Project Progression
Gantt Chart of Project Schedule

Week No:

1 2 3 4 5 6 7 8 9 10
Project Planning  
 
Tools Familiarization        
       
Requirement Analysis  
   
Software Design      
     
Implementation    
       
Testing    
Buffer / Demo  
Legend:
Proposed Progress »  
Actual Progress »  
Week 1: (17 Jan 2002 - 23 Jan 2002)
  • Established project team and assigned each team member to his/her role and responsibility in designing project software.
    Team members are published in Project Members page.

  • Formulated project requirements and proposed the project for another team.
    (Details: Project Request)

  • Received project requirements we will be working with from another team.
    (Details: Project Requirements)

  • Established project schedule as a guide for our project development process.
    (Details: Project Schedule)

Week 2: (24 Jan 2002 - 30 Jan 2002)
  • Analyzed first phase of the project specification using Object Oriented Analysis (OOA) approach. The Use Case diagram will be published after the final phase analysis in week 3.

  • Familiarized the use of Rational Rose as our project modeling software.

  • Familiarized the use of Microsoft Access 2000 & Visual Basic Applications (VBA) as our project implementation programming languages.

Week 3: (31 Jan 2002 - 06 Feb 2002)
  • Completed Use Case diagram. (View)
  • Starting to work on UML Class Diagram analysis.
Week 4: (07 Feb 2002 - 11 Feb 2002)
  • Completed UML Class diagram analysis. (View)
  • Analysed the UML Class diagram further to obtain UML Collaboration diagram and UML Sequence diagram.
  • Completed ER Diagram. (View)
Week 5: (14 Feb 2002 - 20 Feb 2002)
  • Completed UML Collaboration diagram and UML Sequence diagram. (View)
  • Assigned tasks to each project member for each class to be implemented.
    It was decided to use Microsoft Access 2000 and Visual Basic Applications (VBA) to implement this project. All project members will focus on their assigned tasks due to the timing constraint.
  • Completed Normalization. (View)
  • Created Microsoft Access 2000 database.
  • Set the relationship between database tables. (View)
Week 6: (21 Feb 2002 - 06 Mar 2002)
  • Each member was initially assigned to do a small part of program and thus everyone tried to familiarize with Microsoft Access 2000 and VBA.
  • There were many meetings called as we encountered many obstacles due to integration problems. The problems were resolved by keeping to the development role.
  • There were a reshuffling of tasks assigned to the group members as we found the old tasks were not suitable and effective. (View)
Week 7: (07 Mar 2002 - 13 Mar 2002)
  • Design of test case in progress.
  • Programming near completion.
  • Compilation and generation of online report in progress.
Week 8: (14 Mar 2002 - 20 Mar 2002)
  • Design of test case completed.
  • Programming and Integration completed.
  • Testing in progress.
  • Compilation and generation of online report in progress.
  • Creation of Online Help in progress.
Week 9: (21 Mar 2002 - 28 Mar 2002)