|
|
|
Project Links
Last Updated: 12.09.2000 |
Case Study AnalysisSheridan Johnson
The project being analyzed is the NIR Elite Over-The-Wire project from
Boston Scientific – SCIMED. This
project concerned developing the NIR Elite OTW stented cardiac catheter for
submission to the FDA and for easy transition into production.
The reasons this project was chosen are because this project was 1) very
successful, 2) only the second project to go through a new corporate Product
Development Process (PDP), and 3) completed without a concept or development
phase. The reason for no
development or concept phase was that this project was very similar to a few
previous projects. Therefore, all
concept and development work was completed in those projects.
Between these projects, there are two different types of catheters and
two different stents. The NIR Elite
OTW project was the fourth of these projects, so all critical aspects for
concept and development were leveraged from the previous projects.
In the new corporate PDP, each franchise (balloon catheter, stent
delivery system, guidewire, etc.) has its own Product Investment Board (PIB).
Each franchise PIB sponsors all projects, new or continuous improvement,
concerned with its franchise. A
project manager is chosen by the PIB to investigate new projects.
The project manager then writes a Pre-Integrated Business Plan (Pre-IBP)
which outlines all scope, time, cost, market, and human resource concerns.
With PIB approval, the project manager then goes to functional management
and asks for certain people to become members of the core team (usually the
senior members of each functional area on the team) and/or extended core team.
Throughout the project, the project manager must periodically update the
IBP and PIB to make sure the project is going smoothly.
As mentioned before, this project was to complete the “four corners”
of existing projects. The real
problem this project, as well as the other three, addresses is keeping the
company competitive in the market while a new, very flexible stent is being
developed. Without these products in the market, the company’s market
share would fall to levels that would be very difficult to rebound from.
The scope, time, and cost goals were all achieved by this project.
The scope involved having six different stent lengths with each length
having four different diameters. Also,
different technical aspects were part of the scope goals. These were all achieved.
The time goal had two different aspects. One aspect included getting everything ready for FDA
submission on time. Since this
product was being amended to an existing submission, very little flexibility
existed for this aspect of the time goal. If
this goal was missed, this product would have to be submitted separately, which
would take another six months, and at the cost of market share.
The other aspect of the time goal was to have everything needed for the
project would be completed so that once FDA approval comes, the product is ready
for launch. Both of these goals have been achieved on time.
The cost goal was one of the easiest to meet.
Because this project leveraged so much information from previous
projects, no development costs were associated with this project.
The largest amount of cost comes from building product for testing, and
without this cost, the budget was very small to begin with.
Even with this smaller budget, this project was completed within budget,
coming in approximately 40% under budget.
Many of the tools discussed in this class have been used by this project.
Some of these tool, and others, include: Project
Charter – Instead of one charter for
the overall project, each phase of the project has a separate charter.
For example, a separate charter is drawn up for the development phase,
and once that is complete, a separate one is drawn up for the validation phase.
WBS/Gantt
Chart – The project manager for this
project used MS Project 98 to make a WBS and Gantt chart for this project.
This outlines all the critical functional management reviews and
milestones. Integrated
Business Plan – This is the main
business document of the project. This
document contains all information the sponsor of the project wants and needs.
Within this document, market speculation is confronted, earned value
analysis is performed, return on investment is investigated, and risk analysis
is included. Meeting
Minutes – These contain all notes
from the weekly core team meetings. This
are usually kept by the project manager unless an administrative assistant is in
attendance. These are kept with the
entire project dossier at project completion for future reference as to how a
problem was taken care of through the meetings. Project
Dossier – A separate dossier
(pronounced dos – ee – ay) is compiled for each phase of the project.
The dossier contains all testing protocols and reports for each specific
phase of the project, as well as the minutes from the meetings.
At project completion, all dossiers are filed together in documentation
archives for future reference. As you can see, the project manager used many of the tools discussed in this class, and many of the tools are included in the main business document, the IBP. As mentioned before, this project was only the second to come through the new corporate PDP. Before this PDP, many of these tools were not required. Since the new PDP requires many of these tools, the project manager has a fairly structured plan to follow. This has helped the two projects that went through the new PDP to meet their time, cost, and scope goals. |