Last weekend the Critter developed a problem with the electronic controller.  I sent out the part for warranty replacement, but meanwhile I started work on a 115-foot expansion of the main line.  It will include two straightaways, a bridge, and a run through a grove of trees.
8 DOWN, 4 TO GO - By Monday I had finished construction on 8 track panels out of a total of 12.  I have construction time down to 35 minutes including tie cutting. THE SOURCE OF THE FILL DIRT - Out in the main pasture there's a hill that I can smooth out, and the work is a lot easier with the tractor's front end loader!
PREPARING THE FILL - Using the tractor, I moved the fill dirt, flattened it out with the bucket, and compressed it by running the tractor over it.
BRIDGE SITE - between the two forked trees there is a low area.  This will be the site of an 8-foot girder bridge.  The track will run directly at the camera in this view.
BUILDING INSPECTOR - Piney is checking my work, making sure I used the right kind of fill, whether I spread it properly, and how well I tamped it down. ASSISTANT BUILDING INSPECTOR - Smokey is checking the dimensions of the concrete blocks that will be used for bridge abutments.
CHIEF BUILDING INSPECTOR - Charlotte is pointing to the revisions I have to make to pass inspection, namely a pair of turnouts and access to the original route. BUILDING SITE - Paul is riding over the site of the new turnout that Charlotte wants me to build.  He's riding in the last car so he can see the train's rocking motion.
SURVEY CONTINUED - From the culvert the line goes between the trees and back to the original line.  I guess we can call it the "Calvert Culvert."  Or, as Dick suggested, get a lot more culverts and call it the Culvert Central!
SURVEYOR'S MARKERS - The new line through the trees is all staked out, this angle from the bridge site.  In the distance is a pipe that Paul brought for a culvert.