We built a deck on the back of our house.
We took a few hours every Sunday to work on it.
We started demolition to the back yard in the end of September.
We removed all the red rocks, and broke up the concrete by the tree.
Then we dug out the holes for the supports.
Now it's time to lay down the concrete.
We rented a large mixer with the concrete premixed.




Two yards later we had everything filled in.
The weekend of November 11th we got some framing up!
November 28th we finished the framing on the deck.
By December 10th we got the surface started.
Around December 18th we got
all but two rows put on.
Then on the 20th the blizzard of 2006 hit. That has slowed the production down to a screeching halt.
I know, I know, it has been a while since we have updated this but here we are in April with a more recent shot.
We have the hot tub on the deck and all three sets of stairs on it.
Now here are the posts for the railing.
On the right you can see that one railing is done.
April 22, 2007
All we have left is the skirting, Then we are done.