Project Start Date: Sat 4/24/04
Project Finish Date: Tue 6/8/04
Resources and Assignments | Start | Finish | Work |
|---|---|---|---|
Unassigned | Mon 4/26/04 | Fri 4/30/04 | 0 hrs |
Meeting with the sponsor | Fri 4/30/04 | Fri 4/30/04 | 0 hrs |
Divide specific project tasks | Fri 4/30/04 | Fri 4/30/04 | 0 hrs |
Discuss current project plan | Mon 4/26/04 | Mon 4/26/04 | 0 hrs |
Discuss specific tasks | Mon 4/26/04 | Mon 4/26/04 | 0 hrs |
Meeting with sponsor | Wed 4/28/04 | Wed 4/28/04 | 0 hrs |
Heather | Mon 4/26/04 | Tue 6/8/04 | 622.67 hrs |
Select project | Mon 4/26/04 | Wed 4/28/04 | 18.67 hrs |
Select project manager | Wed 4/28/04 | Fri 4/30/04 | 16 hrs |
Create project plan | Mon 4/26/04 | Tue 5/4/04 | 56 hrs |
Kickoff meeting | Mon 4/26/04 | Mon 4/26/04 | 4 hrs |
Create team contract | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Set up website for the project | Mon 4/26/04 | Fri 5/7/04 | 80 hrs |
Obtain web location (URL) | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Lay out websites | Wed 4/28/04 | Fri 5/7/04 | 64 hrs |
Kickoff meeting | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Update schedule for project tasks | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Discuss current changes | Tue 4/27/04 | Tue 4/27/04 | 0 hrs |
Prepare status report | Mon 4/26/04 | Thu 5/13/04 | 112 hrs |
Status report 1 | Fri 5/14/04 | Fri 5/14/04 | 8 hrs |
Prepare status report | Mon 5/17/04 | Thu 6/3/04 | 112 hrs |
Status report 2 | Fri 6/4/04 | Fri 6/4/04 | 8 hrs |
Final presentation | Wed 5/26/04 | Tue 6/8/04 | 80 hrs |
Mahlet | Mon 4/26/04 | Fri 6/4/04 | 190.67 hrs |
Select project | Mon 4/26/04 | Wed 4/28/04 | 18.67 hrs |
Kickoff meeting | Mon 4/26/04 | Mon 4/26/04 | 4 hrs |
Create scope statement | Wed 4/28/04 | Fri 4/30/04 | 24 hrs |
Kickoff meeting | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Create milestone report | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Status report 1 | Fri 5/14/04 | Fri 5/14/04 | 8 hrs |
Status report 2 | Fri 6/4/04 | Fri 6/4/04 | 8 hrs |
Prepare final project report | Mon 4/26/04 | Tue 5/11/04 | 96 hrs |
Olivia | Mon 4/26/04 | Fri 6/4/04 | 230.67 hrs |
Select project | Mon 4/26/04 | Wed 4/28/04 | 18.67 hrs |
Kickoff meeting | Mon 4/26/04 | Mon 4/26/04 | 4 hrs |
Create project charter | Mon 5/3/04 | Wed 5/5/04 | 24 hrs |
Create WBS | Thu 5/6/04 | Fri 5/14/04 | 56 hrs |
Create Gantt chart | Mon 5/17/04 | Tue 5/18/04 | 16 hrs |
Kickoff meeting | Mon 4/26/04 | Tue 4/27/04 | 16 hrs |
Status report 1 | Fri 5/14/04 | Fri 5/14/04 | 8 hrs |
Status report 2 | Fri 6/4/04 | Fri 6/4/04 | 8 hrs |
Write lesson learned | Wed 5/12/04 | Tue 5/25/04 | 80 hrs |