10/15/00 - 16:00-18:00
- Created web page on geocities and ICQ login and emailed group
- Added first meeting minutes and index page to web page
10/15/00 19:30-20:30
- Attended second meeting
11/05/00 - 8:30-9:45pm
- Attended Fourth Meeting
11/07/00 - 7:00-8:15pm
- Attended Fifth Meeting
11/09/00 - 7:00pm-7:45pm
- Attended sixth meeting.
11/12/00 - 6:00pm-7:20pm
- Attended 7th meeting
11/14/00 - 7:00pm-8:10pm
- Attended 8th meeting
- Created a very messy PERT chart, to be scanned and cleaned up later
11/16/00 19:00-20:00
- Attended 9th meeting
- Discussed homework with Drew
11/16/00 23:45-0:00
- Emailed two people from other team to arrange meeting with Drew for homework
11/27/00 11:00-14:00 Tester Duties
- Created Functional Testing Home Page
- Created Iteration 1 basic functionality checklist
- Emailed Drew regarding tomorrow's review and function test checklists:
Hello.. We need to figure out what documents we'll give to the other team for the review tomorrow. Since we're involved primarily with customer-tester issues, I thought the iteration plans and functional tests would be the most appropriate things to throw at them. We could also include the metaphor and scope diagrams if you want. At any rate, I thought we should give them several URLs before this evening. I've been working on functional tests and have added the first iteration general checklist to the web page. Let me know if you have any issues about this as a customer. _________________________________________________________________________ Angela Thelen [email protected] http://www.imsa.edu/~gellowe/
11/28 19:00-21:00 Project review meeting
-met with two members of another group for project review
12/03 13:00-15:00 Project review meeting
-met again with two members of another group for project review
12/05 19:00-19:45 Final group meeting