Eastern Distributor
Sydney’s Eastern Distributor is a 4km high-standard motorway between the Cahill Expressway at Woolloomooloo and Southern Cross Drive at Zetland. The entire project was worth $700 million with large sections of the project tunneled underground. The underground section (between Cathedral St and Anzac Pde) was built largely using the cut-and-cover method under existing rights-of-way. The motorway was funded and built by a private sector consortium, and will be operated, maintained and repaired by the consortium until 2048, when it will revert to the public sector. The motorway is tolled at two locations for northbound traffic. The main toll plaza is just south of the Art Gallery land bridge, and an additional toll plaza is located on the northbound off ramp to William St.
The three-year Eastern Distributor
construction project came to a successful conclusion eight months ahead of
schedule, opening to traffic on 9 December 1999. Journey times along the route
have been cut by up to 20 minutes, and congestion in the inner-eastern Sydney
area has been greatly reduced.
History
An expressway along the route of today's Eastern Distributor was first proposed
in the 1951 County of Cumberland Scheme. It was to form part of a ring road
system around the Sydney CBD collecting through traffic from radiating
freeways/expressways and "distributing" it to various directions
bypassing city streets, hence the name "Eastern Distributor". The
"Western Distributor" south of the Harbour Bridge and over Darling
Harbour was also part of the same ring road plan.
The Sydney Area Transportation Study
conducted in 1970 saw a major review of Sydney's transportation plans and
reassessed the city's changing needs. At this time the Eastern Distributor was
envisaged to be a surface freeway.
Later, the majority of the inner-urban
freeway and ring road corridors in both the County of Cumberland Scheme and the
Sydney Area Transportation Study were abandoned. The Eastern Distributor,
however, was retained as an important bypass.
The Strategic Plan of 1980 revived plans
for the Eastern Distributor and pushed for its early construction to restrict
and relieve the ever-worsening congestion in the residential areas of East
Sydney and Surry Hills.
In 1984 the Department of Main Roads
(DMR), which later became part of the Roads and Traffic Authority proposed the
construction of the Eastern Distributor as originally suggested by the Sydney
Area Transportation Study. In 1985 the DMR exhibited an Environmental Impact
Statement for an amended plan, placing the Eastern Distributor in tunnels from
north of William St to just south of Drivers Triangle on Anzac Parade.
In December 1987 Stage 1 of the new plan
tunnel under William St creating a much-needed bypass for through north-south
traffic crossing east-west William St. The Second and Third Stages: full length
tunnels in each direction, were never constructed.
Since 1985 various environmental factors
further worsened the traffic situation in inner-eastern Sydney. The Sydney
Harbour Tunnel Sydney Harbour Tunnel opened in 1992 increasing through traffic
considerably. The completion of the 3rd runway at the airport saw increasing
domestic and international air traffic, with this route being a major access
for northern and eastern Sydney to the airport. Continuing growth and expansion
of the port facilities at Botany Bay, and the increasing return of population
to the inner suburbs all led to an even greater strain on the traffic handling
capabilities of the area.
A study in 1994 showed that wide support
for a freeway and willingness by motorists to pay a toll, and in May the
private sector was invited to submit proposals to construct, operate and
maintain the Eastern Distributor.
Certain political issues in relation to
taxes and capital borrowing for urban tollways were resolved in June 1996 and
the Roads and Traffic Authority (RTA) continued negotiations for the project
with the preferred proponent: Airport Motorway Ltd (AML). AML is a private
consortium consisting of Leighton Contractors (the builders) and Macquarie Bank
(the financiers).
In August 1996 AML was officially
endorsed by the NSW Parliament as the preferred proponent of the Eastern
Distributor project. The AML proposal was considered likely to generate
sufficient income to fund all the works from Cahill Expressway to Moore Park,
including upgrading of South Dowling St as well as extra RTA works that
included widening Southern Cross Dr from 4 to 6 lanes, and widening General
Holmes Dr from 6 to 8 lanes between Botany Rd and the eastern end of the M5
Eastern Extension.
The Environmental Impact Statement (EIS)
for the AML Eastern Distributor and associated RTA works was exhibited in
November-December 1996. The RTA had made a number of changes to original AML
proposal. Planning approval was granted by the Minister for Urban Affairs and
Planning, subject to 151 conditions, in June 1997. The main contracts became
fully effective and unconditionally binding when all conditions had been
satisfied in August 1997.
The project opened in December 1999, 8
months ahead of its three-year completion schedule.
Information Source: RTA 2001
Date of last revision: 9 Jun
2005