Duration of the Workshop: Action Plan.

Part I: Consultations, Drawings and Sketches                                              – 2 months .

Part II: Development of jigs, moulds patent and processing of raw materials  – 1 months.

Part III: Development and manufacture of Prototypes 10-12numbers            – 2 months

Part IV: Preparation of report and Documentation                                        – 1 month

                                                                                                            ———————

                                                                                                           Total : 6 Months

                                                                                                            ———————

 
     
 

Appendices - Annexure ‘E’

 
 
 
 
 

Manner of Implementation

(1) Process of selection of Artisans carried out with other partners and different cluster members of the AHVY/
     UNDP.

(2) Course Design of the Training Programme was developed in consultation with the consultant and Designer
      appointed for the programme.

(3) Classes on weaving –mat weaving, bag weaving , basket weaving etc . Basic technique of weaving started.

(4) Preparation of Artisans knowledgeable in carpentry work was made to complement /supplement with the
     Cane and Bamboo work.

(5) Operation/ use of tools and machineries taught to the Artisans.

(6) Calculation manner of full use of the raw materials classes was conducted.

(7) Simple technique/ process of pricing of the finished Products was taught to the Artisans.