Programming Manual from the FRC website
12/22/08
- 12 V motors added to control system test bed and controllable via joysticks
- 2nd Jaguar controller added to test setup
- Axis camera added to test bed (not yet tested)
12/20/08
- Firmware in NImC unit updated to FRC update #1 and set in labview mode.
- Control system tested and found to be operational with components installed on it
12/19/08
- Control system test bed completed
- Control system tested
- Firmware in Driver’s station updated
12/17/08
- Continued construction of control system test bed
- Copy of control system manual printed from FRC website
12/12/08
- Received FRC control system via early shipment (UPS)
- Inventoried components in shipment
- Began constructing control system test bed