Before this particular addition could be started a load bearing header had to be installed spanning the garage.
Than a door and stairs were installed from the upstairs hallway to the space above the garage
Now it is time for the flooring and the framing. Along with the walls I framed out a closet. In that closet I installed two access hatches to either side of the attic for additional storage and easy access.
Finally the sheetrock was installed and finished smooth. During this project lighting and outlets were installed. The homeowner finished the room, painting and carpet to save money.