QUESTION: How can I include Gantt charts from Microsoft Project on a Web page?
ANSWER: To publish a Microsoft Project Gantt chart on
a Web page, you should first convert the chart to a GIF file using Microsoft
Project for Windows 95 and Office 97.
To prepare a Gantt chart for the Web
ANSWER: Follow the steps below to remove any date constraints from a selected task, allowing the task to be scheduled based on dependencies rather than on a date entered by a user.
To remove a date constraint from a task
ANSWER: You can use the Paste Link command to create a dynamic data exchange (DDE) link between two fields in different Microsoft Project files. This is not a true dependency link, but it will ensure that the contents of the second field are updated dynamically whenever the contents of the first field change.
To link tasks in separate files