OBJECTIVE 2: Fully utilize field staffs to coordinate legends, conduct field studies, and

solve problems related to the soil resources of the Indiana Headwaters

MLRA Project Office area.



GOAL B: Solve soil correlation and classification problems and develop reliable soil

interpretations within the project area by collecting accurate information and

analyzing to determine its proper application.



Action Items
Team Member
Scheduled Date
Completed Date

1. Identify soil investigation needs and prioritize them. (Include as Long Range Plan of Soil Investigations (LRPSI) attachment to this plan of operations.)

Team

Continuing

See AR

2. Interpretation tables
  • Prepare and update data elements
  • Order tables
  • Review tables with technical specialists

Team

SDQS

1/98-6/98

SeeAR

3. Review and update prime farmland, highly erodible, and hydric soils lists.

Team

1/98-6/98


4. Analyze transect data to determine if existing delineations in the MLRA project area fit the slope conversion convention established by the Region 11 MLRA work group.

Team

Continuing


5. Special studies (refer to attached work plans)
  • Crop yields
  • Limnic Materials Study
    • Assist with wet soils monitoring project (Purdue University)
    • Geomorphic, characterization, and surficial geology
      • *Riddles vs. Rockrun
      • **Maumee vs. Newton
      • **Rensselaer till substratum
      • **Bedrock extent transects
      • **Iron oxide nodules in sandy soils
      • **Investigate the possibilities for spodic horizons
      • *Dense till under Wawasee

*MLRA region wide

**MLRA region wide and Pulaski county



Team

FF

SLM

RAB

WDB

RAB

SLM

WDB

SLM

WDB

Work plans

completed by:

12/97

Continuing


See AR

10/97




5/97

6. Sampling and lab data
  • For NSSL
  • For Purdue University

Team

As needed


See AR