...more weekly news       ...more weekly news          


New cell at landfill nearing completion
By MANLEY J. ANDERSON
Special to the OBSERVER
ELLERY — There’s much more than meets the eye in the construction of a new cell at the Ellery landfill.
From conception, the cell has been subject to almost daily scrutiny from many directions and levels to ensure that all requirements for its construction and operation are met.
The Chautauqua County Department of Public Facilities has oversight responsibility for the landfill. Among the principal county employees involved in the major undertaking are Kenneth W. Bochmann, deputy director of public facilities; Pantelis K. Panteli, senior engineer/project designer; and Jack Skinner, operations manager.
Excavation for the 15-acre cell began in August 1999, but the initial phase of the project was suspended during the winter months.
Barbella Construction of New Jersey, the major contractor on the project, had 50 employees on the job at its peak, said Skinner. All but three of the workers were area residents.
‘‘It was built on a schedule (that was) extended due to weather conditions,’’ Bochmann said. ‘‘They went to seven workdays a week to finish it. It was a major challenge under the weather conditions.’’
Construction on the new cell is nearing completion and the unit will be ready and available for use after a myriad of tests have been passed and operating certification is received from the state Department of Environmental Conservation.
Bochmann said the cost originally had been estimated at $8 million, but the total investment is expected to be about $5.8 million or less, with the cell having a projected use expectancy of about 7 and one-half years at an acceptance rate of 1,000 tons of garbage daily.
‘‘It’s an improvement over the previous one,’’ Panteli said, explaining, ‘‘We made improvements to the standards. It saves air space and you can get more into it.’’
An insight into what’s involved in constructing the unit was provided by Panteli through the use of a display in the landfill office near Towerville.
At the base is an illustration of the groundwater relief system from which water drains into a creek as clean water after sediment has been removed.
Next is a two-foot deep layer of highly compacted clay covered by a high-density polyethylene liner with welded seams and covered by a cushioning liner.
Third in line up from ground level is a foot-deep stratum of screened stone to protect a perforated pipe designed for secondary leachate collection and which in turn is covered by another foot of highly compacted soil.
On top of this is a carpet-like geosynthetic clay liner — the equivalent of six inches of clay which, if it gets wet, expands to become nearly impermeable.
This is covered by the primary liner, ‘‘where you collect the leachate from the actual garbage,’’ Panteli said.
Next comes drainage stone of a special mix as a filter layer, followed by a third collection line and then two more feet of stones, with larger ones around a pipe and the rest as smaller stones.
‘‘What you have in a big bathtub,’’ Bochmann said.
When the numerous layers up from ground level are completed, the facility, after the required certification is received, will be ready to accept what is described in the industry as ‘‘perfect garbage,’’ meaning it’s free of construction material, couches, television sets, sharp objects, recyclables and any other objects that might puncture the liner.
After the compacted level of ‘‘perfect garbage’’ is five feet deep, ‘‘Then you can add regular garbage,’’ Bochmann said.
‘‘The cell (itself) is complete,’’ he said. ‘‘Now we’ve got two things to do. The first is electronic testing for leaks and repair of any that are found. The second is certification by the DEC, which verifies all drawings and determines that it was built to standards.’’
Bochmann said all DEC inspectors on the site, as well as county and private inspectors, have been very cooperative on the project.
‘‘Everything is pre-tested, field tested and tested again,’’ Skinner said of the continuous effort to ensure the integrity of the cell which will continue throughout and beyond its use expectancy.
Panteli said the county will pay about $180,000 for laboratory work and monitoring, which now is done every 90 days.
He and Bochmann explained a special feature of the cell for which specific DEC approval had to be received. It involves installation of a temporary storm water relief system to keep surface water from entering the garbage area as sections of the cell are opened to use.
The innovative system keeps the storm water from mixing with leachate. If mixing occurred, it would require that the entire mixture be treated as leachate — a costly procedure.
‘‘It saves a lot of money,’’ Panteli said, explaining that as a new section of the cell is opened the temporary storm relief system will be removed.
After the new cell eventually is filled, it will be topped with 4 and one-half feet of cover material, but monitoring of the site will continue.
Bochmann said that after the required DEC certification is received for the new cell, a date for its formal dedication will be set.
Although it perhaps doesn’t rank very high on the glamour scale of county projects, the new cell already has at least three major accomplishments in its favor — innovative adaptations, on-schedule completion and, perhaps most importantly to taxpayers, it is being constructed well within budget.
 
 

...more weekly news                   ...more weekly news    

Hosted by www.Geocities.ws

1