(Continued from page 15)
capital projects advance through a longer project development process,
and each phase can take several years to complete. In the first phases
of project development, projects are put into the "Development and
Evaluation" part of the CTP. Only when initial planning is complete and
funding is identified are projects moved to the "Construction" program.
During initial project planning the Department identifies alternatives,
generates travel demand forecasts, completes preliminary environmental
impact and cost studies and holds a public alternatives meeting.
For highway projects, local elected officials must concur before a
project can advance to final project planning. During this process, the
Department completes preliminary engineering and detailed environmental
analyses, prepares an environmental document, obtains preliminary permit
approvals, holds a public hearing and selects an alternative.
Once an alternative is selected, design engineering can begin. This
phase includes the development of construction plans, environmental
re-evaluation and permit applications. This phase also includes a formal
request for State funds and/or authorization of Federal funds.
The next phase involves the acquisition of right-of-way, including a
relocation assistance plan for people who could be affected by the
project. This phase is typically conducted concurrently with the design
engineering phase.
Finally, the Department awards the project contract and proceeds to
construction.
"Maryland's transportation system must do more than connect people to
places. It must connect people to opportunities."
Parris N. Glendening
Governor
"Transportation is both about mobility and about sustaining what is most
important: safe, prosperous communities where we can live, work and
raise families."
Parris N. Glendening
Governor
"Transportation and economic development form a symbiotic relationship.
Transportation connects products with consumers, workers with jobs and
businesses with each other."
Parris N. Glendening
Governor
Copies of the final Maryland Transportation Plan are available by
calling 410-865-1277; TTY 410-865-1342; toll free 888-713-1414.
You may also write for copies to:
MTP, Office of Planning and Capital Programing
Maryland Department of Transportation
P.O.Box 8755
BWI Airport, Maryland 21240
|
|