| Our Icosa Cabin Building | |||||||||||||||||||||||||||||||||||||||
| We started the building process on October 20, 2001. We hope to complete all of the major building in time for an after Christmas vacation. Clint has the top half of the roof to go, then we'll finish up with the woodstove. |
|||||||||||||||||||||||||||||||||||||||
| Our first weekend, October 20 &21 | |||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
| The third weekend, November 3 & 4, Mom and Dad came to visit and help. Dad and I finished putting up the outside walls and finished the windows. Clint finished the roof panels and worked on the trim. | |||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
| The second weekend , October 27 & 28, we completed the struts and 2pieces of roof and wall. | |||||||||||||||||||||||||||||||||||||||
| The fourth weekend, November 10 & 11, Clint sealed the roof and finished the roof supports while I painted the outside and sealed the inner and outer joint spaces. We also finished the door frame and cut the triangle windows. | |||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||
| To Be Continued | |||||||||||||||||||||||||||||||||||||||
| Contact Info: | |||||||||||||||||||||||||||||||||||||||
| Name: | Jodi Iker | ||||||||||||||||||||||||||||||||||||||
| Email: | |||||||||||||||||||||||||||||||||||||||
| [email protected] | |||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||