|
Question #37 - Holes #13 and #14 are the only ones on the course to still have asphalt cart paths. The paths have deteriorated and are in need of replacement with concrete. The architect recommended that, when this is done, a section of the path on the left side of Hole #13 would be moved uphill. The fairway would also be moved left. See the master plan drawing for details. |
||
|
# |
Response Date |
Comment: |
|
1. |
4/3/2008 3:38:00 PM |
Why has this not been done already. It has been due for 15 years and is a Replacement Reserve item. Moving the path out of play is a no brainer. |
|
2. |
4/3/2008 5:16:00 PM |
Could we replace the cart paths with new asphalt? It seems that getting a pridge built that would support a concrete truck is very expensive. |
|
3. |
4/3/2008 7:06:00 PM |
Should be a top priority. |
|
4. |
4/3/2008 8:31:00 PM |
Should be # 1 priority |
|
5. |
4/3/2008 9:38:00 PM |
Let's do it - we've been talking about replacing those paths with concrete for eons! |
|
6. |
4/4/2008 2:32:00 AM |
We paid for this to be done once. Will we have to do it again? |
|
7. |
4/6/2008 3:10:00 AM |
The paths were to be completed back in 1996. |
|
8. |
4/6/2008 6:50:00 AM |
The cost of this change is not justified since no real playable fairway would be gained. The slope of the land left of the current path is too steep. The work to move the cart path up the hill would be way to expensive. Just replace the current asphalt with new cement cart paths. |
|
9. |
4/8/2008 6:31:00 PM |
This needs to be done right away, safety and liability problem |
|
10. |
4/10/2008 8:53:00 PM |
Why? |
|
11. |
4/11/2008 11:03:00 PM |
Will make hole more playable |
|
12. |
4/13/2008 6:24:00 PM |
Cost |
|
13. |
4/16/2008 12:06:00 AM |
hits on the present cart path are common |
|
14. |
4/16/2008 4:31:00 PM |
Replace paths |
|
15. |
4/16/2008 5:19:00 PM |
#14 the lower section of cartpath moved to the left with a new bridge. Remove present cartpath between green and fairway. |
|
16. |
4/16/2008 8:36:00 PM |
fix current paths |
|
17. |
4/16/2008 9:20:00 PM |
PAD and plan available fall of '08 |
|
18. |
4/19/2008 10:39:00 PM |
8 foot wide paths |
|
19. |
4/19/2008 10:50:00 PM |
Leave paths (new concrete) where they are. |
|
20. |
4/20/2008 1:14:00 AM |
This hole punishes good shots now, and these changes would help. |
|
21. |
4/21/2008 4:41:00 PM |
makes sense |
|
22. |
4/21/2008 5:08:00 PM |
this should have been done long ago where is our trail fee money going? |
|
23. |
4/21/2008 10:02:00 PM |
Why only concrete. Are their alternatives |
|
24. |
4/21/2008 11:20:00 PM |
You may want to survey the people who live on these holes |
|
25. |
4/21/2008 11:22:00 PM |
prefer down the middle,speed play,free replay if hit |
|
26. |
4/22/2008 9:57:00 PM |
Need more info on costs involved in relocating cart path and associated costs. |
|
27. |
4/22/2008 11:00:00 PM |
this hole needs work |
|
28. |
4/23/2008 3:19:00 AM |
Their current condition creates a health " safety issue |
|
29. |
4/23/2008 4:47:00 AM |
This is a MUST !!! |
|
30. |
4/23/2008 9:19:00 PM |
Number one priority |
|
31. |
4/23/2008 10:14:00 PM |
Would need to know cost delta of just replacing asphalt versus relocating cart path |
|
32. |
4/23/2008 11:10:00 PM |
The asphalt cart paths are dangerous in spots in their current condition. They should be replaced as soon as possible. Moving the #13 path would also improve the playability as well as the visual picture. |
|
33. |
4/25/2008 2:37:00 PM |
cost? piecemeal? |
|
34. |
4/25/2008 10:04:00 PM |
Unnecessaary cart path relocation. |
|
35. |
4/25/2008 10:30:00 PM |
could create a hazard - would slow play |
|
36. |
4/27/2008 3:49:00 AM |
If the cart paths are to be replaced, then this would be the right time to relocate the #13 path. |