| 5 |
Element
|
£ : p
|
£ : p
|
| 5.1 | Demolition |
765,500.00
|
|
| 5.2 | Substructure |
24,400.00
|
|
| 5.3 | Superstructure | ||
| 5.3.1 | Frame |
238,000.00
|
|
| 5.3.2 | Upper Floors |
171,400.00
|
|
| 5.3.3 | Roof |
400,400.00
|
|
| 5.3.4 | Stairs |
66,100.00
|
|
| 5.3.5 | External Walls |
348,600.00
|
|
| 5.3.6 | Windows and External Doors |
483.900.00
|
|
| 5.3.7 | Internal Walls |
72,000.00
|
|
| 5.3.8 | Internal doors |
82,400.00
|
|
|
1,863,200.00
|
|||
| 5.4 | Internal Finishes | ||
| 5.4.1 | Floors |
371,200.00
|
|
| 5.4.2 | Walls |
333,800.00
|
|
| 5.4.3 | Ceilings |
264,100.00
|
|
|
969,100.00
|
|||
| 5.5 | Fixtures and Fittings |
492,300.00
|
|
| 5.6 | Services | ||
| 5.6.1 | Sanitary, Hot and Cold Water and Waste Plumbing |
34,400.00
|
|
| 5.6.2 | Disposal Installations |
14,700.00
|
|
| 5.6.3 | Hot and Cold Water Installations |
20,500.00
|
|
| 5.6.4 | Mechanical Ventillation |
63,700.00
|
|
| 5.6.5 | Air Conditioning Installation |
362,500.00
|
|
| 5.6.6 | Heating Installation |
232,100.00
|
|
| 5.6.7 | Lift and Dumb Waiter Installation |
64,600.00
|
|
| 5.6.8 | General Electrical Installations |
806,800.00
|
|
| 5.6.9 | Mains Services |
25,600.00
|
|
| 5.6.10 | Underground Drainage |
20,500.00
|
|
| 5.6.11 | Builder's Work in Connection |
82,200.00
|
|
|
1,726,600.00
|
|||
| 5.7 | External Works |
5,000.00
|
|
| 5.8 | Preliminaries and Contractors Return |
716,100.00
|
|
| Sub Total |
6,562,200.00
|
||
| Contingiency (@10%) |
656,200.00
|
||
| Total |
7,218,400
|
![]() |
![]() |
![]() |