IN THE HIGH COURT OF KERALA, AT ERNAKULAM
Present:
The Honourable Mr. Justice P.K.Balasubramanyan
&
The Honourable Mr. Justice M. Ramachandran
Wednesday, the 24th October, 2001/2nd Karthika, 1923.
O.P.No...2 9 8 0 7...OF 2000-W
Biju.V.G. Vs. Thalassery Municipality and others
This Original Petition having been finally heard on 21-8-2001, the court on
24-10-2001 delivered the following:-
J U D G M E N T
BALASUBRAMANYAN, J.
1.This Original Petition is filed by the petitioner, who is the Secretary of the
Kerala Sasthra Sahithya Parishad, Thalassery Unit. According to the petitione,r
the Original Petition is filed in public interest and in discharge of the duties
of the petitioner under Article 48A of the Constitution of India. The petitioner
complains that no proper steps are taken by the State of Kerala, the Union
Government and the authorities concerned to enforce strictly the notification
issued by the Government of India on 19-2-1991 under Sections 3(1) and 3(2) of
the Environment (Protection) Act, 1986. the petitioner is specifically
complaining of the violation of that notification by respondents 2 and 3 in the
Original Petition. He is also complaining of the attidtude of respondent No.1,
the Municipality, in the matter of enforcing the notification and ensuring its
compliance. The prayers in the Original Petition are for setting aside the
orders permitting a construction by respondents 2 and 3 in alleged violation of
the Coastal Zone Regulation notification and for reliefs arising out of the
quashing of those orders that are consequential thereto. There is also a
contention that there has been no proper constitution of the relevant bodies
under the Environment (Protection) Act and a direction is sought for to ensure
that proper bodies are constituted as envisaged by the Act, the Rules and the
notifications.
2. The Original Petition is opposed by respondents 2 and 3, who have constructed
the building, the construction of which is challenged in the Original Petition.
The Union of India has adopted a stand more or less indicating that the
implementation of the regulation by the State leaves much to be desired. The
Municipality has adopted some sort of lukewarm attitude towards environment
protection.
3. Exhibit P1 marked in the Original Petition is the notification published on
20-2-1991 by the Ministry of Environment & Forests under Sections 3(1) and
3(2)(v) of the Environment (Protection) Act and Rule 5(3)(d) of the Environment
(Protection ) Rules, 1986 declaring coastal stretches as Coastal Regulation Zone
(CRZ) and regulating activities in the CRZ. Under Clause-2 of the notification,
construction activities are prohibited and under Clause-3 permissible activities
are regulated. In other words, all activities not prohibited by Clause-2 of the
notification are regulated by Clause-3 of the notification. For any permissible
activity, clearance has to be given when the activity is within the Coastal
Regulation Zone and if it requires water front and foreshore facility. The
notification also contemplates the preparation of Coastal Zone Management Plans
by the States and the Union Territories within one year from the date of that
notification. It is also provided that pending the preparation and publication
of the Coastal Zone Management Plan and their approval, all developments and
activities within the CRZ shall not violate the provisions of the notification.
Clause-4 provides that the Ministry of Environment and Forests and the
Governments of States or Union Territories or such authorities, as maybe
designated for the purpose, shall be responsible for monitoring and enforcement
of the provisions of the notification within their respective jurisdictions.
Annexure-I contains coastal area classification and development regulations. In
this case, we are concerned with Category-II, shortly described as "CRZ-II". The
areas included therein are areas that have been developed unto or close to the
shore-line. A "developed area" is understood as that area within the Municipal
limits or in other legally designated urban area which is already substantially
built up and which have been provided with drainage and approach roads and other
infrastructural facilities, such as water supply and sewerage mains. As regards
CRZ-II, the norms for regulation of activities under Clause 6 is provided as
follows:-
(i) Buildings shall be permitted only on the landward side of the existing road
(or roads proposed in the approved Coastal Zone Management Plan of the area) or
on the landward side of the existing authorised structures. Buildings permitted
on the landward side of the existing and proposed roads/existing authorised
structures shall be subject to the existing local Town and Country. Planning
Regulations including the existing norms or Floor Space Index/Floor Area Ratio.
Provided that no permission for construction of buildings shall be given on the
landward side of any new roads (except road proposed in the approved Coastal
Zone Management Plan) which are constructed on the seaward side of an existing
road".
4. Respondents 2 and 3, acting through their power of attorney, sought to put up
a multi-storied building (non-residential) on the banks of Eranholi River in
the property blocked in Survey No.140/2, 140/4 and 141/1A of Thalassery village.
The construction was attempted admittedly within CRZ-II zone. Special permissions
or exemptions were obtained from the Kerala Building Rules for the construction
of the complex. The petitioner in this Original Petition had approached this
Court with O.P.No.10485/1997 praying for the issue of a direction to the
Thalassery Municipality to restrain all constructions which are in violation of
the CRZ notification, Exhibit P.1. By Judgment dated 18-2-1998, this Court
directed that the issue raised by the petitioner be decided on the basis of the
representation made by the petitioner. It was thereafter, that by the
proceeding, marked as Exhibit P3 in the Original Petition, dated 3-9-1998, the
Municipal Council, Thalassery found that the construction attempted by
respondents 2 and 3 was within the prohibited area going by the Coastal Zone
Regulation. Respondents 2 and 3 challenged the Coastal Zone Regulation
notification by filing O.P.1991 of 1998. In that Original Petition, they moved
C.M.P.3541 of 1998 and this Court by an interim order permitted them to proceed
with the construction of a hotel, but qualified it by saying "if there is a road
separating the petitioner's property and the river". Of course, being only an
interim order, the construction was subject to the result of the Original
Petition or the consequences arising from the final disposal of the Original
Petition. When the original petition finally came up for hearing, respondents 2
and 3 did not pursue their challenge to the notification. The Division Bench in
its judgment dated 18-1-2000 did not go into the merits. It noticed that a
Coastal Zone Management Committee should examine the stand of respondents 2 and
3 herein taking into account the report of the Tahsildar and other relevant
materials. The report of the Tahsildar relied on by respondents 2 and 3 herein
was in support of their claim that there was a public road in between their
property and the Eranholi River.
5. The proceedings of the Committee referred to in the judgment of this Court in
O.P.No.1991 of 1998 was made available for perusal. It was only a
minutes produced before us by anyone. But, a letter dated 31-3-2000 was sent by
the Secretary to Government to the Secretary to the Thalassery Municipality
referring to the claim of respondents 2 and 3 informing him that applying the
provisions contained in CRZ-III(i) of annexure I of CRZ Notification, the
Coastal Zone Management Committee agrees for the issuance of CRZ clearance for
the construction. We may notice here that what is referred to in the
communication, which is marked as Exhibit P.8, is the Original Petition filed by
respondent No.2 herein and the counter affidavit filed by the Tahsildar in that
Original Petition. It may be noted that there is no reference to the "other
relevant materials" referred to in the judgment of the Division Bench in
O.P.No.1991 of 1998. the objector, the present petitioner, had filed
O.P.No.17443 of 1998 before this Court seeking a demolition of the constructions
put up by respondents 2 and 3 and another person. Another Division Bench of this
Court by Judgment dated 26-6-2000 stated that since the Committee had already
taken a decision and that was accepted by the Government of Kerala, the Original
Petition had become infructuous and that the petitioner can be given opportunity
to challenge the order granting permission to respondents 2 and 3. The Division
Bench noticed that if the petitioner felt aggrieved by the Orders, it was for
him to challenge the same. Meanwhile, the Government called for a report from
the Thalassery Nagara Sabha on the unauthorised constructions in violation of
the Coastal Zone Regulations going on within that Panchayat. A report was sent
up, a copy of which is marked as Exhibit P.10, in which it was recommended that
the construction by respondents 2 and 3 was in violation of the Coastal Zone
Regulation (CRZ-II) and that an interim order permitting construction was
obtained by misleading the High Court and that an appeal has to be filed against
the continuance of the construction in violation. It was also reported that if
the construction was effected, the construction would be against the terms of
Section410 of the Municipalities Act. It was also recommended that since the
construction was against the plan submitted to the Government and was against the
plan submitted to the Government and approved by the Municipality, Section
393(10 of the Municipalities Act could also be invoked to cancel the building
permit. Meanwhile, respondents 2 and 3 had also obtained an order from the
Govenrment giving them exemptions from the Kerala Building Rules on the terms
set out in Exhibit P11. The petitioner has again approached this Court with the
present Original Petition praying for the issue of a writ of certiorari to quash
the permissions and exemptions granted to respondents 2 and 3 and for the issue
of a mandamus directing the Thalassery Municipality and the State of Kerala to
take immediate steps to demolish the buildings which are constructed by the
respondents 2 and 3 pursuant to the order Exhibit P8 and for other incidental
reliefs. There is also a prayer for the issue of a writ mandamus directing the
Union of India to replace the members of the Committee constituted under Exhibit
P6 notification with others since they were also in the committee constituted
under Exhibit P7 order and to ensure that those who were included in the
Committee are really interested in protecting the environment and ecology of the
country. The case of the petitioner, in short, is that the construction made and
being made by respondents 2 and 3 on the banks of Eranholi River clearly
violates the Coastal Zone Regulation and the notification issued there under and
that the authority constituted as Kerala Coastal Zone Management Committee
includes in it members who have absolutely no commitment to the environment and
its protection and it is just and necessary to reconstitute the Committee with
fit persons.
6. The Thalassery Municipality has filed a counter affidavit denying that it had
acted without bonafides. Some of the allegations made by the Municipality in its
counter affidavit indicate that it is more loyal than the King. According to the
Municipality the construction by respondents 2 and 3 was on the landward side of
a building that existed in Survey No.140/4 as far back as the year 1935. It had
to concede that when a report was sent up earlier, it was seen that there was no
road in existence between the site of the building and the Eranholi River and
that the construction was not shown as on the landward side of an existing road.
It is also stated that no evidence of existence of a road or a building was
produced when a report was sent up by the Chariman on the earlier occasion. The
counter affidavit winds up by saying that there was a footpath through or by the
side of the river and the buildings are situated in the landward side of the
footpath. then it is asserted that there is no violation of CRZ Rules as
reported by the Senior Town Planner (Vigilance). It may be noted that even as
per this counter affidavit, there is a clear assertion that there was only a
footpath in between the site where the construction is put up and the Eranholi
River.
7. In the statement filed on behalf of the Union of India, it is stated that as
per the Coastal Regulation Zone notification, buildings are not permissible in
Coastal Regulations Zone Areas on the seaward side of the existing road or
existing authorised structures. It is also stated that the Kerala State coastal
Zone Management Authority had been constituted to monitor violation of the
notification. The notification dated 26-11-1998 supersedes any notification
brought out by the State Government. All development activities should be as per
the provisions laid down in Coastal Regulation Zone Notification, 1991 along the
coastal stretches. The violation committed under the notification are monitored
by the Coastal Zone Management Authority, which has been empowered under the
Environment Authority, which has been empowered under the Environment
(Protection) Act to take action against violation. The authority is expected to
fulfil the responsibilities entrusted to it. The Union of India had issued
necessary notifications and orders for implementing Coastal Regulation Zone
Notification from time to time. It was a duty of the State Government and the
authority created by the State Government to take necessary action against
violations. It is significant to note that there is no statement that the
Coastal Zone Management Authority is fulfilling its responsibilities properly or
that the State Government or the authority constituted by it are properly
implementing the Environment (Protection) Act and the concerned regulation.
8. In the counter affidavit filed on behalf of respondents 4 and 5, it is
asserted that the concerned authority has gone by the stand adopted by the
Tahsildar in the counter affidavit in O.P.1991 of 1998 filed in this Court. A
reference is made to the direction of the Division Bench in that Original
Petition to consider the question in the light of the counter affidavit filed on
behalf of the Tahsildar. But, the counter affidavit does not indicate that the
committee examined the other relevant materials that were also referred to by the
Division Bench in its judgment in O.P.No.1991 of 1998 as matters to be
considered. Nor does the affidavit indicate what were the facts that induced the
committee to come to the conclusion that there was no violation of the
notification. We may reiterate here that in spite of being directed to do so,
the Government Pleader did not produce the file relating to the alleged decision
taken by the Coastal Zone Management Committee. What we have is only the
following:-
"Item No.9/5 Tellichery Municipality-Construction of
File No.5079/ Hotel Buildings and Lodge by Shri. A.M.B1/99/STED Raveendran - CRZ clearance reg.
Relying on the report of the Tahasildar
agreed for issuance of CRZ clearance".
From the side of the Kerala Coastal Zone Management Authority what we have is
this:-
"Item No.9/3
File No.5392/B1/2000/STED
Sub:- Coastal Zone Management Authority-Confirmation of
the decisions take by the Coastal Zone Management
Committee.
The Coastal Zone Management Authority confirmed all the decision taken by the
Coastal Zone Management Committee,
when the Committee and Authority were in co-existence".
What we mean to say here is that the file showing what were the materials
considered was not made available for perusal in spite pf direction of the
Coastal zone Management committee meeting on 21-3-2000, the entire reliance for
the clearance was placed on the report of the Tahsildar and relied on by
respondent 2 and 3 before us and no other material in spite of the Division
Bench stating that the Committee should examine the stand of the petitioner
taking into account the report of the Tahsildar and other relevant material
(emphasis supplied). Nothing was shown to us that the other relevant materials
were considered and if considere, what were those materials.
9. Respondents 2 and 3 in their counter affidavits to the various Civil
Miscellaneous Petitions adopted the stand that they have constructed the
building based on the clearance issued by the Coastal Zone Management Committee
as well as the Kerala coastal Zone Management Authority and that considerable
investment has been made by them. There was no justification in interfering at
the instance of the petitioner at this stage. The construction was not on the
seaward side of any existing road. On the other hand, there was a pathway used
by the public between the construction and the Eranholi River. There was also an
old construction on the seaward side of the building put up by respondents 2 and
3. Hence, the construction was authorised and it did not violate the
notification. On 8-8-2001, an additional counter affidavit was filed stating
that the committee that granted the clearance had the necessary experts in it
and the terms of reference were also specified. the allegations of the
petitioner had been examined by that committee of experts and they had given the
clearance. There was no violation of the Building Rules as alleged. In a further
counter affidavit filed on 21-8-2001, respondents 2 and 3 asserted that there
was no violation on their part and producing therewith the report of the Senior
Town Planner (Vigilance) dated 10-8-1999.
10. We may dispose of one preliminary argument even at this stage. The
contention of respondents 2 and 3 that since they have already constructed the
building no relief can be granted to the petitioner cannot be accepted.
Respondents 2 and 3, acting through their power of attorney, constructed the
building pursuant to an interim order obtained in O.P.1991 of 1998. It must by
noted that O.P.1991 of 1998 was filed challenging the Coastal Regulation Zone
notification, since the land in which respondents 2 and 3 were proposing to
construct the building for commercial purpose fell within the Coastal Regulation
Zone. In fact , it is conceded on all hands that the area comes under CRZ-II.
While challenging the notification, respondents 2 and 3 made an interim
application seeking permission to construct. That permission can only be an
interim permission and the permission stated that if there was a road between
the construction of respondents 2 and 3 and the river, respondents 2 and 3 could
construct. Respondents 2 and 3 thereafter did not pursue their challenge to the
validity of the notification when O.P.1991 of 1998 came up for hearing. They
bargained for an order from the Division Bench directing the Coastal Zone
Management committee to examine the stand of respondents 2 and 3 herein (the
petitioners in that Original Petition) by taking into account the report of the
Tahsildar and other relevant materials. Therefore, the construction completed by
respondents 2 and 3 pending the earlier Original Petition and subsequently is at
the risk of respondents 2 and 3 and has to abide by the final adjudication. By
putting up a construction on the basis of an interim order, respondents 2 and 3
cannot over-reach the Environment (Protection) Act or the Court. The argument
that investments have been made is no answer. These aspects are now clear from
the decision of the Supreme Court in M.I. Buildings Pvt Ltd. v. Radhey Shyam
Sahu (AIR 1999 SC 2468) and the subsequent decision following it. The fact,
therefore, that respondents 2 and 3 have put up a construction under the cover
of the interim order of this Court in the earlier Original Petition is
therefore, of no avail and that cannot stand in the way of this Court examining
the legal sustainability or otherwise of the permission granted by the Coastal
Zone Management Committee and adopted by the Kerala Coastal Zone Management
Authority.
11. In Exhibit P5 judgment, as we have noted, this Court directed the Committee
to consider all the aspects including the stand of respondents 2 and 3, the
report of the Tahsildar produced along with the counter is that Original
Petition and other relevant materials. Both the decision of the Committee and
that of the Authority quoted by us earlier, show that the Committee had acted
only on the basis of the report of the Tahsildar produced along with the counter
affidavit in the earlier Original Petition. The authority had only adopted the
decision of the Committee without any independent application of mind. On behalf
of the Committee, the learned Government Pleader could not show that any other
relevant materials were considered or that a considered decision was taken by
the Committee based on the materials available. Therefore, the decision of the
Committee relied on by respondents 2 and 3 is clearly against the terms of the
directions contained in Exhibit P5 judgment. Its infirmity is, therefore, clear
on its face.
12. There is also another aspect. The Coastal Zone Management Plan does not
appear to show that there was any road in between the construction put up by
respondents 2 and 3 and the Eranholi River. What is contended before us is that
there was a pathway. There is a dispute whether such a pathway existed at all
and if it existed, whether it is public pathway which could be considered as
sufficient to permit construction on the landward side of that pathway in terms
of the CRZ notification. There is considerable doubt about the existence of a
pathway in this case in view of the fact that when respondents 2 and 3 applied
for permission to put up the present construction, in the plan that they
submitted, they did not show the existence of any road or pathway between the
River and the proposed construction. That, it was absolutely necessary to show
the existence of any such road or pathway, if it existed, is clear from the
scheme of the Kerala Building Rules, 1984 under which the permission was sought.
rule 7 of the rules contemplated an application for Development permit and Rule
7(2), which provided for an application for a Development Permit, insisted that
the same should be accompanied by a site plan and service plan together with
details and specifications and c4ertificate of supervision as prescribed. Clause
(a) of Rule 7(2) provided for the production of a site plan drawn to a scale of
not less than 1:400. rule 8 of the Rules provided that an application for
Building Permit shall be accompanied by documentary evidence of plot ownership,
the site plan, building plan, service plan, specifications and certificate of
supervision as prescribed. Clause (a) of Rule 8(3) indicated how the site plan
should be drawn and what all details should be shown. It had to show (i) the
boundaries of the plot and of any contiguous land belonging to the owners
thereof; including the revenue survey particulars, (ii) the position of the plot
in relation to neighboring street, (iii) the name, if any, of the street along
which the building is proposed to be constructed. It had also to show all
adjacent streets within a distance of 12 meters of the plot and the nearest
existing street Under Rule 2(104), 'street' means an access to building or site.
Therefore, if there was a public footpath, public pathway or a road in between
the plot of respondents 2 and 3 and the Eranholi River, it was the duty of
respondents 2 and 3 to show that pathway or public road in their site plan while
applying for building permit. It is admitted that in the building plan submitted
by respondents 2 and 3, no such footpath, public pathway or road is shown. this
throws considerable doubt on the question whether there did exist a public
pathway as claimed by respondents 2 and 3. therefore, it was an important
question for the committee to consider whether, as a matter of fact, there was a
public road or public pathway on the seaward side of the proposed construction
of respondents 2 and 3. It must be noted that the relevant plan produced by the
Municipality before this Court as per the direction issued by this Court did not
show that there was a public road in between the site of respondents 2 and 3 and
the Eranholi River. What was attempted to be stated on behalf of the
Municipality
was that there was a public pathway. As we have noted, even the existence of
such a pathway is doubtful in view of the site plan produced by respondents 2
and 3 themselves while seeking permission for putting up a construction in their
plot. It is not seen that the Committee, which was directed to consider all
relevant materials, had even applied their minds to the relevant aspects.
13. In this context, it may also be noted that in the order of the Chairman of
the Thalassery Muncipal Council dated 3-8-1998 pursuant to a direction issued by
this Court in O.P.10485/1997, it is clearly stated that the construction was
even in violation of the exemptions granted by the government and that the
exemption granted does not appear to be proper in view of the CRZ notification.
In that order Exhibit P3 regarding the existence of a road in between the plot
of respondents 2 and 3 and the River, it is stated thus:-
"The said road is not shown in the plan submitted by Sri. Raveendran and
Divakaran. Further as and when this road and a compound wall unauthorisedly
constructed by them, the Municipality issued a notice to them requiring to
demolish the same. Hence I am to state that there was no such road at the time
of notification coming into force and the road now seeing there is a one
recently made by the respondent-applicants (respondents 2 and 3 here)".
This also indicates that the claim of respondents 2 and 3 that there was a
public pathway or a road in between their plot and the Eranholi River remains
only a claim which should have been seriously investigated by the Committee
directed to consider the question by a Division Bench of this Court before
deciding whether there was violation of CRZ notification or not. In the
circumstances, we find a clear abdication of duty by the Management Committee to
consider all the relevant aspects and in that view, the decision taken by the
Committee on 21-3-2000 relying solely on the report of the Tahasildar and
agreeing to the issue of CRZ clearance has to be set aside. Similarly, the
decision of the Management Authority, merely adopting the decision of the
Management Committee at its meeting on 22-12-2000, has also to be quashed or set
aside.
14. There is the further contention of respondents 2 and 3 that there was
already and existing building between their plot and the river and in view of
the existence of that building, the construction cannot be considered to be
objectionable in terms of the notification. On the other hand, on the side of
the petitioner it is contended that the building was not in between the building
of respondents 2 and 3 and the Eranholi River and it is only on one side of it
and that it was not a building which would enable respondents 2 and 3 to claim
that their construction was on the landward side of an existing building. It is
also contended that what is contemplated is the existence of buildings and the
existence of a single structure or shed that is unused is not sufficient. It is
also contended that even in that case, the construction must be consistent with
the local architecture and the surrounding structures and it cannot be said that
the present construction conforms to such a thing. Obviously this aspect has
also to be considered by the Authority when it reconsiders the case of
respondents 2 and 3 for clearance. As of now, the Committee has not applied its
mind to this aspect as well.
15. Now it is the common case that the authority now vests, now with the Costal
Zone Management Committee constituted by the State Government, but with the
Kerala Coastal Zone Management Authority duly constituted. Of course, there is a
challenge for the petitioner to the constitution of that Committee by submitting
that the members are not persons committed to the protection of the environment
and that they should be replaced. The decision of the Supreme Court in Indian
Council for Enviro-Legal Action v. Union of India & ors. (JT 1996 (4) SC 263) is
relied on to emphasis the point that protection of the environment was in public
interest and enforcement of the Coastal Regulation Zone rules and adherence to
the Coastal Management Plan are part of the duties of the State and the High
court can interfere and a citizen can approach the High Court for relief's in
that regard. On behalf of the State, the contention that some of the members of
the Authority are not persons sufficiently committed to the cause of environment
is disputed. We do not think that, for the purpose of this case, it is necessary
to go into that aspect. Since we have found that there has been no proper
application of mind by the Committee pursuant to Exhibit P5 judgment and no
proper decision was taken and no material can be produced before us to show that
there was proper application of mind by the Committee in deciding to grant
clearance and the matter has to be directed to be reconsidered, we do not think
that this aspect need be pursued further in this case. But, it is now clear that
any fresh decision on the question of clearance should be taken by the Kerala
Coastal Zone Management Authority and not by the Coastal Zone Management
Committee. We have every reason to hope that they will show proper and needed
concern for environmental protection and commitment to the strict enforcement of
the concerned laws, Rules and notifications.
16. An argument is raised that the petitioner's approach to this Court lacks
bonafides and that the petitioner has singled out respondents 2 and 3 in his
complaint about violation of the CRZ notification and that there are other
buildings in Thalassery which equally come under the notification. If the
argument of respondents 2 and 3 that others have been spared, we can only say
that the authorites concerned, namely, the Committee at the relevant time, has
been guilty of clear impropriety and it is unfortunate that the State Government
has not insisted on the Coastal Regulation Zone Rules and Coastal Zone
Management Map being strictly implemented and the environment protection laws
strictly implemented. The petitioner claims that he is representing an
organisation which is committed to the protection of the environment is the
State, where, according to the petitioner, there is blatant violation of the
environment protection laws on all fronts. Even assuming that there is substance
in the contention of respondents 2 and 3 that the petitioner's approach to this
Court is not fully bonafide, we find that when aspects like the oncs projected
in this Court are brought to the notice of this Court and violation or
infringement of environment protection laws are alleged, this Court has the futy
to look into those complaints, of course, along with the motive of the
petitioner in approaching this Court. But, in our view, when facts are brought
out which are capable of suggesting that there has been a violation of the
environment protection laws and the CRZ Notification, this court cannot shut its
eyes to the complaint merely on the basis of a plea by the alleged violator of
the Regulation that the petitioner has no bonafides in approaching this court.
In paragraph 37 of the judgment of the Supreme Court in Indian Council for
Enviro-Legal Action v. Union of India & ors. (JT 1996 (4) SC 263), the Supreme
Court has said:-
"There is likelihood that there will be instances of infringement of the main
Notification and also the Management Plans, as and when framed, taking place in
different parts of the country. In our opinion, instead of agitating these
questions before this court, now that the general principles have been laid down
and are well-established, it will be more appropriate that action with regard to
such infringement even if they relate to the violation of fundamental rights,
should first be raised before the High Court having territorial jurisdiction
over the area in question. We are sure and we expect that each High Court will
deal with such issues urgently".
This Court is, therefore, expected to look into complaints of violation of the
environment protection laws including the Coastal Regulation Zone Notification
and the Coastal Management Plan and has to take appropriate action, if the case
is established for it, to ensure that there are no violations of the laws, the
Regulations, the notifications and the plans. Moreover, the body represented by
the petitioner is not shown to be not one interested in environment. There is
also no particular malafides on the side of the petitioner shown except based on
the fact that the petitioner had picked and chosen respondents 2 and 3 alone and
has not initiated action against others. We are confident that the authorites
concerned, including the District Collector, Kannur would take the necessary
action to get rid of all violations of the environment protection laws, the
Coastal regulation Zone notification and the Management Plan within the area of
his operation. The relief's cannot be denied in this case on the ground that the
petitioner has approached this court without bonafides.
17. It is also seen that various exemptions have been granted by the Government
exempting respondents 2 and 3 from Building Rules and even those orders of
exemptions have been alleged to have violated. That is a matter to be looked
into by the local authority, the Municipality. there is a duty in any builder to
comply with the terms of an exemption if he has obtained an exemption. Of
course, elsewhere we have expressed our apprehension about the blanket power of
the Government to grant exemption which boarders on a right to annihilate the
very Building Rules. But, that aspect is not relevant for the purpose of this
Original Petition.
In this situation, we allow this original petition and quash the permission
granted by the Coastal Zone Management Committee and adopted by the Kerala
Coastal Zone Management Authority to respondents 2 and 3 to put up hotel
buildings. Now that the Kerala Coastal Zone Management Authority is in
existence, we direct the Kerala Coastal Zone Management Authority to reconsider
the entire issue of grant of clearance to respondents 2 and 3 after hearing
respondents 2 and 3 and the petitioner in this Original Petition and after
considering all relevant matters and to take a fresh decision in accordance with
law in the light of the directions in O.P.No.1991 of 1998 and the directions
contained herein. A proper quasi-judicial decision taken by it after considering
and discussing all relevant aspects may put an end to the controversy. The fresh
decision should be taken by the authority within five months from today. Pending
any further decision by the Authority, there will be no right in respondents 2
and 3 to carry on any construction, alteration or modification to the building
in the property in question. The local authority and the District Collector,
Kannur are directed to ensure that no construction activity is carried on by
respondents 2 and 3 until the fresh decision and to ensure that the decision of
the Authority to be taken in fully and properly implemented.
Sd/- [P.K.BALASUBRAMANYAN, JUDGE]
Sd/- M. RAMACHANDRAN, JUDGE.]