Sydney
MAJOR
ROADS AND CURRENT PROJECTS
Alfords Point Bridge (Metroad 6)
Duplication $12M (2007)
Bangor Bypass
Stage 1: Akuna Ave to Alfords Point Rd $95M (2004)
Stage 2: Alfords Point Rd
to New Illawarra
Rd, $40M (planning)
Cahill Expressway
Pedestrian Walkway $10M (2002)
Camden Valley Way
Bernera Rd and Croatia
Ave Intersection, $12M (2005)
Bernera Rd to M5 Motorway: widen to 4 lanes, $21.5M (2006)
Cowpasture Rd to Bernera Rd: widen to 4 lanes (planning)
Castlereagh
Rd (Metroad 9)
Jane
St to Penrith
Lakes Widening, $22.7M
(Aug 2000)
City West Link Rd
(Metroad 4)
Balmain Rd to Boomerang St $50M (2000)
Cowpasture
Rd (Liverpool-Smithfield Route)
Camden
Valley Way and Bringelly Rd intersection
$7.7M (2000)
Main
St to Hoxton Park Rd:
widen to 4 lanes, $39M (2006)
Latrobe
Rd-Hoxton Park Rd: Widen to 4 lanes $16M (2005)
Greenway Dr to M7: widen to 4 lanes (planning)
North
Liverpool Rd to Mount St,
4 lanes, $17M (2004)
Mount St to Elizabeth Dr, 4 lanes, $13M (2003)
Edensor
Rd-Prairie Vale Rd $25M (2000)
Prairie Vale Rd-Restwell Rd
widening $8M (2000)
Restwell
Rd-Horsley Dr widening $8.8M (2000)
Cross City Tunnel
The Cross City Tunnel between Darling Harbour
and Kings Cross links the Western and Eastern Distributors providing a bypass
of the Sydney CBD for east-west through traffic. The project was approved in
October 2001. A consortium, Cross City Motorway, was selected to finance,
construct and operate the tunnel. Total
State expenditure $680M,
opened to traffic in August 2005.
Cumberland Highway
(Metroad 7)
Widening to six lanes (The Horsley Dr to Merrylands Rd),
$30M (2002)
Eastern Distributor (Metroad 1)
Eastern Distributor (1999)
Elizabeth Drive
Cabramatta Rd - Cowpasture Rd: widening $25.8M
(2000)
F3 Sydney Newcastle Freeway
Mt Colah Cowan:
widen to 6 lanes (part Federal funding), $132M (2008)
Hawkesbury River Calga: widen to 6
lanes, $81.7M (2004)
F3 to M2 Motorway Link (Wahroonga to Carlingford)
Project is in planning stages and will be Federally funded.
Preliminary planning provides for a route largely in tunnels below Pennant Hills Rd.
Great Western
Highway (Blue Mountains)
Blaxland to Valley Heights (The Boulevarde
to Wyoming St),
$37M (1999)
Faulconbridge: Grose Rd to Parkes Cr, $25M (2001)
Linden Bends 4: Tollgate Dr East to Hepburn Rd 4 Lanes, $14M, (2003)
Linden Bends 5: Water Reservoir to Tollgate Dr E $5.7M (2001)
Woodford to Hazelbrook Stage 1 (Winbourne Rd to
Ferguson Ave):
widen to 4 lanes $45M (2008)
Lawson 1: Ferguson Ave to Honour Ave:
Widen to 4 Lanes, planning
Lawson 2: Honour Ave to Ridge St: widen to
4 Lanes, $54.4M (planning)
Wentworth Falls East: Tableland Rd to Station St: Widen to 4 lanes (planning)
Wentworth Falls West: Falls Rd to West St: Widen to 4
lanes $15M (2004)
Leura: Mt
Hay Rd to Bowling Green Ave: Widen to 4 Lanes, $82M
(2006)
Leura Katoomba Stage 2: East View Ave Bowling Green Ave
(widen to 4 lanes), $25M (2008)
Shell Corner (Katoomba):
Mort St
to Nellies
Glen Rd 4 Lanes, $36M, (2003)
Medlow Bath: Bellevue
Cr to Cox Ave
4 Lanes & Rail Overpass, $17M (2003)
Soldiers Pinch Realignment, Blackheath,
$18M (2003)
Heathcote
Rd
Macarthur
Dr - M5 Motorway: widening, $11.2M (2000)
The Horsley Dr
Railway Overpass: Denison St-Mitchell St $19.5M (2000)
Elizabeth
St to Mimosa Rd Widening
$7M (2003)
Mimosa Rd to Lily St Widening, $17M (2004)
Landon
St to
Fairfield St Widening, $8M (2004)
Cowpasture Rd Intersection, $5M (2005)
Ferrers Rd to M7 (planning)
Hoxton
Park Rd
Banks
Rd - Hill Rd widening
and transitway $6M (2003)
Hill
Rd - Brickmakers Creek Rd:
Widen to 6 lanes and transitway $25M (2005)
Banks
Rd Cowpasture Rd:
widen to 4 lanes (planning)
Hume Highway
(F5 South Western Fwy)
Ingleburn Rd: South
facing ramps $13.7M
(part Federal and local government funding) (2006)
Camden
Valley Way to Brooks Rd:
widen southbound carriageway to 4 lanes, $23M (Federal Funding) (2006)
Brooks
Rd Camden Valley Way:
widen northbound carriageway to 4 lanes, $41M (Federal Funding) (2007)
Lane Cove Tunnel (Metroad 2)
The Lane Cove Tunnel links the Gore Hill Freeway
to the M2 Motorway. The $1.1B project is nearing completion with financing
provided through private sector funding and toll collection on the completed
project (as with the Eastern Distributor and Western Sydney Orbital). It is
scheduled to be open to traffic by 2007.
Mona Vale Rd
(Metroad 3)
Bahai Temple to Ingleside
Rd Widening $18M (2003)
M4 East (Haberfield to Concord)
Feasibility Study commenced 2002 and concept
plans released in 2003. Following
widespread community condemnation of the proposed project and a change in plans
and strategy by the NSW government, the project has been subsequently placed on
hold and will be re-assessed. The
project is now officially resting in planning status.
M5 East (Mascot to Beverly Hills)
The $794M 10km eastern extension to the M5
opened on 10 December 2001 and includes Australia's longest road tunnel
(4km).
Narellan Road (Metroad 9)
Camden
Valley Way to Northern Rd Extension, $20M (2007)
Waterworth Dr and Mt Annan Dr
Signals, $14M (2006)
North West
Transitway
Parramatta to Rouse Hill and Blacktown to Parklea
$524M (2007)
Old Windsor
Rd (Metroad 2)
Seven
Hills Rd
Intersection $11M (2002)
Abbott
Rd to Sunnyholt Rd
(2002)
Norbrik to Celebration Dr $11M (2002)
Sunnyholt Rd to Merriville Rd $27M (2002)
Norwest
Blvd: grade
separated intersection $40M (2006)
Parramatta
Rd (Metroad 4)
Broadway to Woodville Rd Upgrade, $50M, planning
Southern Arterial
This road has been in planning at various stages
but has no definite construction timeframe at this stage.
Southern Cross Dr
South facing ramps are planned for Gardeners Rd. No construction timeframe yet allocated.
Southern Freeway F6
Spit Bridge (Metroad
10)
Spit Bridge and Approaches: widen to 6 lanes $50M (2009)
Stacey St
(Metroad 6)
Stacey St Extension, Bankstown $15.4M
(1999)
Sunnyholt
Rd
James
Cook Dr
to Quakers Hill Pkwy:
widening to 6 lanes $30M (2006)
Sydney Harbour Bridge
Sydney Harbour
Tunnel
Western Distributor
Kent
St to
King St Widening $18M (2003)
Westlink M7 (Western Sydney Orbital)
Construction is underway on the $1.5 billion Westlink M7, formerly known as the long planned Western
Sydney Orbital. The Westlink M7 will be a tolled
motorway linking the M5 at Prestons and the M2 at Baulkham Hills with a full interchange at its junction with
the M4 near Rooty Hill. Construction is being
undertaken by WestLink Motorway Ltd, which is a
consortium that includes major infrastructure construction companies Abigroup and Leighton. The Westlink
M7 is scheduled to be open to traffic by the end of 2006.
Windsor
Rd
(Metroad 2)
Roxborough
Park Rd
to Norwest Blvd:
Widen to 4 lanes $75M (2006) (not part of Metroad 2)
Acres Rd to Old Windsor Rd: Widen to 4 lanes $40M
(2006) (not part of Metroad 2)
Merriville Rd to Schofields Rd: Widening to 4
lanes $10M (2003)
Schofields Rd to Mile
End Rd: Widen to 4 lanes $16M (2003)
Mile End
Rd to Boundary
Rd: Widen to 4 lanes $120M (2006)
Boundary Rd to Henry Rd: Widen to 4 lanes $40M (2006)
Henry
Rd to Curtis Rd Widening
$6.5M (2003)
Pitt
Town Rd
Intersection Upgrade $3M (2002)
South Creek Crossing (Windsor Flood Evacuation Route) $68M
(2006)
Woronora
Bridge
The $47M bridge was open to traffic in February
2001. In conjunction with the bridge project was the widening of Linden St between
The Grand Pde and River Rd ($8.8M)
Last
Revised 21 Sep 2006. Information
sources: Roads and Traffic Authority (NSW) annual financial year estimated expenditure