Habitat Schedule

September 4 - Sills, Frame Deck, Frame walls, Sheath walls, cut rafters
Sept. 11 - Frame Ceiling, Set Rafters, Sheath roof
Sept 18 - Frame porches, Shingle roof, Rough wire and plumb
September 25 - Finish rough wire and plumbing, Finish roof, Set windows, Frame basement walls
Oct 2- Insulate, begin siding
Oct 9-Sheetrock, siding and soffits
October 16- Finish hanging sheetrock, siding, loose ends
October 23- Off, Tapers finish sheetrock
October 30- Interior painting, siding
Nov. 6- Interior painting, Hang doors, interior trim, set cabinets, finish wiring and plumbing
November 13- Finish work, carpet and sheet vinyl laid

-These dates are opened to change because of weather, uncooperative family help from the habitat family, or still needing to fundraise.