|
Base
Functional Component (BFC)
|
An
elementary unit of Functional User Requirements defined by and
used by an FSM Method for measurement purposes
|
|
base
practice
|
A
software engineering or management activity that addresses the
purpose of a particular process
|
|
base
practice
|
An engineering or management activity that addresses the
purpose of a particular process area and thus belongs to it.
[SPICE BPG 0.06] (adapted)
|
|
Baseline
|
A formally approved version of a configuration item,
regardless of media, formally designated and fixed at a specific
time during the configuration item's life cycle.
|
|
Baseline
|
As "configuration baseline" in ISO 10007. An SCI
controlled to provide the ability to change or to rebuild the
specific version at a later date.
|
|
baseline
|
A specification or product that has been formally reviewed
and agreed upon, that thereafter serves as the basis for further
development, and that can be changed only through formal change
control procedures [IEEE-STD-610].
|
|
baseline
|
(1) A specification or product that has been formally
reviewed and agreed upon, that thereafter serves as the basis
for further development, and that can be changed only through
formal change control procedures. A document or a set of such
documents formally designated and fixed at a specific time
during the life cycle of a configuration item. Any agreement or
result designated and fixed at a given time, from which changes
require justification and approval. [IEEE STD 610.12-1990]
|
|
baseline
|
A specification or product that has been formally reviewed
and agreed upon, that thereafter serves as the basis for further
development, and that can be changed only through formal change
control procedures. [IEEE-STD- 610]
|
|
baseline
configuration management
|
The establishment of baselines that are formally reviewed and
agreed on and serve as the basis for further development. Some
software work products, e.g., the software design and the code,
should have baselines established at predetermined points, and a
rigorous change control process should be applied these items.
These baselines provide control and stability when interacting
with the customer. (See also baseline management.)
|
|
Baseline
Finish Date
|
See scheduled finish date.
|
|
Baseline
function point count
|
See Application function point count.
|
|
baseline
management
|
In configuration management, the application of technical and
administrative direction to designate the documents and changes
to those documents that formally identify and establish
baselines at specific times during the life cycle of a
configuration item. [IEEE-STD-610]
|
|
Baseline
Start Date
|
See scheduled start date.
|
|
behaviour
|
how the whole or part of the system acts and reacts
|
|
benchmark
|
A standard against which measurements or comparisons can be
made. [IEEE-STD-610]
|
|
Benchmarking
|
Process of determining a metric baseline for an
organisational or functional unit for the purposes of
comparison.
|
|
BFC
Type
|
a defined category of BFCs
|
|
bidder
|
An individual, partnership, corporation, or association that
has submitted a proposal and is a candidate to be awarded a
contract to design, develop, and/or manufacture one or more
products.
|
|
bottom-up
|
Pertaining to a method or procedure that starts at the lowest
level of abstraction and proceeds towards the highest level.
|
|
boundary
|
a conceptual interface between the software under study and
its users
|
|
Boundary
|
The application boundary is the conceptual interface between
the software under study and its users. Where the users are any
person or any thing that communicates or interacts with the
software.
|
|
Budget
|
A planned sequence of expenditures over time with monetary
costs assigned to specific tasks or jobs. Often used also to
refer to work effort as well as, or instead of, money.
|
|
Budget
At Completion (BAC)
|
The estimated total cost of the project when done.
|
|
Budget
Estimate
|
See estimate.
|
|
Budgeted
Cost of Work Performed (BCWP)
|
The sum of the approved cost estimates (including any
overhead allocation) for activities (or portions of activities)
completed during a given period (usually project-to-date). See
also earned value.
|
|
Budgeted
Cost of Work Scheduled (BCWS)
|
The sum of the approved cost estimates (including any
overhead allocation) for activities (or portions of activities)
scheduled to be performed during a given period (usually
project-to-date). See also earned value.
|
|
Build
|
Physical Design / Internal Design / Coding / Programming /
Package Customisation / Interfaces
|
|
build
|
An operational version of a system or component that
incorporates a specified subset of the capabilities that the
final product will provide. [IEEE STD 610.12-1990]
|
|
business
process
|
a partially ordered set of enterprise activities that can be
executed to realise a given objective of an enterprise or a part
of an enterprise to achieve some desired end-result
|