CONVERSION OF POPLAR BATHS
1 Introduction
1.1 This indicative cost estimate has been prepared for The Phoenix Theatre.
1.2 The scope of works envisaged is the conversion and localised extension of the existing building to form a Theatre and TV Studio facility with associated support facilities, restaurant and bar space.
1.3 In the absence of detailed information and without proposals from structural and services engineers, the costs should be viewed as purely indicative at this stage.
   
2 Information Used
2.1 The following information has been used to prepare the estimate.
2.2 Latitude Architects Revised Sketch Proposals dated 23 November 2001.
2.3 Latitude Architects Outline Schedule of Works dated 28 October 2001.
2.4 Site visits.
   
3 Basis of Costing
3.1 The construction costs calculated in formulating the estimate are based upon the following:
3.2 Approximate auantities taken from the drawings.
3.3 Rates derived from our own database for items of work similar in nature to that envisaged.
3.4 The costs are calculated at present day value.
3.5 The works will be executed as one contract under a recognised standard form of contract. Tenders shall be obtained utilising Bills of Quantities, which will be prepared from complete working drawings of the proposed scheme.
3.6 No fundamental restrictions or obligations will be imposed upon the Main Contractor, which will affect the works and site progress.
3.7 Once the works have commenced, it is assumed that variations will be kept to a minimum.

 

   

 