5
Element
£ : p
£ : p
 
5.1 Demolition
765,500.00
5.2 Substructure
24,400.00
 
5.3 Superstructure
5.3.1 Frame
238,000.00
5.3.2 Upper Floors
171,400.00
5.3.3 Roof
400,400.00
5.3.4 Stairs
66,100.00
5.3.5 External Walls
348,600.00
5.3.6 Windows and External Doors
483.900.00
5.3.7 Internal Walls
72,000.00
5.3.8 Internal doors
82,400.00
   
1,863,200.00
   
5.4 Internal Finishes
5.4.1 Floors
371,200.00
5.4.2 Walls
333,800.00
5.4.3 Ceilings
264,100.00
 
969,100.00
   
5.5 Fixtures and Fittings
492,300.00
 
5.6 Services
5.6.1 Sanitary, Hot and Cold Water and Waste Plumbing
34,400.00
5.6.2 Disposal Installations
14,700.00
5.6.3 Hot and Cold Water Installations
20,500.00
5.6.4 Mechanical Ventillation
63,700.00
5.6.5 Air Conditioning Installation
362,500.00
5.6.6 Heating Installation
232,100.00
5.6.7 Lift and Dumb Waiter Installation
64,600.00
5.6.8 General Electrical Installations
806,800.00
5.6.9 Mains Services
25,600.00
5.6.10 Underground Drainage
20,500.00
5.6.11 Builder's Work in Connection
82,200.00
 
1,726,600.00
 
5.7 External Works
5,000.00
 
5.8 Preliminaries and Contractors Return
716,100.00
 
  Sub Total
6,562,200.00
  Contingiency (@10%)
656,200.00
 
Total
7,218,400
+

 

   

 