Home

Optimization Problem:

A dietician recommends a patient to take exercise for 2 hours/day. It is assumed that swimming burns 320 cal/hr and walking consumes 200 cal/hr. The dietician recommends minimum 10 minutes extra walk than swimming and also that extra walking time should not exceed 25 minutes. Determine the duration in minutes the patient should walk and swim per day so that maximum calories are burnt.

Solution:

Assume x minutes of walk and y minutes of swimming per day.

Hence objective function is z = 320x/60 + 200y/60 which is to be maximized.

Constraints are x + y <= 120 minutes

And 10 <= x – y <= 25

The extreme conditions are x + y = 120, x – y = 10 and x – y = 25

Analytically, solving 2 equations at a time simultaneously as below;

x + y = 120, x – y = 10          x = 65 and y = 55

x + y = 120, x – y = 25          x = 72.5 and y = 47.5

 z1 = 320*65/60 + 200*55/60 = 530

z2 = 320*72.5/60 + 200*47.5/60 = 545

Hence solution corresponding to z2 is optimum solution 

Graphical solution is as follows

 


Problem: A farmer has 1000acres of land on which he can grow corn, wheat and soyabean. An acre of wheat costs Rs. 120 for preparation, requires 10 man days and yields a profit of Rs. 40. Each acre of corn costs Rs. 100 for preparation, requires 7 man days of work and yields a profit of Rs. 30. An acre of soyabean costs Rs. 70 for preparation, requires 8 man days and yields a profit of Rs. 20. If farmer has Rs. 1,00,000 for preparation and can count on 8000 man days of work how many acres should be allocated to each crop to maximize tha profit?

Solution: First convert the description into mathematical model by making a table.

 

Wheat

Corn

Soyabean

Availability

Let acres allotted be

x1

x2

x3

1000

Hence cost of preparation will be

120x1

100x2

70x3

1,00,000

Man days required

10x1

7x2

8x3

8000

Profit

40x1

30x2

20x3

To be maximized

Thus Objective function is maximization of z = 40x1 + 30x2 + 20x3

With constraints that     x1 + x2 + x3 <= 1000

                                    10x1 + 7x2 + 8x3 <= 8000

                                    12x1 + 10x2 + 7x3 <= 10000

The standard for of mathematical system is as below

Maximization of z = 40x1 + 30x2 + 20x3 + 0s1 + 0s2 + 0s3

Subject to         x1 + x2 + x3 + s1= 1000

                        10x1 + 7x2 + 8x3 + s2 = 8000

                        12x1 + 10x2 + 7x3 + s3 = 10000

 

 

 

Cj

40

30

20

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

s1

0

1000

1

1

1

1

0

0

s2

0

8000

10

7

8

0

1

0

s3

0

10000

12

10

7

0

0

1

Z=

0

Zj

0

0

0

0

0

0

 

 

Zj-Cj

-40

-30

-10

0

0

0

 

 

 

 

 

 

 

 

 

Key column is x1

(Xb/x1)1=

1000

(Xb/x1)2=

800

(Xb/x1)3=

833.3333

 

Key row is s2, So s2 replaced by x1

Pivotal element is =

10

 

 

Hence R2/10 then R1-R2 and R3-12R2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

40

30

20

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

s1

0

200

0

0.3

0.2

1

-0.1

0

x1

40

800

1

0.7

0.8

0

0.1

0

s3

0

400

0

1.6

-2.6

0

-1.2

1

Z=

32000

Zj

40

28

32

0

4

0

 

 

Zj-Cj

0

-2

12

0

4

0

 

 

 

 

 

 

 

 

 

Key column is x2

(Xb/x2)1=

666.6667

(Xb/x2)2=

1142.857

(Xb/x2)3=

250

 

Key row is s3, So s3 replaced by x2

Pivotal element is =

1.6

 

 

Hence R3/1.6 then R1-0.3R3 and R2-0.7R3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

40

30

20

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

s1

0

125

0

0

0.6875

1

0.125

-0.1875

x1

40

625

1

0

1.9375

0

0.625

-0.4375

x2

30

250

0

1

-1.625

0

-0.75

0.625

Z=

32500

Zj

40

30

28.75

0

2.5

1.25

 

 

Zj-Cj

0

0

8.75

0

2.5

1.25

 

 

 

 

 

 

 

 

 

As all (Zj-Cj) are positive iterative process ends here

 

 

 

 

Solution is x1 = 625 and x2 = 250 (x3 remains = 0)

 

 

 

 


Problem: Maximize the function z = 25x1 + 9x2 + 10x3 subjected to following three conditions using simplex method

12x1 + 3x2 + 4x3 <= 300

6x1 + 4x2 + x3 <= 225

3x1 + x2 + 2x3 <=100

And x1, x2, x3 >= 0

Solution: Express the mathematical model in standard for as below,

Maximize z = 25x1 + 9x2 + 10x3 + 0s1 + 0s2 + 0s3

Subject to         12x1 + 3x2 + 4x3 + s1 = 300

                        6x1 + 4x2 + x3 +s2 = 225

                        3x1 + x2 + 2x3 + s3 =100

 

 

 

Cj

25

9

10

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

s1

0

300

12

3

4

1

0

0

s2

0

225

6

4

1

0

1

0

s3

0

100

3

1

2

0

0

1

Z=

0

Zj

0

0

0

0

0

0

 

 

Zj-Cj

-25

-9

-10

0

0

0

 

 

 

 

 

 

 

 

 

Key column is x1

(Xb/x1)1=

25

(Xb/x1)2=

37.5

(Xb/x1)3=

33.33333

 

Key row is s1, So s1 replaced by x1

Pivotal element is =

12

 

 

Hence R1/12 then R2-6R1 and R3-3R1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

25

9

10

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

x1

25

25

1

0.25

0.333333

0.083333

0

0

s2

0

75

0

2.5

-1

-0.5

1

0

s3

0

25

0

0.25

1

-0.25

0

1

Z=

625

Zj

25

6.25

8.333333

2.083333

0

0

 

 

Zj-Cj

0

-2.75

-10

2.083333

0

0

 

 

 

 

 

 

 

 

 

Key column is x3

(Xb/x3)1=

75

(Xb/x3)2=

-75

(Xb/x3)3=

25

 

Key row is s3, So s3 replaced by x3

Pivotal element is =

1

 

 

Hence R1-0.333333R3 and R2+R3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

25

9

10

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

x1

25

16.66667

1

0.166667

0

0.166667

0

-0.33333

s2

0

100

0

2.75

0

-0.75

1

1

x3

10

25

0

0.25

1

-0.25

0

1

Z=

612.5

Zj

25

6.666667

10

1.666667

0

1.666667

 

 

Zj-Cj

0

-2.33333

0

1.666667

0

1.666667

 

 

 

 

 

 

 

 

 

Key column is x2

(Xb/x2)1=

100

(Xb/x2)2=

36.36364

(Xb/x2)3=

100

 

Key row is s2, So s2 replaced by x2

Pivotal element is =

2.75

 

 

Hence R2/2.75 then R1-0.1666667R2 and R3-0.25R2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

25

9

10

0

0

0

BV

Cb

Xb

x1

x2

x3

s1

s2

s3

x1

25

10.60606

1

0

0

0.212121

-0.06061

-0.39394

x2

9

36.36364

0

1

0

-0.27273

0.363636

0.363636

x3

10

15.90909

0

0

1

-0.18182

-0.09091

0.909091

Z=

751.5152

Zj

25

19

10

1.030303

0.848485

2.515152

 

 

Zj-Cj

0

10

0

1.030303

0.848485

2.515152

 

 

 

 

 

 

 

 

 

Hence solution is x1 = 10.60606, x2 = 36.363636 and x3 = 15.90909

 

 


Problem: An industry produces two products A & B. Product A is sold at Rs. 50/- and B is sold at Rs. 12/- per piece. Each product passes through three different processes. Data for duration for these processes is given below

 

Process

Hours required

Available hrs/month

 

Product A

Product B

 

I

75

15

1000

II

100

30

1500

III

45

10

750

 

Determine the quantity of products to be produced so as to maximize the sale.

 

Solution: The mathematical model will be;

To maximize z = 50x1 + 12 x2

With constraints that     75x1 + 15x2 <= 1000

                                    100x1 + 30x2 <= 1500

                                    45x1 + 10x2 <= 750

The standard form is     z = 50x1 + 12 x2 + 0s1 + 0s2

Subject to                     75x1 + 15x2 + s1 = 1000

                                    100x1 + 30x2 + s2 = 1500

                                    45x1 + 10x2 + s3 = 750

 

 

 

Cj

50

12

0

0

0

BV

Cb

Xb

x1

x2

s1

s2

s3

s1

0

1000

75

15

1

0

0

s2

0

1500

100

30

0

1

0

s3

0

750

45

10

0

0

1

Z=

0

Zj

0

0

0

0

0

 

 

Zj-Cj

-50

-12

0

0

0

 

 

 

 

 

 

 

 

Key column is x1

(Xb/x1)1=

13.33333

(Xb/x1)2=

15

(Xb/x1)3=

16.66667

Key row is s1, So s1 replaced by x1

Pivotal element is =

75

 

Hence R1/75 then R2-100R1 and R3-45R1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

50

12

0

0

0

BV

Cb

Xb

x1

x2

s1

s2

s3

x1

50

13.33333

1

0.2

0.013333

0

0

s2

0

166.6667

0

10

-1.33333

1

0

s3

0

150

0

1

-0.6

0

1

Z=

666.6667

Zj

50

10

0.666667

0

0

 

 

Zj-Cj

0

-2

0.666667

0

0

 

 

 

 

 

 

 

 

Key column is x2

(Xb/x2)1=

66.66667

(Xb/x2)2=

16.66667

(Xb/x2)3=

150

Key row is s2, So s2 replaced by x2

Pivotal element is =

10

 

Hence R2/10 then R1-0.2R2 and R3-R2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

50

12

0

0

0

BV

Cb

Xb

x1

x2

s1

s2

s3

x1

50

10

1

0

0.04

-0.02

0

x2

12

16.66667

0

1

-0.13333

0.1

0

s3

0

133.3333

0

0

-0.46667

-0.1

1

Z=

700

Zj

50

12

0.4

0.2

0

 

 

Zj-Cj

0

0

0.4

0.2

0

 

 

 

 

 

 

 

 

Hence Solution is x1 = 10, x2 = 16.6667 and s3 = 133.3333

 

 

z = 50x1 + 12x2 + 0s3

 

 

 

 

 

Thus s3 = 133.3333 is meaningless

 

 

 

 

Thus optimum solution is x1 = 10 and x2 = 16.666667

 

 

 


Problem: Maximize      z = 2x1 + x2 – 3x3 + 5x4

Subject to                     x1 + 7x2 + 3x3 + 7x4 <=46

                                    3x1 – x2 + x3 + 2x4 <=8

                                    2x1 + 3x2 – x3 + x4 <= 10

And x1, x2, x3, x4 >= 0

Solution: Standard for of the system is,

Maximize          z = 2x1 + x2 – 3x3 + 5x4 + 0s1 + 0s2 + 0s3

Subject to                     x1 + 7x2 + 3x3 + 7x4 + s1 =46

                                    3x1 – x2 + x3 + 2x4 + s2 =8

                                    2x1 + 3x2 – x3 + x4 + s3 = 10

 

 

 

Cj

2

1

-3

5

0

0

0

BV

Cb

Xb

x1

x2

x3

x4

s1

s2

s3

s1

0

46

1

7

3

7

1

0

0

s2

0

8

3

-1

1

2

0

1

0

s3

0

10

2

3

-1

1

0

0

1

Z=

0

Zj

0

0

0

0

0

0

0

 

 

Zj-Cj

-2

-1

3

-5

0

0

0

 

 

 

 

 

 

 

 

 

 

Key column is x4

(Xb/x4)1=

6.571429

(Xb/x4)2=

4

(Xb/x4)3=

10

 

 

Key row is s2, So s2 replaced by x4

Pivotal element is =

2

 

 

 

Hence R2/2 then R1-7R2 and R3-R2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

2

1

-3

5

0

0

0

BV

Cb

Xb

x1

x2

x3

x4

s1

s2

s3

s1

0

18

-9.5

10.5

-0.5

0

1

-3.5

0

x4

5

4

1.5

-0.5

0.5

1

0

0.5

0

s3

0

6

0.5

3.5

-1.5

0

0

-0.5

1

Z=

20

Zj

7.5

-2.5

2.5

5

0

2.5

0

 

 

Zj-Cj

5.5

-3.5

5.5

0

0

2.5

0

 

 

 

 

 

 

 

 

 

 

Key column is x2

(Xb/x2)1=

1.714286

(Xb/x2)2=

-8

(Xb/x2)3=

1.714286

 

 

As (Xb/x2)1 = (Xb/x2)3, both the rows are equally eligible to become key row.

 

 

Here we may consider any one of the two row as key row.

 

 

 

 

taking key row as s1, So s1 replaced by x2

Pivotal element is =

10.5

 

 

 

Hence R1/10.5 then R2+0.5R1 and R3-3.5R1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

2

1

-3

5

0

0

0

BV

Cb

Xb

x1

x2

x3

x4

s1

s2

s3

x2

1

1.714286

-0.90476

1

-0.04762

0

0.095238

-0.33333

0

x4

5

4.857143

1.047619

0

0.47619

1

0.047619

0.333333

0

s3

0

0

3.666667

0

-1.33333

0

-0.33333

0.666667

1

Z=

26

Zj

4.333333

1

2.333333

5

0.333333

1.333333

0

 

 

Zj-Cj

2.333333

0

5.333333

0

0.333333

1.333333

0

 

 

 

 

 

 

 

 

 

 

As all (Zj-Cj) are positive iterative process ends here

 

 

 

 

 

Solution is x2 = 1.714286 and x4 = 4.857143 (x1 and x3 remain = 0)

 

 

 


Problem: Minimize       z = x2 – 3x3 + 2x5

Subject to         x1 + 3x2 – x3 + 2x5 = 7

                        -2x2 + 4x3 + x4 = 12

                        -4x2 + 3x3 + 8x5 + x6 = 10

And x1, x2, x3, x4, x5, x6 >=0

 

Solution: It is observed that coefficients of x1, x4 and x6 in objective function are = 0. Also their coefficients in constraint equation are two times zero and one time 1. Further the constraints do not have inequality signs. Hence it may be assumed that x1, x4 and x6 are surplice variables (s–variables). Therefore standard form is

Maximize          z = –x2 + 3x3 – 2x5 + 0x1 + 0x4 + 0x6

Subject to         x1 + 3x2 – x3 + 2x5 = 7

                        –2x2 + 4x3 + x4 = 12

                        –4x2 + 3x3 + 8x5 + x6 = 10

 

 

 

Cj

0

-1

3

0

-2

0

BV

Cb

Xb

x1

x2

x3

x4

x5

x6

x1

0

7

1

3

-1

0

2

0

x4

0

12

0

-2

4

1

0

0

x6

0

10

0

-4

3

0

8

1

Z=

0

Zj

0

0

0

0

0

0

 

 

Zj-Cj

0

1

-3

0

2

0

 

 

 

 

 

 

 

 

 

Key column is x3

(Xb/x3)1=

-7

(Xb/x3)2=

3

(Xb/x3)3=

3.333333

 

Key row is x4, So x4 replaced by x3

Pivotal element is =

4

 

 

Hence R2/4 then R1+R2 and R3-3R2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

0

-1

3

0

-2

0

BV

Cb

Xb

x1

x2

x3

x4

x5

x6

x1

0

10

1

2.5

0

0.25

2

0

x3

3

3

0

-0.5

1

0.25

0

0

x6

0

1

0

-2.5

0

-0.75

8

1

Z=

9

Zj

0

-1.5

3

0.75

0

0

 

 

Zj-Cj

0

-0.5

0

0.75

2

0

 

 

 

 

 

 

 

 

 

Key column is x2

(Xb/x2)1=

4

(Xb/x2)2=

-6

(Xb/x2)3=

-0.4

 

Key row is x1, So x1 replaced by x2

Pivotal element is =

2.5

 

 

Hence R1/2.5 then R2+0.5R1 and R3+2.5R1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cj

0

-1

3

0

-2

0

BV

Cb

Xb

x1

x2

x3

x4

x5

x6

x2

-1

4

0.4

1

0

0.1

0.8

0

x3

3

5

0.2

0

1

0.3

0.4

0

x6

0

11

1

0

0

-0.5

10

1

Z=

11

Zj

0.2

-1

3

0.8

0.4

0

 

 

Zj-Cj

0.2

0

0

0.8

2.4

0

 

 

 

 

 

 

 

 

 

As all (Zj-Cj) are positive iterative process ends here

 

 

 

 

Solution is x2 = 4, x3 = 5 and x6 = 11 (x1and x4 become zero and x5 remains = 0)

 

As coefficient of x6 in objective function is zero x6 = 11 has no meaning;

 

 

Therefore solution is x2 = 4, x3 = 5 and x5 = 0

 

 

 

 

 

 

Hosted by www.Geocities.ws

1