Production Timetable

Here is a timeline schedule that I am suggesting for the project.
The most critical scheduling needs to be centered around May1st
which will give us the best time to shoot the outdoor scenes.
Other scenes can be shot both before and after this date.
This timeline gives us benchmark goals to see if we are on track,
not "carved in stone" dates. The timeline roughly follows the development
sequence posted at http://www.geocities.com/mirrorpondmedia/dtdevseq.html
Suggestions are welcome regarding making this as efficient as possible. The
goal with this is to have everyone actually show up when they are supposed
to and to be prepared ahead of time with whatever it is they are choosing to work on.

I know this is incomplete but it gives us an idea of where we will need to be by certain dates.

January
Complete screenplay/script final draft by Jan. 30th
Jan. 4th- Jan 30th ,Visit possible shoot locations including Dare's land scenes, Lineas fantasy scenes in store, livingroom and bedroom, Hooligan street scene, lunch scene.
February
Feb 1- 15, Group reading of final draft screenplay/script
Discuss and plan casting strategy. We need Linea, Dare, Homer the dog, hooligans, possibly a store clerk.
Discuss storyboard development details. Which scenes need to be story boarded, which do not.
Assign directors
Feb 15-28
Review selected story board sequences
List all props,
Generally discuss musical score.
Begin creating graphics for web site and outline web site content.
Shoot winter part of montage fantasy scene
March
Mar 1-15, Finalize casting, wardrobe and aquire all props.
Finalize shoot locations, releases signed?, gather all props,
Most of the pre-production should be done by March 30th
April
April 1-15 try to schedule and shoot hooligan scenes, reserve camera, etc. equip.
May
May 1-15 schedule and shoot tractor shoot, reserve production equip.
Shoot intro. and detail shots.
June
June 1-15 try to schedule linea's fantasy scenes and outdoor scenes after Dare rescues Homer. reserve production equip.
Shooting completes by June 15th
Review musical score concepts
July
Rough editing, Musical score recording.
August
Final editing, titles, dvd reproduction, and entry into any festivals
Sept

Oct

Nov

Dec