FOURTH
SECTION
CASE OF GABAY v.
(Application no. 70829/01)
JUDGMENT
FINAL
This judgment will become final in the circumstances set out in
Article 44 § 2 of the Convention. It may be subject to editorial
revision.
In the case of Gabay v.
The European Court of Human Rights (Fourth
Section), sitting as a Chamber composed of:
Mr J. Casadevall,
President,
Mr R. Türmen,
Mr M. Pellonpää,
Mr R. Maruste,
Mr K. Traja,
Ms L. Mijović,
Mr J. Šikuta,
judges,
and Mr M. O’Boyle,
Section Registrar,
Having deliberated in private on
Delivers the following judgment, which was
adopted on that date:
PROCEDURE
1. The case originated in an application (no. 70829/01) against the
2. The applicant was
represented by Mrs J. Ertürk, a lawyer practising in
3. On
4. On
THE FACTS
5. The applicant was born in
1939 and lives in
6. On an unspecified date,
the applicant lodged a set of enforcement proceedings against his debtors in
order to enforce the payment of six bonds issued by his debtors between 1980
and 1981. The enforcement proceedings lasted for almost ten years. In 1993 the
applicant was paid a sum of 54,000,000 Turkish liras (TRL), interest included.
7. On
8. On
9. On
10. On
11. On
12. On
THE LAW
I. ALLEGED VIOLATION OF ARTICLE
6 § 1 OF THE CONVENTION
13. The applicant complained
that the length of the proceedings had been incompatible with the “reasonable
time” requirement, provided in Article 6 § 1 of the Convention, which
reads as follows:
“In the determination of his civil rights and
obligations ..., everyone is entitled to a ... hearing within a reasonable time
by [a] ... tribunal...”
14. The Government contested
that argument.
15. The period to be taken
into consideration began on
A. Admissibility
16. The Court notes that this
complaint is not manifestly ill-founded within the meaning of Article 35 § 3 of
the Convention. It further notes that it is not inadmissible on any other grounds.
It must therefore be declared admissible.
B. Merits
17. The Court reiterates that
the reasonableness of the length of proceedings must be assessed in the light
of the circumstances of the case and with reference to the following criteria:
the complexity of the case, the conduct of the applicant and the relevant
authorities and what was at stake for the applicant in the dispute (see, among
many other authorities, Frydlender v.
France [GC], no. 30979/96, § 43, ECHR 2000-VII).
18. The Court has frequently
found violations of Article 6 § 1 of the Convention in cases raising issues
similar to the one in the present case (see, Frydlender, cited above).
19. The Court notes that the
domestic courts delivered five decisions in the proceedings during a period of
six years and three months. However, the Court cannot overlook the fact that a
lengthy period- two years and one month- elapsed between the date of the
decision of the Istanbul Commercial Court (29 September 1997) and the date of
the decision of the Joint Civil Chambers of the Court of Cassation on the
applicant’s appeal (3 November 1999). The Government did not offer any
explanation for this state of affairs. In the absence of such an explanation,
or of any indication that the applicant was to blame, the delay must be
considered to be attributable to the domestic courts’ handling of the appeal
proceedings (see, mutatis mutandis, Nuri Özkan v. Turkey, no. 50733/99, §
21, 9 November 2004)
20. Having examined all the
material submitted to it, the Court considers that the Government have not put
forward any fact or argument capable of persuading it to reach a different
conclusion in the present case. Having regard to its case-law on the subject,
the Court considers that in the instant case the length of the proceedings was
excessive and failed to meet the “reasonable time” requirement.
21. There has accordingly
been a breach of Article 6 § 1.
II. APPLICATION OF ARTICLE 41 OF
THE CONVENTION
22. Article 41 of the
Convention provides:
“If the Court finds that there has been a violation of
the Convention or the Protocols thereto, and if the internal law of the High
Contracting Party concerned allows only partial rep
A. Damage
23. The applicant claimed 3,000
euros (EUR) in respect of non-pecuniary damage.
24. The Government contented
that the amount claimed was excessive.
25. Having regard to the
circumstances of the case and making its assessment on an equitable basis, the
Court awards the applicant a sum of EUR 2,000 for non-pecuniary damage.
B. Costs and expenses
26. The applicant also
claimed EUR 2,000 for the costs and expenses incurred before the Court.
27. The Government submitted
that the claims were excessive and unsubstantiated. They argued that no receipt
or any other document was produced by the applicant to prove his claims.
28. According to the Court’s
case-law, an applicant is entitled to reimbursement of his costs and expenses
only in so far as it has been shown that these have been actually and
necessarily incurred and were reasonable as to quantum. In the present case,
regard being had to the information in its possession and the above criteria,
the Court considers that the applicant failed to substantiate his claim in
full. However, in the circumstances of the case, it is reasonable to award the applicant
the sum of EUR 500 under this head.
C. Default interest
29. The Court considers it appropriate
that the default interest should be based on the marginal lending rate of the
European Central Bank, to which should be added three percentage points.
FOR THESE REASONS, THE COURT UNANIMOUSLY
1. Declares the remainder of the
application admissible;
2. Holds that there has been a violation of Article 6 § 1 of the
Convention;
3. Holds
(a) that the respondent State is
to pay the applicant, within three months from the date on which the judgment
becomes final in accordance with Article 44 § 2 of the Convention, EUR 2,000
(two thousand euros) in respect of non-pecuniary damage, and EUR 500 (five
hundred euros) for costs and expenses, plus any tax that
(b) that from the expiry of the
above-mentioned three months until settlement simple interest shall be payable
on the above amounts at a rate equal to the marginal lending rate of the
European Central Bank during the default period plus three percentage points;
4. Dismisses the remainder of the applicant’s claim for just
satisfaction.
Done in English, and notified in writing
on
Michael O’Boyle Josep
Casadevall
Registrar President