Attention is also drawn table A2 which discusses the maintenance and replacement provisions. The most usual way of dealing with a project is to assume a life, and allow for maintenance, and for major replacements when they likely to occur, and finally bring in a positive value at the end representing the scrap value of the plant. In this case, however, it was easier to estimate an annual sum which could keep the plant fully competitive for ever. For ever sounds a long time: but in practice it would make virtually no difference if a life of, say, 50 years had been assumed.

 

Table A3 takes the investment costs of Table A1 and phases them over the two and a half year expected construction period.

 

Table A4 shows the time profile of the project bringing together investment costs and operating costs and benefits. The first two rows are taken from Table A2 and A3. The third row introduces the shadow wage rate at accounting prices was estimated. Assuming that unskilled labour would consume all its wages, and applying the standard conversion factor, consumption at world prices would be 62 ½ per cent of the actual wage. Thus where w is the actual wage, and  c consumption at accounting prices, we have c= 65.5/100  w. From the discussion it appeared that the shadow rate for Pakistan expressed as a percentage of c should be rather high, and so 80 per cent was chosen. The shadow wage is there fore equal to 8c/10, i,c ½ w. The figures of raw (3) of Table A4 are there fore half those of row (1). If anything, 50 per cent may be on the low side, because the standard conversion factor almost certainly underestimates the ratio of world to domestic prices for the typical family budget of an unskilled worker. However, it makes rather little difference to this project what shadow rate is chosen, because labour costs, especially in investment expenditures, are a small proportion of the total.

 

Row (4) of Table A4 is the array of social profits which must be discounted to find the present social value. Rather arbitrarily an ARI of 10 per cent was chosen in the belief that Pakistan’s investments ought to be yielding at least this much. The upshot is that the social present value is negative, minus Rs.18,063. In arriving at this final value, we discounted Year 1 by nothing, Year 2 by 10/11, Year 3 by (10/11)2, and so on. If expenditures and receipts are evenly  spread over the years, this in effect means that we have discounted to a point of time roughly six months ahead. No great distortion is likely to result from this, provided the same procedure is applied to all projects.

 

Since the present social value was negative at 10 per cent, the social internal rate of return was also calculated. This turned out to be 5.4 per cent. The private rate of return given a 100 per cent tariff, had been estimated to be 12.3 per cent.

 

Some reasons may wonder that no allowance has been made for external economies. In truth, we could think of no external economies except labour, and perhaps management, training, But, relative to other industrial projects these would probably be less than normal, partly because it is relatively capital-intensive so that the up-grading of unskilled labour is not large compared to the investment expenditure, and partly because the techniques are, simple, specialized, and standardized,  so that the practical engineering and administrative experience involved is unlikely to be at all catalytic.

 

Finally, there is the question of risk – the risk that our estimates are wrong. It is on balance clear that this is rather a low risk project. Since the techniques are long-established, and the consulting firm has vast experience of erecting such plants in many countries, including many developing countries, their predictions can be taken as being as accurate as any such are likely to be. We can only have erred on the side of optimism in accepting their view that the plant could operate continuously at 100 per cent capacity after two and a half years.

 

It is also clear that the supply and marketing risks are small: the most costly material input is domestically supplied, and the output is for a domestic market which would be assured if the plant were built. There is also rather unlikely to be any fall in the accounting price of the output, since rayon is a long established product with settled techniques and very unlikely to be superseded. The chief risk in our calculations is undoubtedly the price of cotton linters. As we know, the present accounting price assumed cannot have been too high, for if it were any higher the plant could operate on imported wood pulp. On the other hand, it is possible that wood pulp would get more costly over the years, so that the maximum price of cotton linters could rise, and make the assumed accounting price too low. As against this, it may be that now or in the future the alternative use value (for export) for cotton linter is less that $125 per ton. Since the project has negative present value at this price (at a 10 per cent rate of discount) it has to be, to give the project a positive present value at a 10 per cent discount rate. This calculation has been done, and the answer is that the price must be about 39 per cent lower, or about $76 per ton.

 

There is danger in calculating, as above, the value of an uncertain price which is just low or high enough to make the project viable (or definitely not viable). This is because it may set people arguing that this is the right price. But, bearing this in mind, it is quite a useful thing to do, because sometimes the price that would have to be assumed is plainly absurd.

 

1.- What do we conclude from this case study, is it acceptable or unacceptable with the information we have? Explain

 

Table A1. Investment costs

 

 

                                                          Value as    Accounting

                                                         Stated in values for goods unskilled

                ITEM                                   Project    and services     labour      The rest

                                                           Report       excluding  (actual value) (2)+(3)-(1)

                                                                        Unskilled labour

1.- Imported equipment                   22,000      22,000              ___           ___

2.- Duty on above                               4,975              __              ___        4,975

3.- Locally produced equipment       4,900        4,900              ___           ___

4.- Local labour, works and tools      1,200           120           1,080           ___

5.- Foreign labour during start-up        700           700              ___           ___

6.- Total cost of equipment              33,775      27,720           1,080        4,975

7.- Engineering services                    2,400        2,400              ___           ___

8.- Civil engineering and works      11,000        4,400           2,420        4,180

9.- Land                                                   150              94              ___              56

10.-Lighting and fire equipment           350           350              ___           ___

11.-Contingencies                                 500           367                 37              97

12.-Working capital                           4,100        2,378              164        1,558

13.- Management and overheads during start-up 1,500           938           ___      562

14.-Total investment cost                53,775      38,647           3,701      11,428

 

 

 

Table A2. One Year’s operating costs and receipts at 100 per cents (7,000 tons capacity)

 

                                                  Value as       Accounting                

                                                 Stated is  values for goods Unskilled Labour The rest

                                                   Project         & services       (actual value)

                                                   Report          excluding                  

                                                                   Unskilled Labour            

                                                        1                      2                         3                      4

1.- Cotton linters                         See                4,998                 ___                    ___

2.- Chlorine                                 note                      48                 ___                    ___

3.- Sodium bisulphate                  to                        17                 ___                    ___

4.- Sulphur                                   item                    870                 ___                    ___

5.- Chatcoat                                   6                        92                 ___                    ___

6.-Total of above                   13,019                 6,025                 ___                 6,994

7.- Caustic soda                      4,200                 2,939                 ___                 1,270

8.- Other materials                     630                    472                 ___                    158

9.- Filter materials                      315                    197                 ___                    118

10.- Packing materials              154                       96                 ___                       58

11.- Maintenance materials      385                    241                                            144

12.- Electricity                          1,803                 1,442                 433                     -72

13.- Steam                               1,740                    870                 ___                    870

14.- Technical and admve staff 445                    445                 ___                    ___

15.- Other labour                        570                    ___                 570                    ___

16.-  Overhead expenses          770                    480                 ___                    290

17.- Total ‘cost of production’ 24,031             13,195              1,003                 9,830

18.- Maintenance and replacement of                                                                            

      equipment                          3,378                 2,772                 108                    498

19.- Maintenance and replacement of                                                                            

      building                                  330                    132                    73                    125

20.- Total operating cost      27,739               16,102              1,184               10,453

21.- Total receipts                 36,492               18,957                 ___               17,535

22.- Net revenue                      8,753                 2,855             -1,184                 7,082

 

 

 

 

Table A3. The phasing of investment costs as in Table A1 over the 2 ½ year projected construction period

 

                                              1ST Year                    2nd Year                     3rd Year

                                            1       2       3             1          2       3             1          2       3

1.- Imported equipment 7,333 7,333 ___  14,667 14,667  ___        ___     ___  ___

2.- duty on above         1,800  ___  ___     3,175     ___  ___        ___     ___  ___

3.- Locally produced equipment 1,633 1,633 ___  3,267 3,267       ___     ___  ___   ___

4.- Local labour, works & tools 120 120        ___  1,080  ___     1,080     ___  ___   ___

5.- Foreign labour during start-up ___ ___    ___     ___  ___        ___     700  700   ___

6.- Total cost of equipment 10,886 9,086      ___ 22,189 17,934  1,080     700  700   ___

7.- Engineering services 200  200  ___     1,100  1,100  ___     1,000  1,100  ___

8.- Civil engineering & works 7,000 2,800  1,540  4,000 1,600       880     ___  ___   ___

9.- Land                           150     94  ___        ___     ___  ___        ___     ___  ___

10.- Lighting & fire equipment ___  ___        ___     250  250        ___     100  100   ___

11.- Contingencies         ___  ___  ___        250     183                 250     183  ___

12.- Working capital       ___  ___  ___     2,000  1,160     80     2,100  1,218     18

13.- Management and                                                                                                84

      overheads during start-up 200  125        ___     800  500           __     500  313   ___

14.- total investment cost 18,436 12,305    1,540 30,589 22,727  2,058  4,750 3,614  102

 

 

 

Table A4. Time profile of the project

 

                                                       Year 1             Year 3             Year 3      Year 4 and all

                                                                                                                     Subsequent years

1.- Labour – actual  value (sum of cols. 3                    

      of Table A2 and A3)              -1,540             -2,058                -694             -1,184

2.- Accounting values (sum of cols. 2 of                      

      Tables A2 and A3)              -12,305           -22,727             -2,187            +2,855

3.- Labour at shadow wage equal to 50                      

      per cent of actual wage (see text) -770        -1,029                -347                -592

4.- Total of rows (2) and (3)      -13,075           -23,756             -2,534            +2,263

Present value of row (4) at 10 per cent

discount                                       18,086

 

 

 

 

 

CASE 4.- Translate the following paper and answer the questions below.

Visual Basic

 

This is a brief introduction of what VB is, what it has been and an overview of its capabilities. Assuming you have a basic knowledge of Windows 95/98.

 

 

What is Visual Basic?

 

Visual Basic is one of the most powerful developing tools for Windows available today. Originally Visual Basic was called BASIC. Language designers in the 50's developed the BASIC language for beginning programmers. At the time, BASIC was easier to learn than other languages such as FORTRAN or COBOL. True to the originial, Visual Basic does not stray from its roots; new ones learning programming can still create simple Windows programs in a short while, with minimal knowledge. It is to be noted that Visual Basic's simplicity should not be translated as inability. Advanced applications can be made with Visual Basic and it supports various advanced programming techniques, with the exception of true multiple inheritance.

 

Why has BASIC gone Visual? The role of programming has changed over the decades along with the progress of hardware design. Languages today stray greatly from the languages of a few years ago. Before the advent of GUIs(Graphical User Interfaces), a programming language was just a simple text-based tool to construct programs. Presently you need much more than just a language that spits out text. You need a development tool that can take advantage of Window's emerging features, such as graphics, multimedia, online and multiprocessd activities. Visual Basic is more than a language in that it lets you interact with these aspects of the Windows environment and create GUIs easily.

 

The transition from BASIC to Visual Basic is noticable. There are many new features. VB has a compiler that creates standalone runtime .EXE files that execute more quickly than previous versions of VB. A compiler is an application that converts the instructions you write, into a language that the computer understands, so that you and others can use the application. This compiler is called Developer Studio and is also used with lower level languages such as Visual C++ and Visual J++. So, in taking this tutorial you not only learn the IDE(Integrated Development Environment) for VB, but also for other languages. Additionally, wizards have been added to the IDE to speed up the development of programs. Wizards are question and answer boxes that help you step-by-step in creating a custom application.

 

part2

Hosted by www.Geocities.ws

1