COORDINATING COMMITTEE FOR HORN OF AFRICA RELIEF


TECHNOLOGY TRANSFER - BRICK AND TILE PROJECT


FIRING TESTS

FURNACE
Several tests were used to fire clay brick using the furnace indicated below. Firewood was used in the first test. The amount needed to fire the brick to the required level was almost prohibitive. Raw coal, excavated from site more than150km away, was used in the second test. The firing test was a success but more research was needed to choose the right clay mixture.
 
Furnace - Floor Grill Furnace - Back View Furnace - Front View

WATER RESERVOIR
Other facilities include the Water Reservoir
The Water Reservoir is strategically located inside an earth trough at the site with a filtering compartment. Catchment of rainwater is used during the rainy season ( four-five months), while a tanker truck is used to transport water to the reservoir the rest of the year. A 40 KVA Perkins electric generator supplies power to pump water from the reservoir to smaller water tanks..
Water Reservoir - general view Water Reservoir - top view Electric Generator

Click here to see images of Project Activities
Home Production Facilities Model Units Images Nursery Farm
CCHAR, BURAO, SOMALIA
TEL: 252-710733
E-mail your comments: [email protected] (att: Suleiman N. Ali)
Last Updated 05/04/2002
 
Hosted by www.Geocities.ws

1