Project Schedule - CS240 - Fall 03

Myat Min, Mong-Hang Vo, and Pratik Dhupia

Project schedule is revised bi-weekly.

BI-WEEKLY ENDING 2003/11/27

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/10/06 (done)
Design Document 2003/10/20 (done)
Test plan Document 2003/11/17 (done)
Implementation 2003/12/03 (4 days)
Testing and Integration 2003/12/01 (1 week)
Final Project Presentation (Conclusion and Demo) 2003/12/08
Individual and Group Project Reports 2003/12/15 (2 weeks)


BI-WEEKLY ENDING 2003/11/13

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/10/06 (done)
Design Document 2003/10/20 (done)
Test plan Document 2003/11/13 (partial completed)
2003/11/17 (*****due*****)
Implementation 2003/11/24 (2.5 weeks)
Testing and Integration 2003/12/01 (1 week)
Individual Project Report 2003/12/05 (4 days)
Final Project Report and Presentation 2003/12/08


BI-WEEKLY ENDING 2003/10/30

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/10/06 (done)
Design Document 2003/10/20 (done)
Test plan Document 2003/11/17 (*****due*****)
Implementation 2003/11/24 (3.5 weeks)
Testing and Integration 2003/12/01 (1 week)
Individual Project Report 2003/12/05 (4 days)
Final Project Report and Presentation 2003/12/08


BI-WEEKLY ENDING 2003/10/16

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/10/06 (done)
Design documentation 2003/10/13 (almost done)
Implementation 2003/11/24 (5 weeks)
Test plan Document 2003/12/01 (1 week)
Testing and Integration 2003/12/01 (1 week)
Individual Project Report 2003/12/05 (4 days)
Project Deadline 2003/12/08


BI-WEEKLY ENDING 2003/10/02

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/10/06 (done)
Design documentation 2003/10/13 (1week)
Implementation 2003/11/24 (5 weeks)
Testing and Integration 2003/12/01 (2 weeks)
Project Deadline 2003/12/08


BI-WEEKLY ENDING 2003/09/18

Things to do Time to complete
Project Proposal 2003/09/22 (done)
Requirements Document 2003/09/27 (1 week)
Design documentation 2003/10/03 (1week)
Implementation 2003/11/24 (6 weeks)
Testing and Integration 2003/12/01 (2 weeks)
Project Deadline 2003/12/08

Clickable button Return to Main Page


@2003 CS240 Software Project Team
CS240 Fall 2003 - Section 1
San Jose State University
Email: [email protected]
Hosted by www.Geocities.ws

1 1 1