DART Cost Estimates

The vast majority of the rail network is currently in place. New Milton to Wareham = 35.6km.

For a recent extension to the Manchester Metrolink funding was provided as follows :-

Private sector

Capital Challenge scheme

European Development fund

67%

13%

8%





PHASE 1 - New Milton >< Square >< Wareham
Detailed Planning and Development =

Light-rail trains (8+1) @ 1.5m =

Street track 1.25km @ 1.5m per km =

Diversion of street services 1.25km @ 2.0m per km =

New stations at Staple Cross, Westbourne, Triangle, Square @ 0.5m =

Modification to New Milton station =

Modifications to track at New Milton, Westbourne, Branksome (2km) =

Phase 1 TOTAL =

1.000m

13.500m

1.875m

2.500m

2.000m

0.100m

3.000m

23.975m

PHASE 2 - Christchurch >< Square >< Poole Ferry Terminal
Light-rail trains 7 @ 1.5m =

Street track 0.1km @ 1.5m per km =

Diversion of street services 0.1km @ 2.0m per km =

New stations at Lake, Hamworthy Park, Poole Ferry Terminal @ 0.5m = Electrification - Hamworthy to Poole Ferry Terminal (3km @0.25m) =

Modifications to track at Christchurch, Hamworthy (0.25km) =

Pedestrian bridge at Poole Centre =

Phase 2 TOTAL =

10.5000m

0.150m

0.200m

1.5000m

0.750m

0.375m

0.250m

13.725m

PHASE 3 - Bournemouth Station >< Square plus station refurbishment and extension to Norden/Corfe Castle
Street track 1.75km @ 1.5m per km =

Diversion of street services 1.75km @ 2.0m per km =

Refurbish all old stations (11 @ 0.1m) =

New Stations at Landsdowne Rd, St. Peters Rd @ 0.5m

New Stations at Furzebrook, Norden/Corfe Castle @ 0.5m =

Electrification - Worgret to Norden/Corfe Castle (7km @ 0.25m) =

Additional track between Worgret and Norden/Corfe Castle (1.5km) =

Phase 3 TOTAL =

2.625m

3.500m

1.100m

1.000m

1.000m

1.750m

2.250m

13.225m

Grand TOTAL (all 3 phases) = 50.925m