23 OCT 2000
The footings were poured...
01 NOV 2000
The foundation was poured.
06 NOV 2000
Backfill of the foundation.
13 NOV 2000
Start of the framing
process.
25 NOV 2000
Picked out the tile for baths and the foyer.
27 NOV 2000
Framing of the second floor.
04 DEC 2000
Roof is on and windows are in.
11 DEC 2000
The basement was poured.
13 DEC 2000
Electrical "walk through" completed.
15 DEC 2000
The electrical fixtures were ALL picked out. (Almost within budget)
16 DEC 2000
Preliminary flooring done; carpet and kitchen flooring is picked out.
23 DEC 2000
The fireplace is in; stairs to the basement and
bathtubs, too!
30 DEC 2000
The insulation is in and the furnace is on.
03 JAN 2001
Drywall starts going up.
04 JAN 2001
Carpets and Linoleum final pick done.
08 JAN 2001
Alarm system prewire.
09 JAN 2001
Dad still worried about construction being on time.
?? FEB/MAR 2001
Anticipated completion of the house.
27 MAR 2001
CLOSING!!!!
|