ASSUMPTIONS MADE DURING THE DEVELOPMENT OF
1. MLRA Project
office to be located at Winamac, IN and may be relocated to Plymouth,
IN before completion of the subset update. 2. MLRA team will consist of at least four members. 1 MLRA Project Leader 2 Soil Scientists
1 Resource Soil Scientist (20 percent of
time spent on subset update)
3. Availability
of functional equipment and transportation throughout the project.
4. Pedons
previously correlated within the MLRA project office area will
be used where appropriate.
5. Line work
in the 1968 published Pulaski County Soil Survey is satisfactory
and will require little or no revision.
![]() 6. MLRA team work load will be maintained at current levels with only minor deviations (Less than or equal to 5 days). |