| There are many different step in building our house, and we would appreciate help for all of them. From cooking to cobbing, there is something to do for all ages and physical shape. A straw bale house is also a kids friendly site, because our main tools are our hands to play in the straw and mud. Our goal is to be able to live in our house this winter, but as you know, there is always more to do then we expect. So the Schedule will probably be changing as we go. We will keep it update at the best of our knowledge. |
||||||||||||||||||||||
| Date | Work to be done | Status | ||||||||||||||||||||
| Water System Fridge Situate the House, flag it Dig posts Pour concrete posts Pour concrete posts Support Beam Post & Beam structure Windows & doors posts Roof rafters Roof shingles Floor rafters Floor with door cutouts Raising Straw bales Cobing Outside Cobing Outside Windows & doors Cobing Inside Cobing Inside Make inside Walls |
||||||||||||||||||||||
| June 1-7 June 8-14 June 15-21 June 22-28 June 29-July 5 July 6-12 July 13-19 July 20-26 July 27-Aug 2 August 3-9 August 10-16 August 17-23 August 24-30 Aug 31-Sep 6 Sep 7-13 Sep 14-20 Sep 21-27 Sep 28-Oct 4 Oct 5-11 Oct 12-18 |
Done 1/2 done done done done done just starting |
|||||||||||||||||||||