LAMB OF GOD LUTHERAN CHURCH
EXPANSION PROJECT
May 19, 2002:  Church Building Dedication
 
     View:  -Church Service- -LCMS First-VP Daniel Preus -
April 14, 2002:  Education Wings & Organ dedication
       
View:   - Church Service -    - Pastors who have served Lamb of God -
March 17, 2002:  First Sunday worship service.      
          
View:    - Altar -     - Baptismal Font -       - Organ -
March 13, 2002:  FIRST WORSHIP SERVICE HELD IN NEW SANCTUARY!
The goal of Lamb of God's remodeling project
       The altar that will grace our sanctuary
       The crucifix that will be at the center of our altar
       The organ that will lead our singing of praises to the Holy Triune God
Ground Breaking Service
View:
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Click on numbers to view pictures of our progress
Week 28, March 11  All inspections passed.  WE HAVE RECEIVED OUR OCCUPANCY PERMIT!! Pews will be installed March 12.  The first worship service in the new sanctuary will be March 13.
Week 27, March 8 Reinspection scheduled for March 11; Organ installed-Piano delivered; Pews delayed--scheduled to be installed next week; First worship service in new sanctuary scheduled for Wednesday, March13  
Weeks 25 & 26, March 1 List of small items to fix created by Village of Pleasant Prairie upon inspection
Weeks 23 & 24, February 15 Altar, pulpit, and communion rail in place; finishing touches being done getting ready for final inspections
-1-   -2-   -3-   -4-
Week 22, February 1:  Chancel platform built; Internal woodworking continues; Parking lot poles installed;  HVAC work continues; Painting continues
-1-
Week 21, January 25:  HVAC work continues; Painting continues; Internal woodworking begun; Pulpit delivered to church
-1- -2-   -3-
Weeks 19 & 20, January 18:  HVAC work continues; Painting begun; Internal woodworking begun; Off-site: pipe organ repairs done; pew colors chosen
-1-
Weeks 17 & 18, January 4:  Internal work on drywalling, lighting, and HVAC continues.
-1- -2- -3-
Week 16, December 21:  Drywall installed in sanctuary.  Insulation and HVAC vent installation continues.  Siding installed on east and west sides of the outside sanctuary walls.
Week 15, December 14:  The pews are ordered.  Lots of internal work is completed or nearing completion--HVAC work, electrical, sprinkler.  Electrical and fire sprinkler system inspections are passed.
Week 14, December 7:  The steeple is installed!  Sidewalks are poured.
-1- -2- -3-
Week 13, November 30:� Work on the sprinkler system began; outside doors in the classrooms are in; forms for the sidewalk cement around the building were put in
Week 12, November 23:� The roof was finished; the blacktopping of the driveway was completed; carpenters are busy with internal work; duct work for the furnaces continues; a lot of work is on hold awaiting the Village of Pleasant Praire approval of sprinkler system changes.
-1- -2-
Week 11, November 16:� Shingles were applied to the roof; the first layer of blacktop was laid; carpenters are busy with internal work; duct work for the furnaces has begun.
-1-
Week 10, November 9:�  The building is closed in and windows put in.  The detention pond is excavated.  The new parking areas are readied for blacktopping.
-1- -2- -3-
Week 9, November 2 :�  Classroom roofs go up; windows & doors are going in;  sanctuary closed in; the detention pond gets reconfigured again (!)
-1- -2- -3-
Week 8, October 26:�  No new pictures--the rains came down and down and down...
The framing in of the sanctuary roof was completed; the detention pond gets reconfigured again and again. . .
Week 7, October 19:�  The new sanctuary roof goes up!
-1--2- -3- -4- -5- -6- -7-
Week 6, October 12:�  The sanctuary roof comes off...
-1--2-
Week 5, October 5:�  Ditches, Bubblers, Walls, Cement Floors, and Tarps
-1--2- -3- -4-
Week 4, September 29:�  Cement walls are poured; plumbing changes are made
-1--2- -3- -4-
Week 3, September 22:� Deconstruction continues; Footings are poured
-1--2- -3- -4- -5- -6-
Week 2, September 15:� Deconstruction continues; earth moves
-1- -2- -3- -4- -5- -6- -7- -8- -9- -10- -11-
Week 1, September 6:� Expansion and remodeling begins
-1- -2--3-
Thank you for visiting our site.� Please come again and check out our remodeling expansion project.
Please visit www.lambofgodlutheran.org for our full official website.