DIGITEL Total Reallocation Project
Description
: Re-allocation of equipment for the roll-out of
Public Switched Telephone
Network for a total of 95,000 lines across Northern and
Southern Luzon Provinces
Project Duration
: 6 months (started early 1999. completed
mid 1999)
Project Team
: 50
Project Involvement
: Project Team Leader
Batangas
Host Exchange and Remote Exchange facilities I, II and II
Meycuayan
Host Exchange Facility
Talavera
Local Exchange Facility and Remote Exchange Facility
Hardware
: NEAX 61E/EV Digital Switching
Equipment (LARGE PBX Systems)
DIGITEL NX2 Priority 2 Switching Implementation
Project
Description
: Turn-key project for the roll-out of Public
Switched Telephone Network for a total of 200,000 lines
across Northern and Southern Luzon Provinces
Project Duration
: 2 years (started last quarter of 1997, completed
mid 1999)
Project Team
: 60
Project Involvement
: Project Team Leader
Ligao
Local Exchange facility
Naga
Host Exchange Facility and Pili Remote Exchange facility
Legaspi
Host Exchange Facility and Extended Line Units I, II and II
Virac
Local Exchange Facility
Hardware
: NEAX 61E/EV Digital Switching
Equipment (LARGE PBX Systems)
|