Project Status
The month of October saw the continuation of work on the block work, plaster & MEP first-fix throughout the buildings. The external stone cladding work commenced on the DEZ & MoE buildings as well as the external plaster work on the parapets and Service Block.

The backfilling work continued on the underground water tank with the completion expected in November 2002. Work also continued on the external works for services and the permanent power connection from DEWA. The interior design and the FF&E tender proposals were received and are currently under review.

The project progress reporting has been adjusted to reflect the final agreed weighting of the major phases of the project, namely 3% for Pre-Design, 10% for Design, 2% for Tendering and 85% for Construction.

The overall project progress to date is as follows: -
As of October 31, 2002
Exp. Total Project Duration             663 days

Project Start Date                      
    2 June 2001

Exp. Project Completion Date       
27 March 2003

Days Elapsed                                
516 days

Days Remaining                            
147 days

Time Elapsed                                 
77.83 %

Time Remaining                             
22.17 %

Planned % Completion                  
51.40 %

Actual % Completion                    
  45.86 %

Overall Delay                                
37 Days
Activities Completed in October 2002 (Click Here)
Activities Planned for November 2002 (Click Here)

               
Ministry of Education & Dubai Education Zone Project
                                       
       Dubai - U.A.E.

Project Team
Project Profile
Project Status
Master Schedule
Site Photos
WEBSITE INDEX
Overall
Detailed
Project News
Hosted by www.Geocities.ws

1