by Bernardine for November 10, 2002
The Project
- Construction for the chapel project started last October. Estimated cost of construction is 1.2 million pesos. Completion date is scheduled on Dec 28-29, in time for the class' 25th reunion.
Construction Crew
Gilbert Gonzales is the Overall Project Coordinator while Efren Rosana is the Project Engineer. Elenita Sanao-Samblero is the Financial Controller, in charge of procuring construction materials. Basic materials and equipment were donated by several class 77 based in the Philippines.
Estimated Project Cost Summary = P1.2 million
Preliminaries (1 Lot) - P10,000.00
Site Works (1 Lot) - P24,255.00
Concrete (1 Lot) - P253,330.28
Architectural Finishes (1 Lot) - P325,245.76
Carpentry Works (1 Lot) - P128,606.80
Metals & Glass Works (1 Lot) - P28,470.00
Roofing Works (1 Lot) - P187,540.85
Painting Works (1 Lot) - P137,200.00
Plumbing & Sanitary Works (1 Lot) - P30,000.00
Electrical Works (1 Lot) - P78,000.00
Fund Raising Activities
Activities are being undertaken to raise additional funds. These are: raffle draw and publication of a souvenir program.
Donations
Donations can be directed to the following accounts:
Elenita Sanao-Samblero
Land Bank - Legazpi Branch
Account Number: 0137-0005-71
Elenita Sanao-Samblero (Peso Account)
PNB - Legazpi Branch
Account Number: 430-532358-1
Elenita Sanao-Samblero (US$ Account)
PNB - Legazpi Branch
Account Number: 430-703136-7
Nov 10, 2002 continuation
back to project
home
|