  • Engineering, Installation, and Test Commissioning :
    • 900E1 Project Extension at 6 Sites DIVRE-2 Jakarta
    • Rungkut V5.2
    • STP National SDL Extension at 4 Sites
    • Trunk Toll at 2 Sites
    • Intelligent Network Partnership at 7 sites, 2001
  • Investigation, Re-Engineering and Installation of Grounding Systems at 9 Large Central Offices in Divre-2 Jakarta and 1 Central Office in Divre-1 Pakanbaru, 2004

 

  • High Power Amplifier Transmission Spare Part for Telkom – MSC at Cibinong, 2004 .

 

  • Repair Tools for Radio Base Station at Telkom-MSC Jakarta, 2004

 

  • Advance Operation and Maintenance Training for Lucent SDH Product Wavestar ADM16, TDM10G, for PT. Telkom at Central Ancol Jakarta, 2005

 

  • Repair Maintenance Contract for 3-years Nationwide for 5ESS modules, 2005

 

  • Investigation, Re-Engineering and Installation of Surge Arrester for 36,000 Customer Line at 4 Central Offices in Divre-2 Jakarta, 2005

 

  • Investigation, Re-Engineering and Installation of Grounding Systems at sites STO Cikampek, Divre-2 Jakarta. Grounding  grounding protection for equipment NEC Central Office (Neax), various DC Power plant, Various Transmission system, MDF and Mitra's BTSs. Existing Integrated Grounding System is to be re-engineered become Isolated Grounding System. Sept 2005

 

  • Investigation, Re-Engineering and Installation of Grounding Systems at sites STO Purwakarta, Divre-2 Jakarta. Grounding  grounding protection for equipment NEC Central Office (Neax), various DC Power plant, Various Transmission system, MDF and Mitra's BTSs. Existing Integrated Grounding System is to be re-engineered become Isolated Grounding System. Des-2005
 
 