CENTURY
PARK LIMITED
MIDLAND QUARRY, NUNEATON
Design and Construct Tender
Document
June 2003
VOLUME 1 OF 3
Century Park Limited
Tender Document for
Engineered Filling of Part of Former Midland Quarry, Tuttle Hill, Nuneaton
VOLUME 1
&nbssp;
> Tender
Document
>
> Drawings
>
> Appendix 1
– Pre-Tender Health and Safety Plan
&nbssp;
> Appendix 2
– Form of Collateral Warranty
&nbssp;
&nbssp;
> VOLUME 2
&nbssp;
> Appendix 3
– Wardell Armstrong Site Investigation
> Report
March 2003
&nbssp;
&nbssp;
> VOLUME 3
&nbssp;
> Appendix 4
– Joynes Pike & Associates Ltd Ground Investigation
> Report
August 2002
&nbssp;
Appendix 5
– Wardell Armstrong Preliminary Infilling Works to DEV11 Summary Report
WM02457/005
&nbssp;
> Appendix 6
– JMP Consultants Ltd Reinforced Earth Embankment
> Feasibility
Report
&nbssp;
> Appendix 7
– Entec UK Limited – Water Management Strategy
> (Draft)
&nbssp;
> Appendix 8
– Entec UK Limited – Management Strategy (Draft)
&nbssp;
&nbssp;
&nbssp;
&nbssp;
&nbssp;
&nbssp;
>
>
>
&nbssp;
VOLUME 1 - CONTENTS
&nbssp;
Section A - Instructions to Tenderers
Section B - Forms
Form
of Tender
Form
of Tender Appendix A - Parts 1 and 2
Form
of Tender Appendix B
Form
of Tender Appendix C
Form
of Agreement
Section C - Conditions of Contract
Conditions of Contract
Modifications
and Additions to Clauses.
Special
Conditions of Contract
Schedule
of Amendments
Section D - Employer’s Requirements
&nbssp;
Section E - Description of Works
Section F - Specification
&nbssp;
Section G - Lump Sum Build Up/Schedule of Rates
&nbssp;
WM02457/101 Midland
Quarry Site Location
WM02457/102 Original
Site Levels
WM02457/103 Post 2002 Site Levels
WM02457/104 Proposed Infilling Works
APPENDICES
Appendix 1 - Pre-Tender
Health and Safety Plan
Appendix 2 - Form of Collateral Warranty
SECTION A
Tender
Document for Engineered Filling of Former Midland Quarry, Tuttle Hill, Nuneaton
Instructions
to Tenderers
1 These instructions to Tenderers are
issued for the guidance of Tenderers and shall not form part of the
Contract. Failure to comply with these
instructions may result in rejection of the tender.
2 Tenderers shall study the Tender
Documents, visit the site and shall be deemed to have satisfied themselves on
all matters affecting their Tender.
3 Tenderers shall complete and return
copies of the following Documents:-
a) Form of Tender and Appendices A-C to
the Form of Tender
4 The Tender shall be sent by registered
post or delivered by hand in a sealed envelope bearing no mark identifying the
Tenderer either on the envelope or in the franking thereon, and shall be
clearly marked:
Tender
for Engineered Filling of Former Midland Quarry, Tuttle Hill, Nuneaton
The envelope shall be addressed to:
Wardell Armstrong
Thynne
Court
Thynne
Street
West
Bromwich
West
Midlands B70 6PH
Tenders should arrive no later than
12 noon on July 2003.
5 Tenders are to remain open for
acceptance for a period of 90 days from the date for receipt of Tenders.
6 Tenders not received by the time
specified may not be considered.
7 The Employer shall not be bound to
accept the lowest or any tender.
8
The Tenderer is to
submit with his Tender the following documents for all work including that of
sub-contractors, which will be considered to be essential parts of the complete
tender submission:
·
A programme showing
the order in which the various sections of the Works described in the Contract
Documents are to be undertaken and the time which the Tenderer estimates he
will require to complete the Contract.
·
An outline
method statement indicating the procedures by which the Tenderer proposes to
undertake the works and execute the Contract.
·
An outline Health and
Safety Plan prepared in accordance with the Construction (Design and
Management) Regulations 1994.
·
a copy of their
Company's Safety Policy.
·
details of how the
security of the site will be managed.
·
details of any
proposed external Safety Consultant, if any.
·
a copy of their
insurance certificate(s) detailing the extent of cover to be provided under the
Contract.
· Preliminary drawings and specifications in sufficient detail
to enable the Employer to assess the Tenderers proposals;
· a list of proposed sub contractors;
· specification Table 6/1
· the following Appendices to the Specification duly
completed:
Appendix 1/5
Appendix 5/1
Appendix 5/2
Appendix 6/5
· completed Contract Sum Analysis and break down of the Lump Sum Build Up and Schedule of Rates
(attached as part of Section G to the tender);
.
Preparation of Tenders
9 The Tender must be compiled on the
basis of the documents listed in the Form of Agreement, based on the ICE Design
and Construct Conditions of Contract – First Edition and Amendments to the ICE
Conditions of Contract to take into account The Finance Act 1996 (Sections
39-71 and Schedule 5) and the Landfill Tax Regulations 1996
(ICE/D&C/Tax/February 1998) and Amendments to the ICE Conditions of
Contract to take into account The Housing Grants, Construction and Regeneration
Act 1996 (Part II) (ICE/D&C/HGCR/March 1998), modified and added to by the
Modifications and Additions to Clauses together with the Special Conditions of
Contract.
10 Tenderers shall be prepared to supply to
the Employer copies of their last 3 years audited accounts within 7 days, if
requested.
11 No alternative tender will be considered
unless a Tender free from qualifications and strictly on the basis of these
Tender Documents is also submitted.
12 Should any alterations or additions to
the Tender Documents be deemed necessary during the Tender Period, these shall
be notified in writing to the Tenderers and shall form part of the Tender
Documents.
13 No unauthorised alteration or addition
is to be made or qualification added to the Tender Documents. Such alteration, addition or qualification
may result in the Tender being rejected.
14 The contract is to be a Firm Price and
does not include a Price Fluctuation clause.
15 All expenses incurred in the preparation
and submission of the Tender shall be borne by the Tenderer.
16 The Employer and/or the Employer’s
Representative accept no responsibility for the arithmetical or other
inaccuracy of the Tender.
17 Any queries with regard to tendering or visiting the site
shall be directed to Tom Bason (tel 0121 580 0909) or Douglas Brownjohn (tel
01942 260101) at Wardell Armstrong.Any query concerning any aspect of the
Tender shall be referred to the Employer’s Representative in writing. The Tenderer shall abide by the written
interpretation of the Employer’s Representative, providing that such written
interpretation is received at least 3 days before the date on which the Tender
is to be submitted. The Tenderer, if
not in receipt of such written interpretation within the said 3 days shall
attach to his Tender a covering letter stating the interpretation on which his
Tender is based.
18
Tenderers will
be required to provide before award of the Contract, CV's for the Company
Safety Manager and the proposed Site Manager indicating their specific
experience on earthworks projects of a similar nature, their period of service
with the company, details of training/safety courses attended and any other
relevant information.
19
The Tenderers
shall include for all items necessary to complete the works.
20
All design and
other fees shall be included in the Contractor's Tender Sums.
21
The Tender Sum
for carrying out the works shall include for all general preliminaries.
Form of Tender
Form of Tender (Appendix) – Part
1
Form of Tender (Appendix) – Part
2
Form of Agreement
Short Description of Works
All the Design and Permanent and
Temporary Works in connection with the engineered filling operations of part of
the former Midland Quarry, Tuttle Hill, Nuneaton. Including site clearance
operations, bulk earthworks, the import of acceptable inert fill material (if
necessary), the compaction and placement of fill, the construction of a
reinforced earth slope (45°) and ancillary works.
FORM
OF TENDER
(NOTE:
The Appendices form part of the Tender)
To: Century Park Limited
Edwards
Centre
The
Horsefair
Hinckley
Leicestershire
LE10
0AW
Gentlemen,
Having examined the Employer’s
Requirements, Conditions of Contract, Drawings for the above mentioned works
(and the matters set out in the Appendices hereto), we offer to design
construct and complete the said Works and maintain the Permanent Works in
conformity with the said Employer’s Requirements, Conditions of Contract, and
Drawings Specification for the sum of ¼¼¼¼¼¼¼¼¼¼¼¼¼¼¼¼. (words) £¼¼¼¼¼¼¼ or such other sum as shall become payable in accordance
with the said Conditions of Contract.
We undertake to complete and
deliver the whole of the Permanent Works comprised in the Contract within the
time stated in the Appendix hereto.
If our tender is accepted we will, when required, provide
two good and sufficient sureties or obtain the guarantee of a Bank or Insurance
Company (to be approved in either case by you) to be jointly and severally
bound with us in a sum equal to the percentage of the Tender Total as defined
in the said Conditions of Contract for the due performance of the Contract
under the terms of a Bond.
Unless and until a formal
Agreement is prepared and executed this Tender, together with your written
acceptance thereof, shall constitute a binding Contract between us.
We understand that you are not
bound to accept the lowest or any tender you may receive.
We are, Gentlemen
Yours faithfully,
Signature .......................................................
Address .......................................................
.......................................................
.......................................................
.......................................................
.......................................................
Date: .......................................................
FORM OF TENDER (APPENDIX)
(NOTE: Relevant Clause numbers
are shown in brackets).
1 Name of the Employer (Clause
1(1)(a)): Century Park Limited
Address:
Edwards Centre, The Horsefair, Hinckley, Leicestershire, LE10 0AW
2 Name
of the Employer’s Representative (Clause 1(1)(c))and 2(2)) To
be Appointed
Address:
3 Defects
Correction Period (Clause 1(1)(p)): 52 weeks
4 Quality
Assurance (Clause8 (3)) Not
required
5 Contract
Agreement (Clause 9):
Required Required
6 Performance
Security (Clause 10(i)):
Required Required
Amount (if required) to be:
10% of Estimated
Contract
Price 10%
of Tender Total
7 Minimum
amount of third party insurance (persons and property) (Clause 23(3): £5,000,000
for each
and
every occurrence
Unlimited
Occurrences.
8 Works
Commencement Date (if known) (Clause 41(1)(a): To
be agreed
9 Time
for Completion (Clause 43)a:
For
the whole of the Works
weeks
10
Liquidated
damages for delay (Clause 47)
For the whole of the Works £2,000
per week Limit of Liability £50,000
11 Not
required
12 Percentage
of the value of goods and materials to be included
in
Interim Certificates (Clause 60(2)(ii)): 75%
13 Minimum
amount of Interim Certificates (Clause 60(3)): £20,000
14 Rate
of retention (recommended not to exceed 5%) (Clause 60(5(a))): 5%
15
Limit
of retention (% of Tender Total) (Clause 60(5)(a))
(Recommended
not to exceed 5%): 5%
16 Bank
whose Base Lending Rate is to be used (Clause 60(7): National Westminster
17 Name
of the Planning Supervisor (Clause 71(1)(b)): Simon
Gibbs
Address: Innovative Minerals Processing Ltd, P O Box
1638, Stafford ST19 9RP
18 Name
of the Principal Contractor (Clause 71(1)(b)): The Contractor
Address:
19 The
arbitration Procedure to be used is (Clause 66(11)(a))
(a)
The
Institution of Civil Engineers’ Arbitration Procedure (1997)g or
(b)
The Construction Industry Modell Arbitration Rulesg
a If
not stated is to be completed by Contractor in Part 2 of the Appendix.
b To be completed if
required, with brief description. Where
Sectional completion applies the item for "the Remainder of the
Works" must be used to cover the balance of the Works if the Sections
described do not in total comprise the whole of the Works.
c Delete where not
required.
d (If used) Materials
to which the Clauses apply must be listed in Part I (Employer's option) or Part
2 (Contractor's option)
e > Insert here any
amendment or modification adopted if different from that stated in Clause 57.
f If there is any
requirement that the Engineer has to obtain prior approval from the Employer
before he can act full particulars of such requirements must be set out above.
g Delete as appropriate
Appendix A - Part 2<
(To
be completed by Contractor)
1 Insurance
Policy Excesses (Clause 25(2))
Insurance
of the Works (Clause 21(1)) £...............
Third
party (property damage) (Clause 23(1)) £...............
2 Period
for completion of the whole works
………….Weeks
3 Vesting of materials not on Site
(Clauses 54(2) & 60(1)(d)) (if required by the Contractor)
1 ………………………………… 4 .…………………………………
2 ………………………………… 5 ……………………………………
3 ………………………………… 6 ……………………………………
4 Percentage
adjustment for Prime Cost Items (Clause 58(2)) ………….. %
5 Contractor’s
designer (Clause 4(2)(a))
The design work for which the Contractor is responsible will
be carried out by
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
Elements
for which the Contractor has not yet appointed a designer.
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
……………………………………………………………………………………………
Form of Tender
(Appendix)
Appendix
B
Collusive Tendering
Certificate
We certify that this is a bona
fide tender, and that we have not fixed or adjusted the amount of the tender by
or under or in accordance with any agreement or arrangement with any other
person. We also certify that we have
not done and we undertake that we will not do at any time before the hour and
date specified for the return of this tender any of the following acts:
a communicating to a person other than the person calling
for those tenders the amount or approximate amount of the proposed tender,
except where the disclosure, in confidence, of the approximate amount of the
tender was necessary to obtain insurance premium quotations required for the
preparation of the tender;
b entering into any agreement or arrangement with any
other person that he shall refrain from tendering or as to the amount of any
tender to be submitted;
c offering or paying or giving or agreeing to pay or give
any sum of money or valuable consideration directly or indirectly to any person
for doing or having done or causing or having caused to be done in relation to
any other tender or proposed tender for the said work any act or thing of the
sort described above.
In this certificate, the word
"person" includes any persons and anybody or association, corporate
or unincorporate; and "any agreement or arrangement" includes any
such transaction, formal or informal, and whether legally binding or not.
Signed: .......................................................
On Behalf of: .......................................................
.......................................................
.......................................................
Date: .......................................................
Form of Tender (Appendix)
Appendix
C
LIST OF SUB-CONTRACTORS
NOTE: This information is required for guidance in
the assessment of Tenders and shall be completed at the time of tendering
|
Work or Service |
Name and Address of Sub-Contractor |
Brief Details of Previous Similar
Work and Employer |
|
|
|
|
FORM OF
AGREEMENT
THIS AGREEMENT made
the .............................. day of ....................................
2003 BETWEEN Century
Park Limited of Edwards Centre, The Horsefair, Hinckley in the County of Leicestershire.
(hereinafter called "the Employer") and
........................................... of
........................................................ in the County of ...............................................................................................
(hereinafter called "the Contractor").
WHEREAS the Employer
is desirous that certain Works should be designed and constructed, namely the
Permanent and Temporary Works in connection with the engineered filling of part
of the former Midland Quarry, Tuttle Hill, Nuneaton and has accepted a Tender
by the Contractor for the design, construction and completion of such
Works.
NOW THIS AGREEMENT
WITNESSETH as follows:
1. In this Agreement words and
expressions shall have the same meanings as are respectively assigned to them
in the Conditions of Contract hereinafter referred to.
2. The following documents shall be
deemed to form and be read and construed as part of this Agreement :
(a) The
said Tender and written acceptance thereof.
(b) The Drawings.
(c) The Conditions of Contract.
(d) The Description of Works.
(e) The Specification.
(f)
The Employer’s Requirements
(g)
The following Documents:
3. In consideration of the payments to
be made by the Employer to the Contractor as hereinafter mentioned the
Contractor hereby covenants with the Employer to design construct and complete
the Works in conformity in all respects with the provisions of the Contract.
4.
The Employer hereby
covenants to pay to the Contractor in consideration of the design, construction
and completion of the Works the Contract Price at the times and in the manner
prescribed by the Contract.
5.
IN WITNESS whereof
the parties have caused this Agreement to be executed the day and year first
above written.
SIGNED SEALED AND
DELIVERED AS A DEED
by the
said...................................................................................PLC/LIMITED
In the presence of
..........................................................................................
SIGNED SEALED AND
DELIVERED AS A DEED
by the
said...................................................................................PLC/LIMITED
In the presence of
..........................................................................................
Conditions of
Contract
The Conditions of Contract shall be
the ICE Design and Construct Conditions of Contract and Forms of Tender and
Agreement for use in connection with Works of Civil Engineering Construction –
First Edition 1992 (re-printed 1997) approved by the Institution of Civil
Engineers, the Association of Consulting Engineers and the Federation of Civil
Engineering Contractors as amended by Amendment Reference
ICE/D&C/Tax/February 1998 and Amendment Reference ICE/D&C/HGCR/March
1998 – as modified and added to by the following:
Delete existing Clause 71
Add: THE
CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 1994
CDM Regulations 71 (1) In this Clause
1994
(a)
“the Regulations” means the Construction (Design and Management)
Regulations 1994 or a statutory re-enactment or amendment thereof for the time
being in force.
(b)
“Planning Supervisor” and “Principal Contractor” means the persons so
described in regulation 2(1) of the Regulations.
(c)
“Health and Safety Plan” means the plan prepared by virtue of regulation
15 of the Regulations.
(2)
Where and to the extent that the Regulations apply to the Works and:
(a)
the Employer’s Representative is appointed Planning Supervisor and/or
(b)
the Contractor is appointed Principal Contractor.
then in taking
any action as such they state in writing that the action is being taken under
the Regulations.
(3) (a) any action under the Regulations taken
by either the Planning Supervisor or the Principal Contractor and in particular
any alteration or amendment to the
Health and Safety Plan shall be deemed to be an instruction by the Employer’s
Representative or a notification by the Contractor as the case may be. Where appropriate additional payment and/or
extension of shall be assessed in accordance with Clause 52. Provided that the Contractor shall in no
event be entitled to any additional payment and/or extension of time in respect
of any such action to the extent that it results from any lack of action or
default on the part of the Contractor.
<(b)
if any such action of either the Planning Supervisor or the Principal
Contractor could not in the Contractor’s opinion reasonably have been foreseen
by an experienced Contractor the Contractor shall as early as practicable give
written notice thereof to the Employer’s Representative.
Clause 72
Special Conditions
The
following Special Conditions form part of the Conditions of Contract
Clause 73 Gifts
Inducements and Rewards
The Employer
shall be entitled to terminate the employment of the Contractor and to recover
from the Contractor the amount of any loss resulting from such cancellation if
the Contractor shall have offered or given or agreed to give any person any
gift or consideration of any kind as an inducement or reward for doing or
forbearing to do or for having done or forborne to do any action in relation to
the obtaining or execution of this Contract or any other Contract with the
Employer or for showing or forbearing to show favour or disfavour to any person
in relation to this Contract or any other Contract with the Employer or if any
of the like acts shall have been done by any person employed by the Contractor
or acting on his behalf (whether with or without the knowledge of the
Contractor) or if in relation to this Contract or any other Contract with the
Employer the Contractor or any person employed by him or acting on his behalf
shall have committed any offence under the Prevention of Corruption Acts, 1889
to 1916, or shall have given any fee or reward the receipt of which is an
offence under subsection (2) of Section 117 of the Local Government Act
1972. Where any such gift or inducement
or reward has been made or promised in relation to the obtaining or the
execution of the Contract or any subcontract hereunder to any officer or person
in the service of the Employer who shall be in any way connected with the
obtaining or the execution of the Contract or any sub-contract hereunder the
Contractor shall also be liable to pay to the Employer by way of liquidated
damages a sum equal to ten per cent of all the sums paid and payable to him
under the Contract by the Employer. Any
dispute as to the amount recoverable by the Employer from the Contractor as a
result of termination hereunder shall be settled in the manner provided by
Clause 66 hereof.
Clause74 Recovery
of Sums Due from Contractor
Whenever under the Contract any sum of money shall be
recoverable from or payable by the Contractor such sum may be deducted from or
reduced by the amount of any sum or sums then due or which at any time
thereafter may become due to the Contractor under the Contract or any other
contract with the Employer.
Contract Price Fluctuations shall not apply to the
Contract.
1. The
Contract Works are of a confidential nature.
All information, documents and drawings relating thereto shall be
confined to the Contractor, his sub-contractors and their respective employees.
2. Upon
the request of the Employer, the Contractor and his sub-contractors shall sign
a confidentiality undertaking in the form required by the Employer
The Contractor shall not without the previous consent of the
Employer use the Contract or the Works in any way for the purpose of
advertisement or publicity.
In accordance with Clause 31 of the Conditions of Contract
the Contractor’s attention is drawn to the fact that the Employer and other
Contractors will be operating within and in the vicinity of the Site. The Contractor will be required to liaise
fully with the Employer and the Employer’s Representative so as to ensure a
minimum of conflict between his own operations and those of others and shall
programme the movement of this own, his Sub-Contractors, and his suppliers,
plant and vehicles to reduce congestion on the site and roads to a minimum.
The Contractor shall give an undertaking and so instruct all
personnel in his direct and indirect employ that the rights and enjoyments of
all persons attaching to lands and facilities comprising the site of the Works
or adjacent to, will not in any way be impaired, prejudiced reduced, altered or
limited by activities and conduct of persons performing the Works. Such rights include, but are not limited to,
ownership, tenancy, recreation, production, shooting, fishing, game keeping,
walking, riding and other movement to and fro along a recognised path.
The Contractor shall make all necessary enquiries and
physical investigation to determine the presence and location of Statutory
Undertakers' property and equipment, including drainage pipes and manholes, and
any privately owned services on under and within the immediate vicinity of the
Site. To ensure the safety of such
Statutory Undertakers' property and equipment the Contractor shall arrange if
necessary for the Statutory Undertakers to mark out the position of their
property and equipment on the ground.
The Contractor shall ensure that the marked out position of any
Statutory Undertakers property and equipment is maintained throughout the
Works. The Contractor shall comply with
all special requirements of Statutory Undertakers and take all necessary precautions
during the execution of the Works to ensure that Statutory Undertakers'
property and equipment is not damaged.
If the same is damaged by the Contractor, the Contractor shall
immediately inform the Employer’s Representative and Statutory Undertaker. The cost of repair to any damaged Statutory
Undertakers' property and equipment caused by the Contractor during the Works
shall be met in full by the Contractor.
The information in the Contract documents as to the whereabouts of
existing services and mains is believed to be correct but the Contractor shall
not be relieved of his obligations under Clause 11 and 12 of the Conditions of
Contract. The Contractor shall keep the
Employer’s Representative informed of all arrangements he makes with the Statutory
Undertakers.
The Contractor
shall take precautions to prevent damage to property of any kind on or adjacent
to the Site, in or through which the Works and works activities will be
executed. Any damage shall be promptly
made good. All such damage and claims
for damage shall be recorded and reported to the Employer’s
Representative. In the case of damage
to private property, the Employer’s Representative shall be immediately
informed whatever the circumstances.
Unless otherwise directed by the Employer’s Representative,
the Contractor shall at his own expense permanently reinstate all areas on or
off the Site disturbed by him in connection with the execution of the Works,
including surfaces, walls, fences, grassed areas etc., to a condition
equivalent to that existing before the commencement of the Works and shall
provide all materials required. All
such reinstatement shall be to the approval and satisfaction of the Employer’s
Representative and the Authorities, Owners and Occupiers concerned. Highway reinstatement shall be in accordance
with the New Roads and Streetworks Act 1991 and the Specification for the
Excavation and Reinstatement of Openings in Highways (HAUC SWP 163) September
1991.
Clause
83 Cleaning of Roads, including
Carriageways and Paved or Grassed Verges, Drains and Sewers
1. In the event of highways, tracks, accesses and
haul roads becoming dirtied as a result of the Contractor's operations, the
Contractor shall, at his own expense, take all necessary measures to
immediately clean and/or repair them.
2. The Contractor shall prevent the obstruction or
contamination of all drains and sewers.
The
Contractor and all Sub-Contractors engaged by the Contractor shall comply with
the provisions of all appropriate Health and Safety related legislation
including, the Health and Safety at Work etc Act 1974 and all Regulations made
thereunder, including the Management of Health and Safety at Work Regulations
1992, The Construction (Design and Management) Regulations 1994, and the
Construction (Health, Safety and Welfare) Regulations 1996. The Contractor and all Sub-Contractors
employed by the Contractor shall also comply with the requirements of all
appropriated Approved Codes of Practice, Guidance documents and other
recommendations in support of the above Acts or Regulations issued by the
Health and Safety Executive.
SECTION A
Tender
Document for Engineered Filling of Part of Former Midland Quarry, Tuttle Hill,
Nuneaton
Instructions to Tenderers
1 These instructions to Tenderers are
issued for the guidance of Tenderers and shall not form part of the
Contract. Failure to comply with these
instructions may result in rejection of the tender.
2 Tenderers shall study the Tender
Documents, visit the site and shall be deemed to have satisfied themselves on
all matters affecting their Tender.
3 Tenderers shall complete and return
copies of the following Documents:-
a) Form of Tender and Appendices A-C to
the Form of Tender
4 The Tender shall be sent by registered
post or delivered by hand in a sealed envelope bearing no mark identifying the
Tenderer either on the envelope or in the franking thereon, and shall be
clearly marked:
Tender
for Engineered Filling of Part of Former Midland Quarry, Tuttle Hill, Nuneaton
The envelope shall be addressed to:
Wardell Armstrong
Thynne Court
Thynne
Street
West
Bromwich
West
Midlands B70 6PH
Tenders should arrive no later than
12 noon on Wednesday 16 July 2003.
5 Tenders are to remain open for
acceptance for a period of 90 days from the date for receipt of Tenders.
6 Tenders not received by the time
specified may not be considered.
7 The Employer shall not be bound to
accept the lowest or any tender.
9
The Tenderer is to
submit with his Tender the following documents for all work including that of
sub-contractors, which will be considered to be essential parts of the complete
tender submission:
·
A programme showing
the order in which the various sections of the Works described in the Contract
Documents are to be undertaken and the time which the Tenderer estimates he
will require to complete the Contract.
·
An outline
method statement indicating the procedures by which the Tenderer proposes to
undertake the works and execute the Contract.
·
An outline Health and
Safety Plan prepared in accordance with the Construction (Design and
Management) Regulations 1994.
·
a copy of their
Company's Safety Policy.
·
details of how the
security of the site will be managed.
·
details of any
proposed external Safety Consultant, if any.
·
a copy of their
insurance certificate(s) detailing the extent of cover to be provided under the
Contract.
<· Preliminary drawings and specifications in sufficient detail
to enable the Employer to assess the Tenderers proposals;
·
a list of proposed
sub contractors;
·
specification Table 6/1
·
the following
Appendices to the Specification duly completed:
Appendix 1/5
Appendix 5/1
Appendix 5/2
Appendix 6/5
·
completed Contract
Sum Analysis and break down of the Lump
Sum Build Up and Schedule of Rates (attached as part of Section G to the tender);
.
Preparation of Tenders
9 The Tender must be compiled on the
basis of the documents listed in the Form of Agreement, based on the ICE Design
and Construct Conditions of Contract – First Edition and Amendments to the ICE
Conditions of Contract to take into account The Finance Act 1996 (Sections
39-71 and Schedule 5) and the Landfill Tax Regulations 1996
(ICE/D&C/Tax/February 1998) and Amendments to the ICE Conditions of
Contract to take into account The Housing Grants, Construction and Regeneration
Act 1996 (Part II) (ICE/D&C/HGCR/March 1998), modified and added to by the
Modifications and Additions to Clauses together with the Special Conditions of
Contract.
10 Tenderers shall be prepared to supply to
the Employer copies of their last 3 years audited accounts within 7 days, if
requested.
11 No alternative tender will be considered
unless a Tender free from qualifications and strictly on the basis of these
Tender Documents is also submitted.
12 Should any alterations or additions to
the Tender Documents be deemed necessary during the Tender Period, these shall
be notified in writing to the Tenderers and shall form part of the Tender
Documents.
13 No unauthorised alteration or addition
is to be made or qualification added to the Tender Documents. Such alteration, addition or qualification
may result in the Tender being rejected.
14 The contract is to be a Firm Price and
does not include a Price Fluctuation clause.
15 All expenses incurred in the preparation
and submission of the Tender shall be borne by the Tenderer.
16 The Employer and/or the Employer’s
Representative accept no responsibility for the arithmetical or other
inaccuracy of the Tender.
17 Any queries with regard to tendering or visiting the site
shall be directed to Tom Bason (tel 0121 580 0909) or Douglas Brownjohn (tel
01942 260101) at Wardell Armstrong. Any query concerning any aspect of the
Tender shall be referred to the Employer’s Representative in writing. The Tenderer shall abide by the written
interpretation of the Employer’s Representative, providing that such written
interpretation is received at least 3 days before the date on which the Tender
is to be submitted. The Tenderer, if
not in receipt of such written interpretation within the said 3 days shall
attach to his Tender a covering letter stating the interpretation on which his
Tender is based.
22
Tenderers will
be required to provide before award of the Contract, CV's for the Company
Safety Manager and the proposed Site Manager indicating their specific experience
on earthworks projects of a similar nature, their period of service with the
company, details of training/safety courses attended and any other relevant
information.
23
The Tenderers
shall include for all items necessary to complete the works.
24
All design and
other fees shall be included in the Contractor's Tender Sums.
25
The Tender Sum
for carrying out the works shall include for all general preliminaries.
Form of Tender
Form of Tender Appendix A – Parts
1 and 2
Form of Tender Appendix B
Form of Tender Appendix C
Form of Agreement
Short Description of Works
All the Design and Permanent and
Temporary Works in connection with the engineered filling operations of part of
the former Midland Quarry, Tuttle Hill, Nuneaton. Including site clearance
operations, bulk earthworks, the import of acceptable inert fill material (if
necessary), the compaction and placement of fill, the construction of a
reinforced earth slope (45°) and ancillary works.
FORM
OF TENDER
(NOTE:
The Appendices form part of the Tender)
To: Century Park Limited
Edwards
Centre
The
Horsefair
Hinckley
Leicestershire
LE10
0AW
Gentlemen,
Having examined the Employer’s
Requirements, Conditions of Contract, Drawings for the above mentioned works
(and the matters set out in the Appendices hereto), we offer to design
construct and complete the said Works and maintain the Permanent Works in
conformity with the said Employer’s Requirements, Conditions of Contract, and
Drawings Specification for the sum of ¼¼¼¼¼¼¼¼¼¼¼¼¼¼¼¼. (words) £¼¼¼¼¼¼¼ or such other sum as shall become payable in accordance
with the said Conditions of Contract.
We undertake to complete and
deliver the whole of the Permanent Works comprised in the Contract within the
time stated in the Appendix hereto.
If our tender is accepted we
will, when required, provide Performance Security as defined in the said
Conditions of Contract for the due performance of the Contract under the terms
of a Bond.
Unless and until a formal
Agreement is prepared and executed this Tender, together with your written
acceptance thereof, shall constitute a binding Contract between us.
We understand that you are not
bound to accept the lowest or any tender you may receive.
We are, Gentlemen
Yours faithfully,
Signature .......................................................
Address .......................................................
.......................................................
.......................................................
.......................................................
.......................................................
Date: .......................................................
FORM OF TENDER (APPENDIX)
(NOTE: Relevant Clause numbers
are shown in brackets).
1 Name of the Employer (Clause
1(1)(a)): Century Park Limited
Address:
Edwards Centre, The Horsefair, Hinckley, Leicestershire, LE10 0AW
2 Name
of the Employer’s Representative (Clause 1(1)(c))and 2(2)) To
be Appointed
Address:
3 Defects
Correction Period (Clause 1(1)(p)): 52 weeks
4 Quality
Assurance (Clause8 (3)) Not
required
5 Contract
Agreement (Clause 9):
Required Required
6 Performance
Security (Clause 10(i)): Required Required
Amount (if required) to be:
10% of Estimated
Contract
Price 10%
of Tender Total
7 Minimum
amount of third party insurance (persons and property) (Clause 23(3): £5,000,000
for each
and
every occurrence
Unlimited
Occurrences.
8 Works
Commencement Date (if known) (Clause 41(1)(a): To
be agreed
9 Time
for Completion (Clause 43)a:
For
the whole of the Works
weeks
11
Liquidated
damages for delay (Clause 47)
For the whole of the Works £2,000
per week Limit of Liability £50,000
11 Not
required
12 Percentage
of the value of goods and materials to be included
in
Interim Certificates (Clause 60(2)(ii)): 75%
13 Minimum
amount of Interim Certificates (Clause 60(3)): £20,000
14 Rate
of retention (recommended not to exceed 5%) (Clause 60(5(a))): 5%
16
Limit
of retention (% of Tender Total) (Clause 60(5)(a))
(Recommended
not to exceed 5%): 5%
16 Bank
whose Base Lending Rate is to be used (Clause 60(7): National Westminster
17 Name
of the Planning Supervisor (Clause 71(1)(b)): Simon
Gibbs
Address: Innovative Minerals Processing Ltd, P O Box
1638, Stafford ST19 9RP
18 Name
of the Principal Contractor (Clause 71(1)(b)): The Contractor
Address:
19 The
arbitration Procedure to be used is (Clause 66(11)(a))
(c)
The
Institution of Civil Engineers’ Arbitration Procedure (1997)g or
(d)
The Construction Industry Modell Arbitration Rulesg
a If
not stated is to be completed by Contractor in Part 2 of the Appendix.
b To be completed if
required, with brief description. Where
Sectional completion applies the item for "the Remainder of the Works"
must be used to cover the balance of the Works if the Sections described do not
in total comprise the whole of the Works.
c Delete where not
required.
d (If used) Materials
to which the Clauses apply must be listed in Part I (Employer's option) or Part
2 (Contractor's option)
e > Insert here any
amendment or modification adopted if different from that stated in Clause 57.
f If there is any
requirement that the Engineer has to obtain prior approval from the Employer
before he can act full particulars of such requirements must be set out above.
g Delete as appropriate
Appendix A - Part 2<
(To
be completed by Contractor)
1 Insurance
Policy Excesses (Clause 25(2))
Insurance
of the Works (Clause 21(1)) £...............
Third
party (property damage) (Clause 23(1)) £...............
2 Period
for completion of the whole works
………….Weeks
3 Vesting of materials not on Site
(Clauses 54(2) & 60(1)(d)) (if required by the Contractor)
1 ………………………………… 4 .…………………………………
2 ………………………………… 5 ……………………………………
3 ………………………………… 6 ……………………………………
4 Percentage
adjustment for Prime Cost Items (Clause 58(2)) ………….. %
5 Contractor’s
designer (Clause 4(2)(a))
The design work for which the Contractor is responsible will
be carried out by
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
Elements
for which the Contractor has not yet appointed a designer.
…………………………………………………………………………………………….
…………………………………………………………………………………………….
…………………………………………………………………………………………….
……………………………………………………………………………………………
Form of Tender
(Appendix)
Appendix
B
Collusive Tendering
Certificate
We certify that this is a bona
fide tender, and that we have not fixed or adjusted the amount of the tender by
or under or in accordance with any agreement or arrangement with any other
person. We also certify that we have
not done and we undertake that we will not do at any time before the hour and
date specified for the return of this tender any of the following acts:
a communicating to a person other than the person calling
for those tenders the amount or approximate amount of the proposed tender,
except where the disclosure, in confidence, of the approximate amount of the
tender was necessary to obtain insurance premium quotations required for the
preparation of the tender;
b entering into any agreement or arrangement with any
other person that he shall refrain from tendering or as to the amount of any
tender to be submitted;
c offering or paying or giving or agreeing to pay or give
any sum of money or valuable consideration directly or indirectly to any person
for doing or having done or causing or having caused to be done in relation to
any other tender or proposed tender for the said work any act or thing of the
sort described above.
In this certificate, the word
"person" includes any persons and anybody or association, corporate
or unincorporate; and "any agreement or arrangement" includes any
such transaction, formal or informal, and whether legally binding or not.
Signed: .......................................................
On Behalf of: .......................................................
.......................................................
.......................................................
Date: .......................................................
Form of Tender (Appendix)
Appendix
C
LIST OF SUB-CONTRACTORS
NOTE: This information is required for guidance in
the assessment of Tenders and shall be completed at the time of tendering
|
Work or Service |
Name and Address of Sub-Contractor |
Brief Details of Previous Similar
Work and Employer |
|
|
|
|
FORM OF
AGREEMENT
THIS AGREEMENT made
the .............................. day of ....................................
2003 BETWEEN Century
Park Limited of Edwards Centre, The Horsefair, Hinckley in the County of Leicestershire.
(hereinafter called "the Employer") and
........................................... of
........................................................ in the County of
...............................................................................................
(hereinafter called "the Contractor").
WHEREAS the Employer
is desirous that certain Works should be designed and constructed, namely the
Design, Permanent and Temporary Works in connection with the engineered filling
of part of the former Midland Quarry, Tuttle Hill, Nuneaton and has accepted a
Tender by the Contractor for the design, construction and completion of such
Works.
NOW THIS AGREEMENT
WITNESSETH as follows:
1. In this Agreement words and
expressions shall have the same meanings as are respectively assigned to them
in the Conditions of Contract hereinafter referred to.
2. The following documents shall be
deemed to form and be read and construed as part of this Agreement :
(a) The said Tender and written acceptance thereof
(b) The Conditions of Contract
(c) The Employer’s Requirements
(d) The Description of Works.
(e) Specification
(h)
Lump Sum Build
Up/Schedule of Rates
(i)
Collateral Warranty
(j)
Appendices 1-8
3. In consideration of the payments to
be made by the Employer to the Contractor as hereinafter mentioned the
Contractor hereby covenants with the Employer to design construct and complete
the Works in conformity in all respects with the provisions of the Contract.
6.
The Employer hereby
covenants to pay to the Contractor in consideration of the design, construction
and completion of the Works the Contract Price at the times and in the manner
prescribed by the Contract.
IN WITNESS whereof
the parties have caused this Agreement to be executed the day and year first
above written.
SIGNED SEALED AND
DELIVERED AS A DEED
by the
said...................................................................................PLC/LIMITED
In the presence of
..........................................................................................
SIGNED SEALED AND
DELIVERED AS A DEED
by the
said...................................................................................PLC/LIMITED
In the presence of
..........................................................................................
Conditions of
Contract
The Conditions of Contract shall be
the ICE Design and Construct Conditions of Contract and Forms of Tender and
Agreement for use in connection with Works of Civil Engineering Construction –
First Edition 1992 (re-printed 1997) approved by the Institution of Civil
Engineers, the Association of Consulting Engineers and the Federation of Civil
Engineering Contractors as amended by Amendment Reference ICE/D&C/Tax/February
1998 and Amendment Reference ICE/D&C/HGCR/March 1998 – as modified and
added to by the following:
Delete existing Clause 71
Add: THE
CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 1994
CDM Regulations 71 (1) In this Clause
1994
(d)
“the Regulations” means the Construction (Design and Management)
Regulations 1994 or a statutory re-enactment or amendment thereof for the time
being in force.
(e)
“Planning Supervisor” and “Principal Contractor” means the persons so
described in regulation 2(1) of the Regulations.
(f)
“Health and Safety Plan” means the plan prepared by virtue of regulation
15 of the Regulations.
(3)
Where and to the extent that the Regulations apply to the Works and:
(c)
the Employer’s Representative is appointed Planning Supervisor and/or
(d)
the Contractor is appointed Principal Contractor.
then in taking
any action as such they state in writing that the action is being taken under
the Regulations.
(3) (a) any action under the Regulations taken
by either the Planning Supervisor or the Principal Contractor and in particular
any alteration or amendment to the
Health and Safety Plan shall be deemed to be an instruction by the Employer’s
Representative or a notification by the Contractor as the case may be. Where appropriate additional payment and/or
extension of shall be assessed in accordance with Clause 52. Provided that the Contractor shall in no
event be entitled to any additional payment and/or extension of time in respect
of any such action to the extent that it results from any lack of action or
default on the part of the Contractor.
<(c)
if any such action of either the Planning Supervisor or the Principal
Contractor could not in the Contractor’s opinion reasonably have been foreseen
by an experienced Contractor the Contractor shall as early as practicable give
written notice thereof to the Employer’s Representative.
Clause 72
Special Conditions
The
following Special Conditions form part of the Conditions of Contract
Clause 73 Gifts
Inducements and Rewards
The Employer
shall be entitled to terminate the employment of the Contractor and to recover
from the Contractor the amount of any loss resulting from such cancellation if
the Contractor shall have offered or given or agreed to give any person any
gift or consideration of any kind as an inducement or reward for doing or
forbearing to do or for having done or forborne to do any action in relation to
the obtaining or execution of this Contract or any other Contract with the
Employer or for showing or forbearing to show favour or disfavour to any person
in relation to this Contract or any other Contract with the Employer or if any
of the like acts shall have been done by any person employed by the Contractor
or acting on his behalf (whether with or without the knowledge of the Contractor)
or if in relation to this Contract or any other Contract with the Employer the
Contractor or any person employed by him or acting on his behalf shall have
committed any offence under the Prevention of Corruption Acts, 1889 to 1916, or
shall have given any fee or reward the receipt of which is an offence under
subsection (2) of Section 117 of the Local Government Act 1972. Where any such gift or inducement or reward
has been made or promised in relation to the obtaining or the execution of the
Contract or any subcontract hereunder to any officer or person in the service
of the Employer who shall be in any way connected with the obtaining or the
execution of the Contract or any sub-contract hereunder the Contractor shall
also be liable to pay to the Employer by way of liquidated damages a sum equal
to ten per cent of all the sums paid and payable to him under the Contract by
the Employer. Any dispute as to the
amount recoverable by the Employer from the Contractor as a result of
termination hereunder shall be settled in the manner provided by Clause 66
hereof.
Clause74 Recovery
of Sums Due from Contractor
Whenever under the Contract any sum of money shall be
recoverable from or payable by the Contractor such sum may be deducted from or
reduced by the amount of any sum or sums then due or which at any time
thereafter may become due to the Contractor under the Contract or any other
contract with the Employer.
Contract Price Fluctuations shall not apply to the Contract.
1. The
Contract Works are of a confidential nature.
All information, documents and drawings relating thereto shall be
confined to the Contractor, his sub-contractors and their respective employees.
2. Upon
the request of the Employer, the Contractor and his sub-contractors shall sign
a confidentiality undertaking in the form required by the Employer
The Contractor shall not without the previous consent of the
Employer use the Contract or the Works in any way for the purpose of
advertisement or publicity.
In accordance with Clause 31 of the Conditions of Contract
the Contractor’s attention is drawn to the fact that the Employer and other
Contractors will be operating within and in the vicinity of the Site. The Contractor will be required to liaise
fully with the Employer and the Employer’s Representative so as to ensure a
minimum of conflict between his own operations and those of others and shall
programme the movement of this own, his Sub-Contractors, and his suppliers,
plant and vehicles to reduce congestion on the site and roads to a minimum.
The Contractor shall give an undertaking and so instruct all
personnel in his direct and indirect employ that the rights and enjoyments of
all persons attaching to lands and facilities comprising the site of the Works
or adjacent to, will not in any way be impaired, prejudiced reduced, altered or
limited by activities and conduct of persons performing the Works. Such rights include, but are not limited to,
ownership, tenancy, recreation, production, shooting, fishing, game keeping,
walking, riding and other movement to and fro along a recognised path.
The Contractor shall make all necessary enquiries and
physical investigation to determine the presence and location of Statutory
Undertakers' property and equipment, including drainage pipes and manholes, and
any privately owned services on under and within the immediate vicinity of the
Site. To ensure the safety of such
Statutory Undertakers' property and equipment the Contractor shall arrange if
necessary for the Statutory Undertakers to mark out the position of their
property and equipment on the ground.
The Contractor shall ensure that the marked out position of any
Statutory Undertakers property and equipment is maintained throughout the
Works. The Contractor shall comply with
all special requirements of Statutory Undertakers and take all necessary
precautions during the execution of the Works to ensure that Statutory
Undertakers' property and equipment is not damaged. If the same is damaged by the Contractor, the Contractor shall
immediately inform the Employer’s Representative and Statutory Undertaker. The cost of repair to any damaged Statutory
Undertakers' property and equipment caused by the Contractor during the Works
shall be met in full by the Contractor.
The information in the Contract documents as to the whereabouts of
existing services and mains is believed to be correct but the Contractor shall
not be relieved of his obligations under Clause 11 and 12 of the Conditions of
Contract. The Contractor shall keep the
Employer’s Representative informed of all arrangements he makes with the
Statutory Undertakers.
The Contractor
shall take precautions to prevent damage to property of any kind on or adjacent
to the Site, in or through which the Works and works activities will be executed. Any damage shall be promptly made good. All such damage and claims for damage shall
be recorded and reported to the Employer’s Representative. In the case of damage to private property,
the Employer’s Representative shall be immediately informed whatever the
circumstances.
Unless otherwise directed by the Employer’s Representative,
the Contractor shall at his own expense permanently reinstate all areas on or
off the Site disturbed by him in connection with the execution of the Works,
including surfaces, walls, fences, grassed areas etc., to a condition
equivalent to that existing before the commencement of the Works and shall
provide all materials required. All
such reinstatement shall be to the approval and satisfaction of the Employer’s
Representative and the Authorities, Owners and Occupiers concerned. Highway reinstatement shall be in accordance
with the New Roads and Streetworks Act 1991 and the Specification for the
Excavation and Reinstatement of Openings in Highways (HAUC SWP 163) September
1991.
Clause
83 Cleaning of Roads, including
Carriageways and Paved or Grassed Verges, Drains and Sewers
1. In the event of highways, tracks, accesses and
haul roads becoming dirtied as a result of the Contractor's operations, the
Contractor shall, at his own expense, take all necessary measures to
immediately clean and/or repair them.
2. The Contractor shall prevent the obstruction or
contamination of all drains and sewers.
The
Contractor and all Sub-Contractors engaged by the Contractor shall comply with
the provisions of all appropriate Health and Safety related legislation
including, the Health and Safety at Work etc Act 1974 and all Regulations made
thereunder, including the Management of Health and Safety at Work Regulations
1992, The Construction (Design and Management) Regulations 1994, and the
Construction (Health, Safety and Welfare) Regulations 1996. The Contractor and all Sub-Contractors
employed by the Contractor shall also comply with the requirements of all
appropriated Approved Codes of Practice, Guidance documents and other
recommendations in support of the above Acts or Regulations issued by the
Health and Safety Executive.
Employer’s
Requirements
EMPLOYERS REQUIREMENTS
1.
The purpose of this
section is to identify the scope of works, design standards and constraints
which will apply to the works required in the design and construction of the
reinforced earth slope and engineered earthworks to infill the eastern section
of the void at Midland Quarry. Further
information and requirements are given in Section E Description of Works.
2.
The Employer
requires the construction of a reinforced earth wall and the infilling of the
eastern part of the void at Midland Quarry as a precursor to subsequent
residential, leisure and retail development by others. The Contractor will be
required to maximise the area available for building development. The
Contractor shall provide supporting information to demonstrate the developable
area, and areas associated with the quarry high wall which are sterilised for
development. The derivation of such areas shall be supported by analysis of the
predicted settlement of the infill materials.
3.
The Contractor
shall commission his own design consultants to develop the scheme and shall be
entirely responsible for the design and construction of the Works. The scheme designs included within the
Tender Documentation are indicative only and the Contractor is free to develop
his own detailed design as he sees fit within the limits indicated.
4.
Throughout the
construction period the Contractor’s designs, specification and construction of
the Works will be reviewed by the Employer's Representative as appropriate.
Specific items of work which require to be referred to the Employer's
Representative are noted in this document.
The Employer's Representative will provide input to any aspect of the
design, construction and maintenance process as he deems necessary in the form
of design briefs and comment on design.
5.
Whilst the
Employer’s Requirements includes copies of two site investigation reports it is
the Contractor’s responsibility to determine the existing ground conditions,
including the carrying out of any further site investigation.
6.
It is the
Contractor's responsibility to establish the actual existing site levels shown
on the drawings by either checking the information within this document or by
carrying out his own level survey.
7.
The Contractor will
be required to enter into Collateral Warranties with subsequent Developers/Leasees/Funders of the
development scheme. The General Form of the Collateral Warranty is included as
Appendix 2.
Section E
1.
Site Description
and Background
1.1
The Midland Quarry
site is located approximately 1.5 km to the north west of the town of Nuneaton,
off Tuttle Hill (B4114) as shown on Drawing WM02457/101.
1.2 The site is a hardrock quarry that has been dormant for some time. Since March 2002 some preparatory works, including site clearance and infilling works to the eastern end of the void, have taken place. Drawing WM02457/102 indicates levels prior to any works being undertaken, whilst Drawing WM02457/103 indicates levels post works carried out in 2002. Digital versions of both surveys are available on request. It is also proposed that others will extract a further 5 million tonnes of rock from the southern wall of the existing quarry upon completion of this Contract.
Superficial Deposits
Solid Geology
· Woodlands Member, massive arkosic sandstone with subordinate shale;
· Home Farm Member, conglomeratic, micritic limestone;
· Jees Member, buff to dark red micaceous sandstone with shale;
· Tuttle Hill Member, grey to red brown arkosic sandstone with mudstone and sparse conglomerate;
· Park Hill Member, massive grey arkosic sandstone.
2
Scope of Works
2.1 The Contractor shall be responsible for the design and
construction of the following:
· Reinforced Earth Slope;
· Engineered Infill to required levels;
· Excavation of existing quarry overburden mound.
3
Reinforced Earth
Slope
3.1 The
Contractor shall design and construct a reinforced earth slope in the
approximate location shown on Drawing WM02457/104. The Contractor shall design
the slope such that the crest of the slope is not further east than the line
indicated on Drawing WM02457/103 and not higher than the proposed levels
indicated. The slope shall have a 45 degree face.
3.2 The reinforced earth
slope shall be designed to accommodate the following:
·
A Industrial
Distributor Road (7.3m carriageway and 2.0m footpaths) constructed to adoptable
standards at a minimum 2.0m from the crest of the slope;
·
The potential to
include an access road constructed on a 10m wide berm running across the slope
from 94.4m down to 70.0m for access to the water body in the main void – the
location and gradient of such a road have not been identified and it will be
the responsibility of the Contractor to establish the requirement for such a
road in consultation with the Employer;
·
The construction of,
up to, 3 storey buildings, constructed on raft foundations with loadings of between
75 to 120 kn/m2, at a minimum 5.0m from the crest of the slope;
·
No geotextile within
the top 3.0m of the slope to accommodate the construction of roads, foundation,
services etc;
·
The variable
topography of the base and sides of the existing void in the area of the
proposed slope – the Contractor must include within his design for all
necessary excavation of rock and loose materials to permit the construction of
the slope, and for any necessary anchoring of the geotextile to the rock faces
at the sides of the slope;
·
Inundation of the
fill materials within the reinforced slope, and to the rear, to a level of at
least 85 mAOD;
·
The rapid draw down
of the main water body (after completion of the construction works) from 85
mAOD to below the base of the slope;
3.3 The slope
shall be finished with a suitable protective face beneath, and just above the
water level, and a suitable medium above to allow vegetation of the slope. All
finishes shall be in keeping with the remaining quarry walls.
3.4 A drainage system
shall collect surface water run-off from the completed surface to prevent
erosion of the surface and silting of the adjacent water bodies and discharge
it at the point authorised by the Environment Agency via settling and
interceptor tanks.
3.5 A 1.5m high
post and rail fence (or similar) shall be erected along the top of the
completed slope.
3.6 The level of the
top of the slope shall be as shown on Drawing WM02457/104.
3.7 The Contractor shall be responsible for determining the
following:
·
The suitability (both
geotechnical and geochemical) of the materials within the overburden mound for
use within the reinforced earth slope;
·
The quantity of rock
required to be trimmed from the base and sides of the void to allow
construction of the slope;
·
The precise location
of the slope to provide the required developable area (or more) whilst
maintaining a safe stand off from the edge of the bench to the main void to
allow construction of the wall and ensure its long term stability;
·
The requirement for
any drainage layers within the slope;
·
The topography of the
slope to allow the exposure of a section of the unconformity cited in the RIGS
designation.
4
Engineering Infill
4.1 The
Contractor shall design and construct the engineered infill at the location
indicated on Drawing WM02457/104.
4.2 The specification shall be the ‘Specification for Highway Works’ 1998 (incorporating revisions dated June 1998 and May 2001) published by the HMSO as Volume 1 of the Manual of Contract Documents for Highway Works (referred to hereafter as the General Specification) subject to the amendments in Section F. For the purposes of this contract, references in the Specification for Highway Works to numbered Appendices shall refer to the Particular Specification.
4.3 The works shall be undertaken with the appropriate plant and labour necessary to comply with the requirements of the Specification.
4.4 Suitable reference points for the control of levels shall be erected by the Contractor prior to the commencement and maintained until the completion of the Works. Finished fill levels will be confirmed by Century Park Ltd.
4.5 Adequate precautions shall be taken against damage to the storm sewer which flows through the southern section of the site. Additionally both Bar Pool and Holly Stitches Brooks are to be protected.
4.6 The Works shall include
the excavation and stockpiling when required of all excavated fill materials.
4.7 It is estimated that the total amount of compacted fill required for the re-engineering of all phases of the works is in the order of 330,000m3. Double handling of materials into stockpiles is likely to be required.
4.8 During the placement and compaction of fill materials at the commencement of the site works, field tests shall be carried out to assess the standard of compaction that can be achieved with the various site won and imported fill materials. The standard of compaction achievable on site shall be assessed by field observations on field trial pads.
4.9 All materials encountered during the excavation works shall, where acceptable, be used for fill and, where unacceptable, be stockpiled separately. Any topsoil encountered during the excavation works shall be stockpiled separately for re-use across the site under a separate contract. Unacceptable materials, such as oversize blocks and organics (wood etc) are defined in the Specification.
4.10 All areas of prepared base of excavation shall be inspected, photographed and approved prior to the commencement of filling operations.
4.11 After completion of the reduced level dig and prior to the placement of any fill the base of the excavation shall be compacted by the number of passes of the compaction plant as appropriate to the class of material being compacted. The prepared formation shall be inspected and any soft spots removed as deemed necessary.
4.12 All materials placed will be compacted to an end product specification to achieve 95% of the maximum dry density. Material for compaction shall be spread in uniform layers and the thickness of the compacted layer and the number of passes of the compacting equipment shall be determined from the category of the fill material and the type and weight of the compacting plant as defined in the Specification. They will be determined prior to commencing operations and may be varied as the work proceeds. During placement construction traffic shall be directed uniformly over the whole of the compacted area. Any damage to compacted layers shall be made good prior to placement of any further layers.
4.13 If any material deposited as fill subsequently reaches a condition such that it cannot be compacted in accordance with the requirements of the Contract it shall either:
i) be removed from the works either to the unsuitable area or elsewhere until it is in a suitable physical condition for re-use and replaced with acceptable material, or
ii) be made good by mechanical or chemical means to improve stability, or
iii) works shall be terminated on the material until its physical condition is again such that it can be compacted as described in the Specification.
4.14 All fill shall be placed in near horizontal layers and made up evenly with an adequate fall maintained on the compacted surface at all times so that surface water may be shed rapidly. The fall should be directed away from the operational fill area. Surface water may need to be controlled to prevent flooding of adjacent land.
4.15 When fill levels have risen sufficiently for natural drainage of the area, the surface shall be regulated to avoid ponding and secure rapid run off. Particular attention shall be paid to ensuring the site is free draining at the end of each working day. No nuisance shall be caused to owners and occupiers of adjacent land or the Local Authority in respect of its road and sewers by surface water and any sand, silt or clay carried in suspension draining from the site. All necessary steps shall be taken to ensure that all such run off is contained on the site and dispersed via silt traps in a planned manner. Any proposals to dispose of excess water to a public sewer shall be subject to the prior agreement and requirements of the responsible Authority.
4.16 In the event of the work being suspended by prolonged wet weather or frost, filling operations shall not be resumed until the formation level or compacted surface has drained or thawed and inspections have shown it still to be in a sufficient state of compaction. If considered necessary, further compaction shall take place to restore the surface to its previous condition before any new fill is deposited.
4.17 Special care shall be taken around the margins of the fill to ensure that these areas are properly compacted. If necessary, in small fill areas, special compaction machinery shall be used and layer thickness reduced but in no case shall a lower standard of compaction be accepted.
4.18 Where excavation material includes any blocks of natural or man-made origin which exceed 2/3rds the compacted layer thickness or are greater than approximately 0.015m³ in volume, the materials shall be deemed to be unacceptable for immediate re-use as fill without processing.
4.19 Any organic materials (such as wood branches etc) encountered either at the site of excavation or within the fill area shall be removed.
4.20 When materials of widely divergent characteristics are used in fill areas, they shall be spread and compacted in separate clearly defined areas in such a manner as to comply with the requirements for each material type as defined in the Specification. If more than one class of material is used such that it is impracticable to define the areas in which each class occurs separately, compaction plant shall be operated as if only the material which requires the greatest compactive effort is being compacted.
4.21 All reasonable steps shall be taken to prevent nuisance from dust blowing from the surface of the site and, in particular, special attention shall be given to haul roads by regular watering or other treatment.
4.22
The engineered infill
shall be designed to allow for raft type foundations with a minimum bearing
capacity of 80 kN/m2.
4.23
The Contractor shall
be responsible for determining the requirement for any drainage layers within
the engineered infill. Additionally the requirement for drainage measures to
intercept any seepages from the quarry walls will need to be considered.
4.23 The Contractor
shall include within his design and works settlement monitoring apparatus and a
long term monitoring/reporting regime (minimum 2 years).
4.24
4.25 The Contractor
shall allow for the establishment of a daily monitoring regime to record the
amount of precipitation at the site, the water level in the main void and the
rate and duration of any pumping from/into the main void.
4.26 The Contractor
shall be responsible for determining the suitability of the materials placed
and compacted within the shallow void during 2002 for incorporation into this
Contract. If deemed suitable for incorporation without any further works the
Contractor shall include within his design appropriate geotechnical
justification to the satisfaction of the Employers Representative. The
Contractor shall also accept liability for the previous works and include it
within his warranties for the whole of the works.
5
Excavation, Classification and Utilisation of Excavated
Materials
5.1 The majority of
the materials to be excavated will comprise topsoil, subsoil, clay, silt, sand
and gravel.
5.2 The Contractor
may use any of the excavated materials within the Works (subject to compliance
with the specification) and any surplus material shall be deposited in adjacent
areas at locations to be agreed.
6
Access Roads and Haul Roads
6.1 Access to the
site shall be via the existing gates onto Tuttle Hill. The Contractor shall take all necessary
measures to prohibit the deposition of mud etc onto Tuttle Hill. The Contractor
shall obtain written approval from the Highways Authority in relation to the
use of the access and any necessary modifications and signage.
6.2 The
Contractor shall construct and maintain temporary haul roads to a standard
which the Contractor considers will be suitable for the trafficking of his
plant etc and shall remove and reinstate all temporary haul roads on completion
of the works.
7
Working Constraints
7.1 The Contractor shall make allowance within his design and construction works for the limitations of working within a quarry site with unprotected highwall/slopes and deep water
7.2 Due to the depth of the quarry void and the limitation of the working area in the base of the void the Contractor shall be aware of the need for careful planning and programming of the works.
8
Control of Surface
Water and Groundwater
8.1 The Contractor shall take all measures to collect and control groundwater and surface water during the works and shall ensure that all discharges satisfy the Environment Agency.
9
Possession of Site
9.1 Prior to commencement of the Works, the boundary to the Site shall be agreed between the Employer and the Contractor. Access to all areas of the Site will be available from the Date of Commencement of Works. The Contractor shall note that the entrance onto Tuttle Hill shall also provide access to the quarry for the Employer. It is essential that access to the site for the Employers vehicles is maintained at all times unless agreed otherwise by Employer.
10
Programme
&nbbsp;
10.1 The Contractor shall
submit a programme for the Works to the Employer’s Representative.
11
Contractor's Site
Offices, Services and Facilities for Employees, Stores, Workshops etc
11.1 All the Contractor's administration offices, site offices, cabins, stores and facilities must be located within an area to be agreed with the Employer’s Representative. The Contractor shall supply office space (minimum 2 desks), office supplies, suitable protective clothing, welfare facilities and consumables for use by the Employer and Employers Representative. The Contractor shall supply all toilets, washing and other facilities to be used by his staff, the Employer and the Employers Representative.
12
Additional
information made available by Employer at time of Tender
12.1 Additional information made available by the Employer at time of Tender is attached as Appendices 1-8.
13
Health and Safety
13.1 The Contractor shall, in addition to all of his statutory obligations with respect to Health and Safety, comply with the requirements of the Employer in respect of his operations on Site. The Contractor shall note that the works will be subject to the requirements of the Construction (Design and Management) Regulations 1994.
14
Meetings
14.1 The Contractor shall attend fortnightly progress meetings during the course of the Contract to be held with (as a minimum) the Employers Representative.
Specification
PREAMBLE TO THE SPECIFICATION
1 The Specification referred to in the
Tender shall be the `Specification for Highway Works' 1998
(incorporating revisions dated June 1998 and May 2001) published by HMSO as Volume 1 of the Manual of Contract Documents for
Highway Works, as modified and extended by the following:
(i) Appendix
0/1: Contract Specific Additional, Substitute and Cancelled Clauses and Tables.
(ii) The
numbered Appendices listed in Appendix 0/3.
Attached Appendix 0/4 contains a list of the Drawings.
3 An Additional Clause as indicated by a
suffix`AR' in Appendix 0/1 is a Contract-specific alteration.
4 A Substitute Clause as indicated by a
suffix`SR' in Appendix 0/1 is a Contract-specific alteration.
5 A Cancelled Clause indicated by a`CR'
in Appendix 0/1 is a Contract-specific alteration.
6 Insofar as any of the Numbered Appendices
may conflict or be inconsistent with any provision of the Specification for
Highway Works the Numbered Appendices shall always prevail.
7 Any reference in the Contract to a
Clause number or Appendix shall be deemed to refer to the corresponding Substitute
Clause number or Appendix listed in Appendix 0/1.
8 Where a Clause is altered any original
Table referred to in the Clause shall apply unless the Table is also
altered. Where a Table is altered any
reference in a Clause to the original Table shall apply to the altered Table.
9 Where a Clause in the Specification
relates to Work goods or materials which are not required for the Works it
shall be deemed not to apply.
10 Any Appendix referred to in the
Specification which is not used shall be deemed not to apply.
11 Any material Class not amended in Tables
6/1(i)-(ii)SR shall conform to the requirements of the original Table 6/1.
APPENDIX 0/1
CONTRACT
SPECIFIC ADDITIONAL, SUBSTITUTE AND CANCELLED CLAUSES AND TABLES INCLUDED IN
THE CONTRACT
INDEX
|
Clause No (etc) |
Title |
|
SERIES
100 170AR 171AR 172AR 173AR 174AR 175AR 176AR 177AR 178AR |
PRELIMINARIES General Protection Of Roads And Accesses Preservation Of Existing Features Storage Of Hazardous Materials Hours Of Working Nuisance Drainage Publicity Materials Arising From The Site To Be Stored On
Or Off Site |
|
SERIES
200 270AR |
SITE
CLEARANCE Burning Of Surplus Material |
SERIES 100 – PRELIMINARIES
General
The Contractor shall be responsible for the
provision of any services for his own use, full details of which shall be
agreed with the Employer. The
Contractor shall also be responsible for any diversions or alterations to
existing services which he requires, full details of which shall be agreed with
the Employer.
Clause 171AR
Protection Of Roads And Accessees
The Contractor shall ensure that the wheels or
tracks of any vehicles or other plant leaving the Site are thoroughly cleaned
so that no dirt is deposited on the highway.
Tracked vehicles will not be allowed to traffic directly on public
highways.
Clause 172AR
Preservation Of Existing Featurres
The Contractor shall take all reasonable and
necessary precautions to safeguard existing features which the Employer
requires to be retained in or about the Works and shall make good to the
approval of the Employer any damage done to existing structures, paths, fences,
trees and other natural features. No
trees, hedges or bushes are to be removed without the prior consent of the
Employer, whether specified in the Contract to be removed or not.
Clause 173AR
Storage Of Hazardous Materials<
In compliance with COSHH legislation, the
Contractor shall make arrangement for the safe storage of Hazardous Materials
that he may require to use in connection with the Works and for their
distribution about the Site. If any
area of the Site becomes contaminated with hazardous materials imported or used
by the Contractor, the contamination shall be treated by the Contractor. Fuels and lubricants shall be drawn from a
central supply point approved by the Employer and appropriate bunding shall be
provided by the Contractor for fuel tanks etc.
The capacity of all bunding arrangements shall be 1.1 times the relevant
tank size.
Clause 174AR
Hours Of Working
The hours of working on the Site shall be from 0700
to 1900 from Monday to Friday and 0700 to 1300 on Saturday. Under no circumstances shall work on the
Site be carried out outside the specified hours or at any time on Sunday or
Public Holidays without the permission of the Employer.
Clause 175AR
Nuisance
The Contractor shall carry out the Works so as to
cause the minimum of nuisance and inconvenience to the general public and to
the owners and occupiers of properties adjacent to the Site.
Clause 176AR
Drainage
Notwithstanding the Special Reqquirements of the Environment Agency the
Contractor shall comply with the following:
(i)
Water shall not be
discharged from the Works into existing water courses or elsewhere without the
prior approval of the Employer.
(ii)
No discharge
whatsoever shall be made to existing sewers, drains and manholes unless
otherwise agreed with the Employer.
Clause
177AR
Publicity
1.
The Contractor shall
not give any information concerning the Works for publication in the press or
on radio, television or screen or elsewhere without the written approval of the
Employer.
2.
The Employer shall
first approve all advertisements and Contractors or Sub-Contractors nameboards
to be erected within the Site by the Contractor or by any Sub-Contractor.
3.
All approved
advertisements and Contractors or Sub-Contractors nameboards within the Site
shall be removed within seven days of the date of the Certificate of Completion
of the Works.
Clause 178AR
Materials Arising From The Sitee To Be Stored On Or Off Site
1.
Where materials
arising from the Works are to be transported to or from Stockpiles, the
Contractor shall carefully remove them, haul and fill as described in the
Contract.
SERIES 200 – SITE CLEARANCE
Clause 270 AR
Burning Of Surplus Material
The
onsite burning of materials shall not be permitted.
 p;
APPENDIX 0/3
LIST OF NUMBERED APPENDICES
REFERRED TO IN THE SPECIFICATION AND INCLUDED
IN THE CONTRACT
&nbssp;
|
Series |
Appendix
No |
Contents |
|
100 |
1/1 1/2 1/3 1/4 1/5 1/6 1/7 1/8 1/9 1/10 1/11 1/12 1/13 1/14 1/15 1/16 1/17 1/18 1/19 1/20 1/21 1/22 1/23 1/24 1/25 |
PRELIMINARIES Not Used Not Used Not Used Not Used Testing To Be Carried Out By The Contractor Not Used Site Extent and Limitation on Use Not Used Not Used Structures to be designed by the Contractor Not Used Setting Out And Existing Ground Levels Programme Of Works Monthly Statements Not Used Privately and Publically Owned Services and
Supplies Traffic Safety and Management Not Used Routing of Vehicles Not Used Not Used Not Used Not Used Not Used Not Used |
|
200 |
2/1 2/2 2/3 2/4 2/5 |
SITE
CLEARANCE Not Used Not Used Retention of Material Arising from Site
Clearance Not Used Not Used |
|
300 |
3/1 3/2 |
FENCING
AND ENVIRONMENTAL BARRIERS Not Used Not Used |
|
400 |
4/1 4/2 |
SAFETY
FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS Not Used Not Used |
|
500 |
5/1 5/2 5/3 5/4 5/5 |
DRAINAGE
AND SERVICE DUCTS Drainage Requirements Service Duct Requirements Not Used Not Used Not Used |
|
600 |
6/1 6/2 6/3 6/4 6/5 6/6 6/7 6/8 6/9 6/10 6/11 6/12 6/13 |
EARTHWORKS Requirements For Acceptability And Testing Etc.
Of Earthworks Materials Not Used Requirements For Excavation, Deposition,
Compaction (Other Than Dynamic Compaction) Not Used Geotextiles Used To Separate Earthworks Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used |
|
700 |
7/1 7/2 7/3 7/4 7/5 7/6 |
ROAD
PAVEMENTS - GENERAL Not Used Not Used Not Used Not Used Not Used Not Used |
|
1100 |
11/1 |
KERBS,
FOOTWAYS AND PAVED AREAS Not Used |
|
1200 |
12/1 12/2 12/3 12/4 12/5 12/6 |
TRAFFIC
SIGNS Not Used Not Used Not Used Not Used Not Used Not Used |
|
1300 |
13/1 13/2 13/3 |
ROAD
LIGHTING COLUMNS AND BRACKETS Not Used Not Used Not Used |
|
1400 |
14/1 14/2 14/3 14/4 14/5 |
ELECTRICAL
WORK FOR ROAD LIGHTING AND TRAFFIC SIGNS Not Used Not Used Not Used Not Used Not Used |
|
1500 |
15/1 |
MOTORWAY
COMMUNICATIONS Not Used |
|
1600 |
16/1 |
PILING
AND DIAPHRAGM WALLING Not Used |
|
1700 |
17/1-17/4 (inclusive) |
STRUCTURAL
CONCRETE Not Used |
|
1800 |
18/1 |
STRUCTURAL
STEELWORK Not Used |
|
1900 |
19/1 19/2 19/3 19/3 19/4 19/5 19/6 19/7 19/8 19/9 |
PROTECTION
OF STEELWORK AGAINST CORROSION Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used |
|
2000 |
20/1 20/2 |
WATERPROOFING
FOR STRUCTURES Not Used Not Used |
|
2100 |
21/1 |
BRIDGE
BEARINGS Not Used |
|
2200 |
22/1 |
PARAPETS Not Used |
|
2300 |
23/1 23/2 |
BRIDGE
EXPANSION JOINTS AND SEALING OF GAPS Not Used Not Used |
|
2400 |
24/1 |
BRICKWORK,
BLOCKWORK AND STONEWORK Not Used |
|
2500 |
25/1 25/2 25/3 |
SPECIAL
STRUCTURES Not Used Not Used Not Used |
|
2600 |
26/1 26/2 |
MISCELLANEOUS Not Used Not Used |
APPENDIX 0/4
Drawing
Number Title Scale
WM02457/101 Midland
Quarry Site Location 1:10,000
WM02457/102 Original
Site Levels 1:1000
WM02457/103 Post
2002 Site Levels 1:1000
WM02457/104 Proposed
Infilling Works 1:1000
APPENDIX 1/5
1.
The Contractor shall
demonstrate by appropriate testing that the Works have been constructed in
accordance with the contractor’s design and the Contractor’s specifications.
2.
The scope of testing
shall comply in all respects with the relevant tests covered in Table NG1/1 of
the Notes for Guidance on the Specification.
3.
The Contractor shall
identify in his design submission the schedule of tests he considers
appropriate to confirm compliance with the requirements of the specification
and design and shall list any further testing he considers necessary which is
not covered in Table NG1/1.
4.
The following Table
1/5 is to be completed by the Contractor
|
Clause |
Work |
Test |
Frequency |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
APPENDIX 1/7
(i)
The extent of the
Site is indicated on the Tender Drawings.
2.
Limitation of the
Use of the Site
(i)
The Contractor must
comply in all respects with the information detailed in the Specification and
Description of Works and on the Tender Drawings.
APPENDIX 1/10
STRUCTURES
TO BE DESIGNED BY THE CONTRACTOR
1 The
Contractor shall design all the Works described in the Employer’s Requirements
and Description of Works.
&nbssp;
&nbssp;
&nbssp;
&nbssp;
&nbssp;
APPENDIX
1/12
SETTING OUT AND EXISTING GROUND
LEVELS
&nbssp;
1
The location and
co-ordinates of survey control stations to be used for the setting out of the
Works will be supplied to the Contractor as will the level datum used to
determine existing ground levels shown on the drawings.
2
The Contractor
shall, as soon as he takes possession of the Site, check the inter-relationship
between the survey control stations for which information is provided and any
discrepancies found shall be reported and revised values agreed with the
Employer’s Representative before setting out the Works.
3
The Contractor
shall, as soon as he takes possession of the Site, check the levels and any
discrepancies between these and the levels indicated in any part of the
Contract shall be reported to the Employer’s Representative before commencement
of the Works.
4
The Contractor
shall as soon as practicable supply the Employer’s Representative with records,
relating to all survey ground markers and reference pegs as well as bench marks
and shall keep such records up to date by formal notice to the Employer’s
Representative.
APPENDIX
1/13
PROGRAMME OF WORKS
&nbssp;
1. The
Contractor shall provide the Programme of Works in a form of Bar
Charts/Space-Time Diagrams produced as a result of a Critical Path Analysis.
They shall show the level of detail appropriate to each stage of the Works and
all activities and restraints, each of which shall be given a short title. All events shall be numbered and annotated
with earliest and latest event dates. At
the time of the Programme the Contractor shall also provide the locations and
capacities of anticipated plant and other resources.
APPENDIX
1/14
&nbssp;
MONTHLY STATEMENTS
&nbssp;
1. The
Contractor shall submit a schedule of payments at time of tender for consideration
and approval by the Engineer.
APPENDIX 1/16
PRIVATELY
AND PUBLICY OWNED SERVICES AND SUPPLIES
1.
The Contractor
shall make arrangements with the Statutory Undertakers and Utility Companies
and others concerned, for the co-ordination of his work with all work which
needs to be done by them or their Contractors concurrently with the works.
2.
The Contractor
shall make arrangements with the Statutory Undertakers and others concerned for
the phasing of all necessary disconnections and diversions of private services
affected by the works.
3.
Disconnected
apparatus can be removed by the Contractor only with the prior approval of the
Authority/Company concerned.
APPENDIX
1/17
TRAFFIC
SAFETY AND MANAGEMENT
1.
Access Roads and Haul Roads
APPENDIX
2/3
RETENTION
OF MATERIAL ARISING FROM SITE CLEARANCE
1. Timber and
other vegetation arising from the works shall be shredded by the
Contractor and deposited in an area
identified by the Employer’s Representative.
APPENDIX
5/1
DRAINAGE
REQUIREMENTS
1.
The Contractor
shall submit with this design a completed Appendix 5/1: Drainage Requirements in accordance with the
Notes for Guidance on the Specification.
2. Drains
and associated structures shall be constructed by the Contractor as detailed in
the Specification and Description of Works.
3. The
Contractor shall carry out testing of all materials in accordance with the
details given in Appendix 1/5.
&nbssp;
APPENDIX
5/2
1.
The Contractor
shall submit with this design proposals a completed Appendix 5/2: Service Duct
Requirements in accordance with the requirements of the Notes for Guidance on
the Specification.
APPENDIX
6/1
REQUIREMENTS
FOR ACCEPTABILITY AND TESTING ETC OF EARTHWORKS MATERIALS
1.
The Contractor
shall be required to classify the available materials in accordance with Series
600 of the Specification and shall supply the Employer’s Representative with
copies of information and laboratory test data.
2.
The Contractor
shall submit with his design proposals a completed Specification Table 6/1:
Acceptable Earthworks Materials: Classification and Compaction
Requirements. The Contractor’s
attention is drawn to the need to prepare and submit a completed Appendix 1/5
detailing his proposals for testing for the classification and acceptability of
materials.
3.
The Contractor
shall be responsible for determining suitably of materials at point of
excavation and point of deposition and the suitability of all imported
materials in accordance with requirements of Appendix 1/5. Materials for use as general fill shall have
a moisture content between the range determined from the 2.5kg rammer
compaction test (Appendix 1/5) as necessary to achieve 95% of maximum dry
density.
APPENDIX
6/3
REQUIREMENTS
FOR EXCAVATION, DEPOSITION, COMPACTION (OTHER THAN DYNAMIC COMPACTION)
1.
The contractor
shall ensure that the angle of all permanent excavated slopes shall be no
greater than 1 in 3 to the horizontal. Temporary slopes shall be no greater
than 1 in 1 to the horizontal. Shallow
bunds and stockpiles shall be formed at angles no steeper than 1 in 2 to the
horizontal.
2.
Details of
compaction requirements for materials acceptable for use as general fill are
given in Specification Table 6/1 (to be completed by the Contractor).
3.
The Employer’s
Representative may use a nuclear surface density gauge to measure field
densities and moisture contents of compacted fill.
4.
The Contractor
shall satisfy himself as to the quality of all formations prior to constructing
the Works. The Contractor shall allow
for undertaking further investigation of the formation, if necessary, in order
to satisfy himself that the performance of the formation will be adequate.
5.
Copies of existing
Site Investigation information are attached as Appendix 1.
APPENDIX
6/5
GEOTEXTILES AND GEOMEMBRANES USED
TO SEPARATE EARTHWORKS MATERIALS
&nbssp;
1. The Contractor shall submit with his design proposals a completed Appendix 6/5: Geotextiles used to Separate Earthworks Materials in accordance with the requirements of the Notes for Guidance on the Specification.
Section G
Lump Sum Build Up/Schedule of Rates
To be completed by Tenderer.