IMPLEMENTATION SCHEDULE


Project is proposed to be implemented as under:-


� Commencement Completion
i) Acquisition of land Already Acquired
ii) Infrastructural Development Oct. 2001 Mar. 2002
iii) Civil work�
a. Factory building Nov. 2001 April 2002
b. Machinery foundation Dec. 2001 April 2002
c. Auxiliary building Apr. 2001 Aug. 2001
d. Administrative Building �
e. Misc. building �
iv) Indigenous Machinery�
a. Placement of orders Nov. 2001 Nov. 2001
b. Delivery on site Jan. 2002 Feb. 2002
v) Arrangement for power & Water Dec. 2001 Jan.2002
vi) Erection of Facilities Feb. 2002 Feb. 2002
viii) Commissioning May 2002 June 2002